c.
W$LF CREEK
- NUCLEAR OPERATING CORPORATION
.l Bart D. Withers Preskient end April 8, 1992 Chief Executive 0+heer i
VM 92-0050 U. S. Nuclear Regulatory Comm!ssion
. ATTN: Document Control Desk Mail Station F1-137 Vashington, D. C.
20555
Reference:
- 1) Letter WM 92-0002 dated January 6, 1992 from B. D. Vithers, WCNOC, to R. D. Martin, NRC
- 2) Letter NO 92-0010 dated January 15, 1992 from J. A. Bailey, WCNOC to the NRC
Subject:
Docket No. 50-482:
Revised Schedule for Completion of Commitments Gentlemen:
The purpon of thie letter is to provide a revised schedule for the completion of actions committed to in the references.
The revised schedule is primarily due to an unscheduled outage that began on February 19._
1992 and continued:through March 27, 1992. The resources necessary to meet these L
commitmente were required in support of -the unscheduled _ outage.
The L
extension of these cornmitments was discussed between Mr.
S.
G.
- Wideman, p
Supervi'sor Licensing and Mr. G. A. Pick, Senior Resident Inspector, NRC on March 30, 1992.
Reference 1 committed to review and implement enhancements to the operability determination process byP ch 31, 1992.
Various Wolf Creek Nuclear Operating Corporation (WCNOC.
disciplines have.
reviewed-the available guidance on nonconforming conditions and operability and
- determined the need ti enhance the entire process.
Due to this expanded scope. and the unscheduled outage, the effort will be completed by May 29, 1992.
4 Reference 2 transmitted a License Event Report 91-017-01 concerning a Fuel Building /Auxi'iary Building pressure boundary door found open without a continuous' watch having been established. As part of the corrective actions y
~ associated with this event, WCNOC committed to evaluate and implement _any l-
< additional long-term programmatic enhancements by March 31, _ 1992.
An administrative procedure has. been drafted which provides the necessary.
controls for doors utilized to prevent a breach in a fire barrier, fire zone L
- barrier, pressure boundary or security barrier.
The reviews of the l
procedure are in process and will be completed by April 30.-1992.
9204140!57 "2t%O8 PDR ADOCK 05000482
\\
P PDR P0. Box 411 ! Ourhngtog KS 66839 i Phone: (316) 364 8831 Ih An Equal opportundy Employer M F HCArf f
g 1
.= 4 e+
n
+
\\M'92-0050 Page 2 s
If you have any questions concerning this matter, please contact me or Mr. S. G. Videman of my 4taff.
Very truly yours, I
Bart D. Withers President and Chief ' Executive Officer BDWlaem cc:
A. T. Howell (NRC)
R. D. Martin (NRC)
G. A. Pick (NRC)
W. D. Reckley (NRC)