I JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE
SUMMARY
OF OPERATIONS June, 1984 There were no unit shutdowns or significant power reductions during the month of June. On May 25, 1984, the IC steam generator atmospheric relief valve lifted four times within a half hour period. A thorough investigation revealed no cause for this event and the valve wa6 returned to service. No further occurrences have been noted.
The following major safety-related maintenance was performed in the month of June:
1.
Performed miset11aneous corrective and preventive maintenance on diesel generators.
2.
Replaced bearings on 1C diesel generator.
3.
Replaced #4 river water pump.
4.
Replaced steam generator level transmitter LT-495.
wim7amh
+
,p
'i c:
50-348 gm pg, UNg7 1
July 3, 1984 DATE COMPLETED SY J D Woodard l
l TELEPHONE /W R49-5156 une, 1980 MONT11 DAY AVERACE DAILY F0WER LEVIL DAY
- AVERACE DAILY POWER LEVEL (MWe Net)
(MWe NetI 825 807 g,
g7 2
820 gg 806 815 3
gy 30s 801 4
813 j
811 3
aos
~
809 809 g
g 8I3 7
807 23 8
All 3
810
[
t 9
811 25-811 822 f
10 Ai1 3
810 817 i
3g g
12 RDA 3
all b
805 13 g,3 14 30 815 l
796 L
l$
807 3g
.i 806 16 1
^
\\
245TRUCTIONS On this formar. list the avenge daily umt power levelin MWe Net for each day in the reporting munih. Campute to
, the nearest whole ne;: wait.
7 I
4 a
(997) 4 G
R
I OPERATING DATA REPORT DOCKET NO. 50-148 DATE Julv 3.
1984 COMPLETED BY T D. k'codard TELEPHONE (205)899-5156 OPERATING STATUS
- 1. Unit Name:
Joseph M. Farley - Unit 1 Notes
- 2. Reporting Period:
. Tim e. 1984
- 1) Cumulative data since
- 3. Licensed Thermal Power iMWtp:
2652 12-1-77, date of 860 comnercial operation.
- 4. Nameplate Rating (Gross MWep:
629 S. Design Electrical Rating (Net MWel:
- 6. Maximum Dependable Capacity (Gross MWe):
AA1 R
- 7. Maximum Dependable Capacity (Net MWe):
797.I
- 8. If Changes Occur in Capacity Ratings titems Number 3 Through 7) Since Last Report. Give Reasc.is:
v/A (Net MWe):
N/A
- 9. Power Level To Which Restricted,if Any /A
- 10. Reasons For Restrictions,if Any:
N This Month Yr..to Date Cumulatise
- 11. Hours in Reporting Period 720 4.367 57,695
- 12. Number Of Hours Reactor Was Critical 79n.n 7.58A.8 37,712.0
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 3,650.0
- 14. Hours Generator On.Line 720.0 2,504.0 16.607.4 l$. Unit Reserve Shutdown Hours 0.0 0.0 0.0 I6. Cross Thermal Energy Generated (MWH) 1,908,735 6.201.318 92.302.844
- 17. Gross Electrical Energy Generated (MWH) 616,540 1,990,512 29,313,522
- 18. Net Electrical Energy Generated (MWH)
MR1 Ana 1,861,096 27,562,158
- 19. Unit Sersice Factor 100.0
- sy_,
63.4
- 20. Unit Availability Factor 100.0 57.1 63.4
- 21. Unit Capacity Factor (Using MDC Net) 101.7 53,5
$g,9
- 22. Unit Capacity FactorIUning DER Net) 97*7 51.4 57.6
- 23. Unit Forced Outage Rate nn 1.1 14.6
- 24. Shutdowns Scheduled Oser Next 6 Months IType. Date.and Duration of Each):
N/A
- 23. If Shut Down At End Of Report Period. Estimated Date of Startup:
N/A
- 26. Units in Test Status iPrior eo Commercial Operationi:
Forecast Achiesed t
INITI A L CRITICALITY 8-6-77 8-9-77 INITIAL ELECTRICITY 8-20-77 8-18-77 C0\\lMERCI AL OPER ATION 19_ i _ r 7 i_3,,,7f (9/77 J
r~
~
'7
\\
~
50-348 UNIT 54M11 DOWNS AND POWER REDUCTIONS DOCKET NO. T.T. Farley - Unit I~
UNIT NAME.
~
DAIE July 3, 1984 COMPLETEp gy J. D. Woodard REPORT MONilf June, 1984 TEl.1;Pif0NE (205) 899-5156 "k
Llocnsee E-r, k
Cause & Connective Eg
}
h Ek g 'g No.
Ibse
(
- E g 2sE Evene g7 6.
Atti m to
$E E
j;f5g Repent
- g mO O
Prevent Recussence 6
6 l
THE LE WERE N O IJ KIT SN GTDOWhS OR SIGNIFICANT POWE1 REDUCT1 0NS DURINC THE MONTH OF JUNE.
I i
i l
2 3
4 F: Fueced Reasins:
Methid:
Exliibit G -Instructiims S: Scheduled A Equipnient Failwe(Emplain)
I-Manual for Peeravatiim inf D.ana B Maintenance v.iTest 2 Manual Scram.
Entey Sheets for I.kensee C-Refueling
- 3. Automatic Sciam.
Esent Repine II.[Ril~ite t NtlREG-D Regulatiny Restikti m 4-Delice (E mplain) 0161)
E4)peratur Training A license Enamination F-Administnative 5
G Operathmal L
,e (Eng4ain)
I shibis I Same S. mice l's/77) ll Oshet (Engdain)
V s
Mailing Address Atbama Power Comp ny 600 North 18th Street r
Post Office Box 2641 Telephone 205 783-6090 R. P. Mcdonald Senior Vice President-F ntridge Bu din d!3b3W3lDWCf v.<..
,,,r.,w.. -
July 9, 1984 Docket No. 50-348 Director, Office of Management Information and Program Control U. S. Nuclear Regulatory Comission Washington, D.C.
20555
Dear Sir:
RE: Joseph M. Farley Nuclear Plant Unit 1 Monthly Operating Data Report Attached are two (2) copies of the June 1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 1, required by Section 6.9.1.10 of Appendix A of the Technical Specifications. As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a
" Narrative Sumary of Operating Experience" is included in the attached report.
If you have any questions, please advise.
Yours very trul,
I s
J R. P. Mcdonald RPM /KWM: sam Enclosures xc: Mr. Ted Cintula (1 copy)
Director, IE (10 copies)
Director, RII (1 copy) d*
e bc:.Mr. J. M. Farl:y Mr. W. O. Whitt Mr. R. P. Mcdonald Mr. H. O. Thrash Mr. W. G. Hairston, III Mr. L. S. Williams Mr. T. H. Nesbit Mr. J. D. Woodard Mr. A. E. Hammett Mr. M. L. Stoltz Ms. S. N. Knight Mr. J. M. Elliott Mr. J. R. Crane Mr. B. E. Hunt Mr. L. B. Long Mr. N. M. Horsley Ms. Sylvia Schoel Mr. J. C. Miller INPO Records Center ANI Library File: Binder Copy A-2.1 i