Forwards Hydrogen Control Program Plan for Perry Nuclear Power Plant, in Support of Full Power Ol.Plan Updates Earlier Info Submitted in Response to FSAR Question 480.40, as Discussed W/Nrc During 840619 Meeting
ML20090H854
Person / Time
Site: Perry  
Issue date: 07/19/1984
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: Youngblood B
Office of Nuclear Reactor Regulation
Shared Package
ML20090H857 List:
References
NUDOCS 8407270236
Download: ML20090H854 (2)


Text

0 o

" $J r pi tt*

!c > (4 -

~)

s 1 e yn C*

L ('2" O,: p 1'

I d( L ULL t.

I

'1

(

L i ' 1 e el L4 sv P.o. box 5000 - CLEVELAND. oHlo 44101 - TELEPHONE (216) 622-9800 - ILLUMINATING DLDG-

- 55 PUsLICSoVARE Serving The Best Location in the Nation MURRAY R. EDELMAN VICE PRESIDENT NUCLEAR July 19, 1984 PY-CEI/NRR-0122 L Mr. B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555 Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Hydrogen Control Program Plan

Dear Mr. Youngblood:

The Cleveland Electric Illuminating Company (CEI) has been involved in a comprehensive program to resolve the degraded core hydrogen control issue, in order to support a full power operating license for Perry Nuclear Power Plant.

Attached is a detailed description of the program CEI has undertaken to resolve the hydrogen control issue.

The program plan updates earlier information submitted in response to FSAR Question 480.40, and was discussed with members of the NRC staff during a meeting on June 19, 1984.

Due to the complex nature of the hydrogen control licensing issue, a significant amount of analyses, testing and design activities requiring several diverse fields of expertise is required to assure an adequate resolution.

A significant amount of work has been completed by CEI and the liydrogen Control Owners Group (HCOG) to resolve the hydrogen control issue for a Mark III containment.

CEI has been and intends to remain an active member of IICOG and is committed to resolution of the issue.

The attached Program Plan is intended to provide a management guide to the program activities completed, ongoing and planned to resolve the hydrogen control issue.

The program is aimed at addressing the significant issues raised by the NRC Staff during their review of the Grand Gulf Nuclear Station (GGNS) liydrogen Ignition System and the llCOG activities. A significant portioet of the program includes resolution of generic issues through HCOG activities.

We feel that including meneric activities to the maximum exteitt possible and addressing applicable issues previously identified during the review cf Grand Gulf Nuclear Station in cur program plan will utilize the NRC Staff's and our resources in the most expeditous manner.

8407270236 040719 PDR ADOCK G5000

^

p 9

i 1

Mr. B. J. Youngblood July 19, 1984 Again, I would like to take this opportunity to assure you that CEI is committed to resolving the hydrogen control issue in an expeditous manner to support full power licensing of the Perry Nuclear Power Plant.

Very truly yours, iM [Y Murray R.

delman Vice President Nuclear Group MRE:nje Attachment ec: Jay Silberg Esq.

John Stefano J. Grobe i

9 4

9

.