ML20090H684

From kanterella
Jump to navigation Jump to search
Monitoring of Electric Power to Reactor Protection Sys for Vermont Yankee Nuclear Power Station, Technical Evaluation Rept
ML20090H684
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 03/16/1984
From: Selan J
LAWRENCE LIVERMORE NATIONAL LABORATORY
To:
NRC
Shared Package
ML20090H687 List:
References
CON-FIN-A-0250, CON-FIN-A-250 UCID-20036, NUDOCS 8404180234
Download: ML20090H684 (10)


Text

- _____ . _ _ _ _ _ __

j 5 #

.s l

.c ,

e. '.. .

~ . _

e s .. .

9. . - x

. s UCID- 20036 4

.4

=a 3 ,

n',."

,6_ y

'w' .

n W',,

a ,

1, r

g g

'i. .

. h=

,. 1

~; - - -

, s i

g.

m g ,v s

4.

,- , . .q- 1..u t ,s w -

., , ~,

, r f . 1t j

^ '

-s j

"' l

[ TECHNICAL EVALUATION REPORT'ON THE $

~

~;?J' r 1HONITORING O'F ELECTRIC POWER

' " TO THE REACTOR . PROTECTION SYSTEM FOR'THE -

VERMONT YANKEE NUCLEAR: POWER. STATION -

.1 .

i, .

~

u- . ,.

~.a .

~

,. c b '.' .

3 Docked No. 50-271) ' '

..- .- .,=.z. q ,

[."!:s l

2m

, , , s s

    • ..a

. i 's < % ,'n....; +., 9, ,v cj k , ' ' ,'

4

? ' % , ,c%A , g' ~.. '>.' . s WJ.ames C.: Selan- i

.f*6 d

, ,2, , . . - , . ,,

.- .> . . " ,.L..8

  • Ay. (! #
  • rei .7 * , - )

wp 2, .-e ,.x-*

rw.

{

i

  • , *r a

, 4.

)

, c r

c. , ; 3,. +4 i*

s

.=

.<: ca- , .

p , =,- ,

- a e- -

c;;, ,

1 -%..

> ,< v

, , . -. ,, .>.ae . , :s-., gg;7 , ,

w, \ .g s ,

u : * -r . .-, , - ,

m. -

/ w. ' e yn [. .  ; &  ;.  ; v.

.. At'

~' }  ; .gf . 'y ,, " ' v

g 1 Q ." ,i'+. ]  ? ' '

..pt .

+.. ~

~  : . .'.

-d.,

.s- .. .- ,

a s . m..  :, ,

u

,-~- .

.. _ ,'~ . . . . .. . , > - - ^

i s

- March 16, 1984- ~

Ai s. :....... ** #

L

\

^* # .

i.J 2

  • k s.

, ,<  %. M ; :l;g^R-Q;., . _ .;Q: -

q:h +* .. ., 4[ 4.'~ ..

ht.:.+G4jG ';@Q@h g ,"*;^f.l.$. mf'#l.y;;y$:;fR$

~

-4s .

aMGQf ' . 6

% ~'

i Th3s is an informal report intended primar9y for internal or lisaited external distribution.

y > h' '

The opinions and conclusions stated are those of tM author sad may or may not be those D^8 5 of ths Laboratory.

)N g, '

This work was supported by the United States Nuclear Reguistory Commission under

' ^* a s Mrmorandum of Understanding with the United States P:g:- --t of Energy.

js NRC FIN No. A-0250 ,

4 2

W T

O I

"***sm.

l(h

'N

])llfO?> " f -

u,(

, 4

', ABSTRACT This report documents the technical evaluation of the monitoring of electric power to the reactor protection system (RPS) at the Vermont Yankee

, Nuclear Power Station. The evaluation is to determine if the proposed design modification will protect the RPS f rom abnormal voltage and frequency conditions which could be supplied from the power supplies and will meet certain require-ments set forth ',y the Nuclear Regulatory Commission.

The proposed design modifications will protect the RPS from sustained abnormal voltage and frequency conditions from the supplying sources.

FOREWORD

=

1 This report is supplied as part of the Selected Operating Reactor Issues Program II being conducted for the U. S. Nuclear Regulatory Commission, Office of Nuclear Reactor Regulation, Division of Licensing, by Lawrence Livermore National Laboratory.

The U. S. Nuclear Regulatory Commission funded the work under the authorization entitled " Selected Operating Reactor Issues Program II,"

B&R 20 19 10 11 1, FIN No. A-0250.

D .

i n

l L

r-l 1

1 l

TABLE OF CONTENTS  !

Page

1. INTRODUCTION . . . . . . . . . . . . . . . 1
2. DESIGN DESCRIPTION . . . . . . . . . . . . . 2
3. EVALUATION . . . . . . . . . . . . . . . 3 4 CONCLUSION . . . . . . . . . . . . . . 5 REFERENCES . . . . . . . . . . . . . . . . 6 n.

)

b

-111-1 i

r TECHNICAL EVALU/. TION REPORT ON THE MONITORING OF ELECTRIC POWER TO THE REACTOR PROTECTION SYSTEM AT THE VERMONT YANKEE NUCLEAR POWER STATION (Docket No. 50-271)

James C. Selan Lawrence Livermore National Laboratory, Nevada

1. INTRODUCTION During the operating license review for Hatch 2, the Nuclear Regulatory Commission (NRC) staff raised a concern about the capability of the Class lE reactor protection system (RPS) to operate af ter suffering sustained, abnormal voltage or frequency conditions from a non-Class 1E power supply. Abnormal voltage or frequency ceeditions could be produced as a result of one of the following causes: combinations of undetected, random single failures of the power supply components, or multiple failures of the power supply components caused by external phenomena such as a seismic event.

The concern for the RPS power supply integrity is generic to all General Electric (GE) boiling water reactors (BWR) MARK 3's, MARK 4's, and MARK 5's and ell BWR MARK 6's that have not elected to use the solid state RPS design. .a staff therefore pursued a generic resolution. Accordingly, CE proposed a revised design, in conceptual form, for resolution of this concern [Ref. 1). The proposed modification consists of the addition of two Class 1E " protective packages" in series between each RPS motor generator (M-G) set and it's respective RPS bus, and the addition of two similar packages in series in the alternate power source circuit to the RPS buses.

Each protective package would include a breaker and associated overvoltage, undervoltage and underfrequency relaying. Each protective package would meet the testability requirements for Class 1E equipment.

With the protective packages installed, _any abnormal output type failure (undetectable random or seismically caused) in either of the two RPS y M-G sets (or the alternate supply) would result in a trip of either one or both of the two Class lE protective packages. This tripping would interrupt the power to the effected RPS channel, thus producing a scram signal on that channel, while retaining full scram capability by means of the other channel.

-Thus, fully redundant Class 1E protection is provided, bringing the overall n.

1 l

l I

l RPS design into full conformance with General Design Criteria (GDC)-2 [Ref. 2],

and CDC-21 [Ref. 3] (including IEEE-279 [Ref. 4] and the standard review plan i

[Ref. 5]). The NRC staff reviewed the proposed GE design and concluded that the modification was acceptable [Ref. 6], and should be implemented in conform-ance with the applicable criteria for Class lE systems.

The NRC requires that the components of the RPS not be exposed to unacceptable electric power of any sustained abnormal quality that could damage the RPS. This involves providing means to detect any overvoltage, undervoltage, or underfrequency condition that is outside the design limits of the RPS equipment and to disconnect the RPS from such abnormal electric power before damage to the RPS can occur. The equipment which performs these functions must satisfy the single failure criterion and be seismically qualified.

The NRC issued a generic letter [Ref. 7] to all operating BWR's requesting the licensees to submit design modification details and Technical Specifications for post implementation review.

By letters dated January 27,1981 [Ref. 8], February 25, 1983 [Ref. 9],

Augus t 5, 1983[Ref. 10], and December 14, 1983 [Ref. 11], Vermont Yankee Nuclear Power Corporation (VYNPC), the licensee, submitted design modification details regarding the monitoring of electrical power to the RPS at the Vermont Yankee Nuclear Power Station.

The purpose of this report is to evaluate the licensee's submittal with respect to the NRC criteria and present the reviewer's conclusion on the adequacy of the design modifications to protect the RPS from abnormal voltage and frcquency conditions.

2. DESIGN DESCRIPTION The licensee has installed the GE designed " electrical protection assembly" (GE No. 914E175) to monitor the electric power in each of the three sources of power (RPS M-G sets A and B, and the alternate source) to the RPS.

Each assembly (EPA) consists of two identical and redundant packages. Each package includes a circuit breaker and a monitoring module. When abnormal electric power is detected by either module, the respective circuit breaker will trip and disconncet the RPS f rom the abnormal power source.

The me.nitoring module detects overvoltage, undervoltage, and underfrequency conditions and provides a time-delayed trip when a setpoint is exceeded.

3. EVALUATION The NRC stated several requirements that the licensee must meet in their design modification to monitor the power to the RPS. A statement of these requirements followed by an evaluation of the licensee 's submittals is as follows:

(1) "The components of the RPS shall not be exposed to unaccept-able electric power of any susteined abnormal quality that could damage the RPS. "

The monitoring module will detect overvoltage, undervoltage, and underfrequency conditions with the following interim setpoints.

Nominal voltage 120 volts, 60 Hz nominal Condition Setpoint Time Delay Ove rvolt age < 126 volts < 4 seconds Undervoltage > 111 volts < 4 seconds Underfrequency > 57 Hz < 4 seconds In a telecon dated November 28, 1983 [Ref. 12], the fol-lowing additional information on the selection of the trip setpoints was provided by the licensee.

The present setpoints of the installed monitoring packages are: overvoltage of 129 volts, undervoltage of 108 volts, and underfrequency of 57.5 Hz. The time delay for each setpoint is < 4 seconds. The selection of these setpoints are justified based on a low line voltage drop for the 115 volt rated components (Ref. 11]. Since the Vernont Yankee Station utilizes both 115-volt and 120-volt rated components, the selection of the setpoints must consider both the components ' capabilities and the bandwidth for plant operation. Therefore, the present setpoints will be in effect until the next scheduled refueling outage (planned e for June,1984), at which time they will be changed to those listed above. These interim setpoints are based on a con-servatively assumed line voltage drop of 3 volts. These

, new setpointo will be procedurally administered until a more extensive study on the voltage requirements, to opti-mize the setpoints, is completed. This study is planned for completion in late 1984 with a subsequent Technical Speci-fication change request' in February 1985 [Ref.11].

The above chosen new setpoints allowing for an assumed line voltage drop of 3 volts will limit the voltage variation at the RPS components to be within the capabilities certified by CE of + 10% of the 115 volt and 120 volt ratings.

(2) " Disconnecting the RPS f rom the abnormal power source shall be automatic. "

The monitoring module will automatically disconnect the RPS buses from the abnormal power supply af ter the set time delay should the parameters setpoints be exceeded.

(3) "The power monitoring system shall meet the requirements of IEEE 279-1971, GDC-2 and CDC-21."

The monitoring packages meet the Class IE requirements of IEEE 279, the single f ailure criteria of GDC-21, and the seismic qualifications of GDC-2.

(4) " Technical Specifications shall include limiting conditions of operation, surveillance requirements, and trip setpoints."

The above protective setpoints are applicable only for an interim period and will be controlled administratively until-the more extensive analysis is ,gompleted and the setpoints optimized. During this interim period, the output of the RPS powar supplies will be checked on a once per shif t basis in accordance with the NRC Generic letter dated August 7,1978

{Ref. 13]. Formal Technical Specification changes will be submitted upon completion of the analysis.

The Technical Specifications submitted in Reference 10 were not, in part, in conformance with the model Standard Technical Specifications. Specifically, they did not include a 6 month functional test, the setpoints and time delays, the alternate source in the LCOs, and the 30 minute time limit in the LCOs for restoring at least one of two inoperable protective panels to an operable status. The licensee is required to commit to the conformance with the Standard Technical Specification requireme nts.

l o , ,__

4 CONCLUSION Based on the information submitted by Vermont Yankee Nuclear Power Corporation for the Vermont Yankee Nuclear Power Station, it is concluded that:

(1) Considering the assumed line voltage drop to be conservative, the proposed interim setpoints of the relays in the two pro-tective packages installed in series, in each of the power sources to the RPS buses, will automatically protect the RPS components from sustained abnormal overvoltage, undervoltage, and underf requency conditions outside the design limits of the RPS components.

(2) The protective packages meet the requirements of Class 1E equipment (IEEE 279), single failure criteria (GDC-21), and seismic qualification (GDC-2).

(3) The proposed time ' delay before circuit breaker tripping will not result in damage to components of the RPS or prevent the RPS from performing its safety functions.

(4) The installation of the Class 1E protective packages with the chosen setpoints in each of the non-Class 1E power supplies is better than the existing non-Class 1E monitoring system.

(5) The continuation of the surveillance program of once per shif t on the output of the RPS supplies in conjunction lth the admin-istratively controlled interim setpoints is a satisfactory interim surveillance until the finalization of the required Technical Specifications.

(6) The licensee is required to commit to the conformance with the model Stannard Technical Specification requirements.

Accordingly, I recommend that the NRC accept the interim setpoints which will be under administrative control, in conjunction with the additional surveillance program for protecting the RPS components for abnormal power, until such time that the additional analysis to optimize the setpoints is completed and formal Technical Specifications are submitted in accordance with the model Standard Technical Specifications.

3 l

l REFERENCES l

1. General Electric Company letter, MFN 408-78 (G. G. Sherwood) to NRC (R. S. Boyd), dated October 31, 1978.
2. General Design Criteria-2 (GDC-2), " Design Bases for Protection Against Natural Phenomena," of Appendix A, " General Design Criteria for Nucicar Power Plants," in the Code of Federal Regulations, Title 10, Part 50 (10 CFR 50).
3. General Design Criteria-21 (GDC-21), " Protection System Reliability and Testability," of Appendix A, " General Design Criteria for Nuclear Power Plants,' in the Code of Federal Regulations, Title 10, Part 50 (10 CFR 50).

4 IEEE Std. 279-1971, " Criteria for Protection Systens for Nuclear Power Generating Stations."

5. NUREG -75/087, " Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants."
6. NRC memorandum f rom Faust Rosa to J. Stolz, T. Ippolito, and G. Lainas, dated February 19, 1979. ~
7. NRC letter to Operating BWR's, dated September 24, 1980.
8. VYNPC letter (L. H. Heider) to th NRC (T. A. Ippolito), dated Janua ry 27, 1981.
9. VYNPC letter (J. B. Sinclair) tc the NRC (D. B. Vassallo), dated Februar/ 25, 1983.

10 VYNPC letter (L. H. Heider) to toe NRC (D. G. Eisenhut), dated Augus t 5, 1983.

11. VYNPC letter (J. B. Sinclair) to the NRC (D. B. Vassallo), dated December 14, 1983.
12. Telephone conference, J. Sinclair, P. Johnson, D. Reese, R. Padogin, and B. Wansick (VYNPC), V. Rooney and J. Donohew (NRC), and J. Selan (LLNL), dated November 28, 1983.
13. NRC letter (T. A. Ippolito) to VYNPC, dated August 7, 1978.

~-

.. ^ ,

U ,

DISCLAlkdER

' His doenaame was peepared as an account of wwk sponsored by an agency of the Umked States Goveressent.

Neister the Uniend States Goverumsat mer the University of Californie per any of their empierees, makes any warranty, empress er W er assumes any legal liehoisy or s , ' , for the accarecy, cem-pisesseme, er easedmass of any ' " . apparatus, praduct, er process discleesd, or represamts that its

' use would met ladrange privessly sumed righam. Referesse herein te any speciSc commercial products, process,

= service by trade ammm, tredamerk, e, w scherwiu, dose act _ ;, cousaksee w haply hs

, er fevering by the Uniend States Government er the Umi,ersity of California.

, he ,6ese and epimimms of smakere empressed herois de met necessarSy sense er renset these of the United

s. Semene Gewsment -

thoveef,*

and shmN mot be uset fw adentising w predmet endereement perpenas. -

,, - , , . - s ' n, . -

., , I _

s' a>

a; - R ,

-, y y -

.s'

'r i.'

. - ~

. .( ,3.. - .' .

e, f . .s,

, .E , i, '

s 3,1 . , .',)

-s . ,

,,.s ,. e.:'s ,

f. '

L.  ;; c ' >

t

'n .,. - . 4 ;,..,

, f > 'l ; , 'r. ~. '

4, a y y, ,

.23-

.( (,,,-t w s s W'.-%

-< 3 .<4 * * ..

4' *' -

pieense se she Uniese sesessef Asess4ca . y , -

w yy sp lo 4 . c ., . , ww %% <

+

u

' o < , ;l , , p . , nW

-" ., t

.1 . ,j U.1 Dayeremsee of Ceenamerce '.

', 9 c , 3 ; .-

3 gagg g ,g,y.g3.,g '

ej .p r;.y ynm, a - e .

, *n s.

+

i

~,, ~ "

' Prke Pneese Cayy 8 a heicreache Sue ,

s .

- P

  • 3',; , . n, '<

-jg, '

Deussede * * 'I h

,g ' A, ,7 ..a<'

' ' ' Dessentic '

. - [ Page Range [ Price , Page Range ' ' Price r, '

, y',, : ( 0t1-025 - S* '7.00 1 ( , 326 380,

$ 26.50

.,. 036 050 a 8.50 ; 381 375

> 20.00

, , 051-075 10.00 ;376-400 29.50 076 100 , 11.50 i 401-426 "'

"

  • 31.00

~ 101-125 13.00 427-450 ;

  • 32.5G '

<. 126-150. . 14.50 - 451-475 34.00

  • C. j 151-175 16.00 476-500 > 35.50

- 176-200 17.50 501-525 37.00

' 201-225 '

19.00 ' 526 550 30.50 226-250 20.50 551-575 40.30

. 251-275' 22.00 ~576-600 41.50 276-300 ' 23.50 601-up'

, 301-325 +

25.00 .. . .

" Add 1.50 for each additional 25 page incrennent , or portio n

, thereof from 601 pages up. -

4 1

s a

h

_ _ _ - _ _ _ _ - _ _