Tennessee Valley Authority, Sequoyah Nuclear Plant, P.O. Box 2000, Soddy Daisy, Tennessee 37384 March 30, 2020 10CFR50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Subject:
Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation
References:
- 1. Safety Evaluation Report Related to the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application, dated January 29, 2015 (ML14329A635) 2.
NUREG-2181, "Safety Evaluation Report Related to the License Renewal of Sequoyah Nuclear Plant Units 1 and 2," dated July 31, 2015 (ML15187A206) 3.
NUREG-2181, Supplement 1, "Safety Evaluation Report Related to the License Renewal of Sequoyah Nuclear Plant Units 1 and 2," dated September 30, 2015 (ML15259A332) 4.
Issuance of Renewed Facility Operating Licenses Numbers DPR-77 and DPR-79 for Sequoyah Nuclear Plant, Units 1 and 2, dated September 25, 2015 (ML15097A454)
Pursuant to Sequoyah NuclearPlant (SQN) Unit 1 Renewed Facility Operating License Condition 2.0(31) and SQN Unit 2 Renewed Facility Operating License Condition 2.0(24),
which were issued per Reference 4, the Tennessee Valley Authority (TVA) confirms that SQN Units 1 and 2 new programs and enhancements to existing programs of References 2 and 3, required to be implemented no laterthan March 17, 2020, for Unit 1 and March 15, 2021, for Unit 2 are complete. The designated inspection and testing activities, as noted inAppendix A of Reference 1, required to be completed no later than March 17, 2020, for Unit 1 and March 15, 2021,for Unit 2 are complete. Certain license renewal programs and activities described in the Updated Final Safety Analysis Report have been changedas allowed bySQN Units 1 and 2 LicenseConditions 2.C.(31)(a) and 2.C.(24)(a), respectively.
printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 March 30, 2020 There are no regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact Mr. Jeffrey Sowa, Site Licensing Manager, at (423) 843-8129.
Respectfully, Matthew Rasmussen Site 'lice President Sequoyah Nuclear Plant cc:
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant