Notifies That Amend 5 to FSAR Will Not Be Submitted Before May 1984.Tabulation of FSAR Commitments for Mar 1984 & Corresponding Resolution for Each Commitment Encl
ML20088A548
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 04/02/1984
From: Mittl R
Public Service Enterprise Group
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 8404120188
Download: ML20088A548 (5)


Text

.

0 IgS1 Cm Company Putmc service E Eatoc and Gas 80 Park PLua, Newark, NJ 07101/ 201430 8217 MAILING ADDRESS / P.O. Box 570, Newark, NJ 07101 Robert L. Mitti General Mana<f tr Nuclear Assurance and Regulation April 2, 1984 Director of Nuclear Reactor Regulation U.S.

Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20014 1

Attention:

Mr. Albert Schwencer, Chief l

Licensing Branch 2 l

Division of Licensing l

Gentlemen:

HOPE CREEK GENERATING STATION DOCKET NO. 50-354 PSAR COMMITMENT STATUS THROUGH MARCH 1984 1

Public Service Electric and Gas Company presently does not plan to issue Amendment No. S to the Hope Creek Goncrating Station Final Safety Analysis Report before May 1984.

Accordingly, this letter is provided to document the ststus ot Hope Creek Generating Station responses to NRC requests i

for additional information which were forecanted to be responded to'by March 1984.

Attached is a tabulation of the Hope Creek Generating Station Final Safety Analysis Report commitments for March 1984 and the corresponding resolution for each commitment.

Should you have any questions in this regard, do not hesitate to contact us.

Very truly yours, i

l h?'///

8404120188 840402 PDR ADOCK 05000354 A

PDR The Energy People g

OS 4312 (4M) 7 M

O Director of Nuclear 2

4/2/84 Reactor Regulation C

D.

H. Wagner (w/ attach.)

USNRC Licensing Project Manager Mr.

W.

H. Bateman (w/ attach.)

USNRC Senior Resident Inspector AD02 1/2

o 7

~

  • ~

~

Page 1 of 3 a

^

ATTACHMENT i

Hose CREEK GENERATING STATION-

~$

FSAR COMMITMENT-STATUS THROUGH MARCH 1984 FSAR COMMITMENT 1

LOCATION

~

COMMITMENT RESOLUTION 1.

Question / Response This commitment concerns Appendix:

qualification of NSSS essen-Question 271.1 tial electrical components and -instruments." A requali-fication program is in J

progress to upgrade qualifi-cation-to NUREG-0588.

The qual-ification information required in Table 3.10-3 will be provided in June 1985.

j 2.

Question / Response This commitment concerns

~

Appendix:

submittal of additional i

Question 460.5 information to address TMI task action Item III.D.l.l.

d This informatiori will be j

included in,FSAR Section e

1.10, Item III.D.l.~1 in Amendment 5 to the HCGS FSAR.

a i

3.

Supplemental Requests This commitment concerns two 4

Appendix:

items:

1) subtaittal of a SRAI (5) partial status cummary list of all safety related equip-i ment, and 2) submittal of i

information rhquired to i

demonstrate the ability of the containment. purge and.

vent talves to close during a DBA.

The partial status summary-list is being transmitted under separate cover.

SRAI

. (5) will be revised ~in Amend-ment 5 to reference ~ this transmittal.

4 A descript1ori of. the qualifi-cation of the fcontainment purge anduvent valves will be included in. Amendment 5 to the HCGS FSAR.-

t j

i.

.7.,

,.s I~

m 4

~

~

Page 2 of 3 FSAR COMMITMENT LOCATION COMMITMENT RESOLUTION 4.

Section 9.3.2.6 This commitment concerns submittal of information describing the methods uti-i lized for verifying dissolved i

oxygen concentration in reactor coolant.

This infor-mation will be provided in Amendment 5 to the HCGS FSAR.

5.

Question / Response This commitment concerns Appendix:

submittal of the Preservice Question 250.1 Inspection Program Plan for 1

NRC review.

The Preservice Inspection Program Plan is being transmitted under separate cover.

Question j

250.1 response will be revised in Amendment 5 to reference this transmittal.

6.

Question / Response This commitment concerns Appendix:

identification of the spent Question 281.13 fuel rack materials and a description of the spent fuel rack design details.

This information will be provided in Amendment 5 to the HCGS FSAR.

7.

Question / Response This commitment concerns Appendix:

submittal of information to Question 640.9 demonstrate the adequacy of drainage to preclude flooding l

upon automatic sprinkler i

actuation.

This information will be provided in May 1984.

8.

Question / Response This commitment concerns Appendix:

submittal of a figure which Question 410.69 shows the protection of the station service water system l

3 from the floodwater (includ-j ing wave effects) of the design basis flood.

This information will be provided in Amendment 5 to the HCGS FSAR.

4 Page 3 of 3 I

f FSAR COMMITMENT LOCATION COMMITMENT RESOLUTION 9.

Question / Response These commitments concern Appendix:

diesel generator design, Questions 430.22 testing, operating condi-430.83 tions, and auxiliary sys-430.108 tems.

This information will 430.109 be provided in May 1984.

430.131 430.135 430.136 430.138 430.145 l

10. Question / Response This commitmnt concerns the Appendix addition of drain lines to j

Question 440.21 the LPCI system shown on l

Figure 5.4-13.

This figure will be revised in May 1984.

DD:db 4/3/84 OT 01 01/03-A