ML20087Q012

From kanterella
Jump to navigation Jump to search
Responds to 810529 Request for Quarterly Progress Repts. Fuel Load Scheduled for 840423.Extension of Schedule Will Allow Addl Time for Internal Review & Approval of Test Results
ML20087Q012
Person / Time
Site: Callaway Ameren icon.png
Issue date: 04/03/1984
From: Cornelius W
UNION ELECTRIC CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
ULNRC-784, NUDOCS 8404100206
Download: ML20087Q012 (1)


Text

- _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

UNION ELECTRIC COMPANY 1901 GRATeof STREET-ST. Louis w.a. corn.UU.

MAsuMG ADDRE..t April 3, 1984

.r. CoUi.5=*o'.'."....

Mr. Harold R..Denton, Director Office of Nuclear Reactor Regulation

'U.S.

Nuclear Regulatory Commission Washington, D.C.

20555 ULNRC-784

Dear Mr. Denton:

DOCKET NUMBER 50-483 CALLAWAY PLANT, UNIT 1 QUARTERLY PROGRESS UPDATE

Reference:

ULNRC-712 dated December 30, 1983 This is a quarterly follow-up response to your letter of May 29, 1981 regarding progress of our Callaway Plant.

On February 28, 1984 Union Electric announced a new date for commencement of fuel load operations.

The unit should be ready for fuel load on April 23, 1984 rather than April 2.

This extension of the schedule will allow additional time for internal review and approval of test results, review of test results by NRC, completion and/or close-out of items required for fuel load, and_ coordination of final activities associated with processing of the operating license.

Our schedule for commercial operation remains unchanged and is late 1984 or early 1985.

Sincerely,

/Q LQ 8404100206 840403 PDR ADOCK 05000483 A

pg

)