Text
- 7_'
l n1sconsin Electnc maca couessy 231 W. MICHIGAN, P.O. BOX 2046. MILWAUKEE. WI 53201 March 30, 1984 Mr. H.
R.
Denton, Director Office of Nuclear Reactor Regulation U.
S. NUCLEAR REGULATORY COMMISSION Washington, D. C.
20555 Attention:
Mr. J.
R. Miller, Chief Operating Reactors, Branch 3 Gentlemen:
DOCKET NOS. 50-266 AND 50-301 UPGRADED EMERGENCY OPERATING PROCEDURES POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 In Section 7 of our letters dated April 15 and August 24, 1983, Wisconsin Electric provided a description and schedule for implementation of our upgraded Emergency Operating Procedures (EOP's).
Those submittals were in response to Mr. D. G.
Eisenhut's letter dated December 17, 1982, Generic Letter 82-33 entitled
" Supplement 1 to NUREG-0737 Requirements for Emergency Response Capability".
As you know, we are using Revision 1 to the Westinghouse Owners Group (WOG) Emergency Response Guidelines (ERG's) to upgrade our-EOP's.
At'the time of the August 24 letter, we had expected Westinghouse to issue Revision 1 to the WOG members late in August 1983.
It was not, however, issued to WOG members until November 16, 1983-Also, distribution of the last of the background material needed to revise the EOP,'s has been delayed three months from December 30, 1983 and is now scheduled to be sent out by the
~
WOG on March 30, 1984.
This three-month delay is resulting in a similar delay in the completion of the EOP writing effort which has been extended from February 1984 to May 1984.
However, by reworking the EOP. verification, approval, and training schedule, the final implementation of the EOP's will be delayed only one 4
month, until January 1985.
This assumes that the upgraded EOP verification and approval can be completed by August 1984 and that EOP validation and training will be completed by December j
1984.
. 8404100199 840330 8
4 PDR ADOCK 05000266
'{i_
F PDR f
5 Mr.
H.-R.
Denton March 30, 1984 Our August 24 letter also committed to submitting a procedures generation package in_ April-1984.
This submittal will
.lua delayed one month to May 1984.
This will ensure it is submitted at least three months prior to training on the new EOP's as
. required :in Supplement 1_ to NUREG-0737.-
We will continue to do all we can to_ implement the upgraded EOP's in'an acceptable and timely manner.
Should you wish to discuss this matter further, please contact us.
Very truly-yours,
}/
7 Vice Pr sid nt-Nuclear Power C.
W.- Fay
. Copy to NRC Resident Inspector 3-
-