ML20087K534
| ML20087K534 | |
| Person / Time | |
|---|---|
| Site: | Satsop, Washington Public Power Supply System |
| Issue date: | 03/13/1984 |
| From: | Sorensen G WASHINGTON PUBLIC POWER SUPPLY SYSTEM |
| To: | Dircks W NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO) |
| References | |
| G1-84-69, GO1-84-0069, GO1-84-69, GO5-84-38, NUDOCS 8403260221 | |
| Download: ML20087K534 (1) | |
Text
_ _ _ _ _ _.
Washington Public Power Supply System j-3000GeorgeWashingtonWay P.O. Box 968 Richland, Washington 99352-0968 (509)372-5000 Docket Nos. 50-509 50-513 l
March 13,1984 G01-84-0069 & G05-84-38 Mr. William J. Dircks Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Dircks:
Subject:
SUPPLY SYSTEM NUCLEAR PROJECTS 4 AND 5 TRANSITION TO PHASE II 0F TERMINATION
Reference:
Letter, R. L. Ferguson to W. J. Dircks, " Termination of Supply System Nuclear Projects 4 and 5 (WNP-4 and WNP-5)," February 1,1982.
The referenced correspondence discussed the Supply System's Termination Program to dispose of the assets of WNP-4/5. Phase I of the Program was to concentrate on finding new owners for the projects.
If the search for new owners proved to be unsuccessful, the Supply System was to move to Phase II, which would focus on the sale of plant assets in a piecemeal fashion.
/
This letter is 'to infom you that the Supply System is now in Phase II of the Temination Program for WNP-4/5.
It is our intent that Phase II will last until at least June,1985.
If you have any questions, please do not hesitate to call me at (509) 372-5238.
Sincerely,
{
ne '=y
/
G. C. Sorensen, Manager Regulatory Programs CVH/kd el
'/d
$$0300 0
p A
)