ML20087K373

From kanterella
Jump to navigation Jump to search
Informs of Start Failure Delay Relay SFD-2 Failure to Operate within Required Time Period on 750409,during Annual 3D Emergency Diesel Insp.Schedule Being Developed to Exercise & Check Relays for Reliable Operation
ML20087K373
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/28/1975
From: Burstein S
WISCONSIN ELECTRIC POWER CO.
To: Rusche B
Office of Nuclear Reactor Regulation
References
NUDOCS 8403260135
Download: ML20087K373 (2)


Text

.

p x

00 (v s I

I Wisconsin Electnc POWER COMPANY 231 WEST MICHIGAN, MILWAUKEE, WISCONSIN 53201 April 28, 1975 9

Mr. Benard C. Rusche, Dire'ctor Office of Nuclear Reactor Regulation

' gMk U.

S. NUCLEAR REGULATORY COMMISSION

/

[

Washington, D. C.

20555

Dear Mr. Rusche:

DOCKET NOS. 50-266 AND 50-301 INFORMATION REPORT ON FAILURE OF DIESEL RELAY POINT BEACH NUCLEAR PLANT The event recorded bel'ow does not constitute an abnormal occurrence as described in Section 15.1.a of the Point Beach Nuclear Plant Technical Specifications, nor is it a 30-day reportable item as described by Section 15.6.6.3 of the Technical Specifications.

This report is filed for informational purposes.

On April 9, 1975, during the annual 3D emergency diesel inspection, a start failure delay relay, SFD-2, failed to operate within its required time period when tested.

The relay operated in approximately one minute thirty-nine seconds versus.the normal time of approximately four seconds.

The relay operated satisfactorily upon immediate retest, was cleaned, and again satisfactorily retested.

The function of the diesel start circuit start failure delay relays is to time out after four seconds, and if the primary diesel starting circuit has failed to bring the diesel speed to over 100 rpm within the four-second period, it shuts down the primary starting circuit and shifts to the secondary starting circuit.

Full details of pneumatic relay and the diesel starting logic can be found in the manuals of the Square "D" Company, Class 9050 Series pneumatic relays and the Electro-Motive Division (General Motors) electrical drawing 8413730, respectively.

k COPY gr REGION _

O m

PDR

~1-YW4 m _ w

- _ _ ~

O o'

Mr. Benard'C. Ruscha April 28, 1975 Since the test of the No. 1 starting circuit start failure delay relay, SPF-1, performed just prior to SPD-2 test was satisfactory and since all previous tests of these relays have been satisfactory, the SFD-2 relay failure is not considered to be generic in nature.

As a precautionary measure, however, a schedule will be developed to exercise and check the relays for reliable operation on a semi-annual basis rather than the present annual schedule.

Since the inability of the start failure delay relays to shift to the redundant start circuit presumes a double failure (and more so as th'e diesel is itself redundant), and since as an additional back-up manual start of the diesel was available, the. failure of the SFD-2 start failure delay relay to operate within the required interval posed no health or safety ha=ard to the public.

Very truly yours, 3

Ex,ecu ive Vice President' Sol Burstein Copy to Mr. James G. Keppler - Region III m