ML20087F868
ML20087F868 | |
Person / Time | |
---|---|
Site: | Summer, Seabrook, 05000000 |
Issue date: | 03/08/1984 |
From: | Moriarty J COLT INDUSTRIES, INC. |
To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
References | |
REF-PT21-84-165-000 PT21-84-165, PT21-84-165-000, NUDOCS 8403190248 | |
Download: ML20087F868 (1) | |
Category:DEFICIENCY REPORTS (PER 10CFR50.55E & PART 21)
MONTHYEARML20216J4191999-09-24024 September 1999
[Table view]Part 21 Rept Re 990806 Abb K-Line Breaker Defect After Repair.Vendor Notified of Shunt Trip Wiring Problem & Agreed to Modify Procedure for Refurbishment of Breakers ML20206H2971999-05-0505 May 1999 Part 21 Rept Re Common Mode Failure for magne-blast Breakers.Vc Summer Nuclear Station Utilizes These Breakers in Many Applications,Including 7.2-kV EDG Electrical Buses RC-99-0087, Part 21 Interim Rept (SSH 99-0001) Re 990218 Failure of Circuit Breaker Located in Cubicle 14 of XSW1DB to Close During Surveillance Testing.Caused by Positive Interlock Angle Was Incorrect.Breaker Was Returned to GE Factory1999-04-15015 April 1999 Part 21 Interim Rept (SSH 99-0001) Re 990218 Failure of Circuit Breaker Located in Cubicle 14 of XSW1DB to Close During Surveillance Testing.Caused by Positive Interlock Angle Was Incorrect.Breaker Was Returned to GE Factory ML18106B0931999-02-25025 February 1999 Part 21 Rept Re Possible Defect in Swagelok Pipe Fitting Tee,Part Number SS-6-T.Caused by Crack Due to Improper Location of Heated Bar.Only One Part Out of 7396 Pieces in Forging Lot Was Found to Be Cracked.Affected Util,Notified ML18106B0551999-02-0101 February 1999 Part 21 Rept Re Possible Matl Defect in Swagelok Pipe Fitting Tee,Part Number SS-6-T.Defect Is Crack in Center of Forging.Analysis of Part Is Continuing & Further Details Will Be Provided IAW Ncr Timetables.Drawing of Part,Encl ML18106B0441999-01-29029 January 1999 Part 21 Rept Re Possible Defect in Swagelok Pipe Fitting Tee Part Number SS-6-T.Caused by Crack in Center of Forging. Continuing Analysis of Part & Will Provide Details in Acoordance with NRC Timetables RC-98-0076, Final Part 21 Rept Re a DG EG-B for Vsns,As Followup to .Power Control Svcs of Engine Sys,Inc Provided Response on 980318.Evaluation Concludes That Failure of EG-B Is one-time non-repeatable Failure1998-04-17017 April 1998 Final Part 21 Rept Re a DG EG-B for Vsns,As Followup to .Power Control Svcs of Engine Sys,Inc Provided Response on 980318.Evaluation Concludes That Failure of EG-B Is one-time non-repeatable Failure ML20212H1421998-03-0202 March 1998 Interim Part 21 Rept SSH 98-002 Re EG-B Unit That Was Sent to Power Control Svcs for Determination of Instability & Refurbishment of a Dg.Cause of Speed Oscillations Unknown. Completed Hot Bore Checks on Power Case ML20199E6391998-01-28028 January 1998 Part 21 Rept Re Failure of EG-A Control Serial Number 1425251 on 980109.Engine System Incorporated Has Been Notified of Situation & Understands That Part 21 Notification Being Submitted Based on Coc RC-97-0253, Follow-up Part 21 Rept SSH 960004 Re Defect Determined Not to Be Potentially Associated W/Substantial Safety Hazard (Ssh).Westinghouse Determined That SSH Reportable Under 10CFR21 Does Not Exist Based on Listed Info1997-12-15015 December 1997 Follow-up Part 21 Rept SSH 960004 Re Defect Determined Not to Be Potentially Associated W/Substantial Safety Hazard (Ssh).Westinghouse Determined That SSH Reportable Under 10CFR21 Does Not Exist Based on Listed Info ML17309A6211997-09-29029 September 1997 Part 21 Rept Re Final Disposition of Masterflow 713 & Embeco 636 Grout Nonconformance Reported by Master Builders,Inc. Licensee Continuing to Monitor shelf-life of Masterflow 713 & Embeco 636 Grouts Produced at Rancho Cucamonga ML20133E8001997-01-0808 January 1997 Deficiency Rept Re Nonconformance Related to Masterflow 713 Grout,Which Master Builders,Inc Has Supplied as Nuclear SR Product to 18 Npps.Cause Unknown.Requests That Listed Info Be Provided to Gain Insight as to Scope & Possible Cause ML20138Q2791996-12-13013 December 1996 Part 21 Rept Re Notification on Model 763 Wire Failures.Itt Barton Presently Investigating Understanding of Situation & Intends to Identify Suitable Repair,Can Be Implemented in Field ML20134L1681996-07-31031 July 1996 Part 21 Rept Re Failure of Itt Barton Model 763 Pressure Transmitters.Itt Barton Has Not Established Root Cause But Is in Process of Evaluating Failure ML20115F7081996-07-15015 July 1996 Part 21 Rept Re Failures of Abb/Ite 27N Relays.Abb Has Not Established Root Cause for What Appears to Be Repetitive Failure of U5 Timer RC-96-0157, Part 21 Rept Re Nozzle Weld Defects in Chemical & Vol Control Sys Connections at RCP Seal Injection Nozzles & Ccws Connections at RCP Thermal Barrier Heat Exchanger Inlet & Outlet Nozzles Supplied by W1996-06-17017 June 1996 Part 21 Rept Re Nozzle Weld Defects in Chemical & Vol Control Sys Connections at RCP Seal Injection Nozzles & Ccws Connections at RCP Thermal Barrier Heat Exchanger Inlet & Outlet Nozzles Supplied by W ML20116C9811996-05-20020 May 1996 Part 21 Rept Re Defective Welds Originally Specified & Performed by W on Component Cooling Water Nozzles for RCP Seal Injection Lines RC-95-0040, Interim Part 21 Rept (SSH 940002) Re Failure of 27N Degraded Voltage Relay Mfg by Asea Brown Boveri1995-02-15015 February 1995 Interim Part 21 Rept (SSH 940002) Re Failure of 27N Degraded Voltage Relay Mfg by Asea Brown Boveri RC-94-0308, Interim Part 21 Rept (SSH 940002) Re Failure of 27N Degraded Voltage Relay.Degraded Voltage Relay Returned to Mfg for Further Evaluation & Repair.Sc&G Expects to Complete Evaluation of 10CFR21 Reportability by 9502171994-12-0202 December 1994 Interim Part 21 Rept (SSH 940002) Re Failure of 27N Degraded Voltage Relay.Degraded Voltage Relay Returned to Mfg for Further Evaluation & Repair.Sc&G Expects to Complete Evaluation of 10CFR21 Reportability by 950217 RC-93-0251, Follow-up to 930521 Interim Part 21 Rept SSH 930003 Re Spare Model D26 Type M Relays Mfg by Cutler-Hammer & Supplied by Vitro Corp.All Affected Relays in storage,35 Rejected & Will Not Be Used in Any in-plant Application1993-09-28028 September 1993 Follow-up to 930521 Interim Part 21 Rept SSH 930003 Re Spare Model D26 Type M Relays Mfg by Cutler-Hammer & Supplied by Vitro Corp.All Affected Relays in storage,35 Rejected & Will Not Be Used in Any in-plant Application ML20046C6611993-08-0505 August 1993 Follow-up to 930226 Interim Part 21 Rept.Part 21 Evaluations for Reportability for Nonconformances Ncn 452 & Ncn 4555 Completed W/Determination That Neither Nonconformance Reportable ML20046C3251993-07-28028 July 1993 Part 21 Rept Re Failure of 27N Undervoltage Relay Mfg by Asea Brown Boveri.Subsequent Evaluation by Licensee, Folowing Insp by Vendor,Determined Item Not Reportable,Per 10CFR21 ML20044G3161993-05-25025 May 1993 Interim Part 21 Rept Re Failure of 27N Undervoltage Relay Discovered During Bench Testing Performed Prior to Installation.Relay Returned to Mfg for Repair.Relay Replaced ML20044E7531993-05-21021 May 1993 Interim Part 21 Rept SSH 930003 Re Three Defective Spare Model D26MR31A Type M Relays Mfg by Cutler-Hammer & Supplied by Automation Ind/Vitro Labs.All Vitro Supplied C-H Relays Placed on Hold & Two Relays Sent Off Site for Evaluation ML20126J5961992-12-31031 December 1992 Part 21 Rept Re Potential Loss of RHR Cooling During Nozzle Dam Removal.Nozzle Dams May Create Trapped Air Column Behind Cold Leg Nozzle Dam.Mod to Nozzle Dams Currently Underway. Ltrs to Affected Utils Encl ML20125C7161992-12-0707 December 1992 Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils Encl ML20127P5861992-11-23023 November 1992 Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl ML20118B4391992-09-11011 September 1992 Part 21 Rept Re Degradation in Abb Type 27N Undervoltage Relays Used in Electrical Switchgear.Recommends That Users Review Applications Requiring Exposures Greater than 1E03 Rads TID W/Time Delay Function Option ML20102B1211992-07-10010 July 1992 Part 21 Rept Re 911107 C Feedwater Isolation Valve Actuator Failure Due to Defect in Poppet Seal.Seal Replaced & Testing by Independent Lab Being Performed to Determine Physical Properties of Original Poppet Seals ML20087B3211992-01-0606 January 1992 Part 21 Rept Re C Feedwater Isolation Valve Actuator Failure During Testing.Caused by Poppet Seal in Control Valve Assembly.New Design Poppet Seal Extensively Tested & Placed Into Svc,Resolving Problem ML20081F6091991-04-23023 April 1991 Part 21 Rept Re Edward Controlled Closure Check Valves & Testable Piston Check Valves Dashplate Bolt Failures Due to Rapid Valve Opening or Impulsive Differential Pressure Surge Across Dashplate.Design Changes Recommended ML20058F4791990-10-30030 October 1990 Part 21 Rept Re Design of Chilled Water Sys & Postulated Seismic Events Leading to Rupture of Nonsafety Piping ML20012A9011990-02-27027 February 1990 Suppls 900213 10CFR21 Rept Re Chilled Water Sys Operation. Evaluation of Crystal River Determined That Postulated High Energy Line Break in Intermediate Bldg May Be Subj to Steam Loads Higher than Normal Loads,Causing Rising Water Temp ML20011F5971990-02-22022 February 1990 Part 21 Rept Re Solder Connections in Abb 27/59 Relays Deteriorated Due to Thermal Stress,Causing Bonding of Printed Wiring Pattern to Glass Epoxy Circuit Board.Interim Circuit Board W/Larger Pads & Higher Wattage Will Be Used ML20011F1941990-02-22022 February 1990 Part 21 Rept Re Abb 27/59 Relay Catalog Series 211L.Solder Connections to Printed Wiring Runs on Bottom of Circuit Board Deteriorated Due to Thermal Stress.No Actual Failure Occurred & Relays to Be Changed at Next Outage ML20011E8411990-02-13013 February 1990 Part 21 Rept Re Possible Rise in Chiller Water Temp When Svc Water Flow Valve Opened to Increase Flow.Initially Reported on 900209.Revised Guidelines Issued for Min Chiller Load Operation by Selectively Isolating Cooling Coils ML18153C1011990-02-0202 February 1990 Part 21 Rept Re Two of Three Pc Cards in GE Type SLV11A1 Over/Undervoltage Relays Failing to Produce Output.Short Between Leads Would Result in Damage to Component 1C5. Sketch of Threshold Detection Board Encl ML17223A7451990-01-26026 January 1990 Part 21 Rept Re Backup Rings Furnished in Spare Parts Seal Kits & in 25 Gpm 4 Way Valves as Part of Actuators Made of Incorrect Matl.Rings Should Be Viton & Have Been Identified as Buna N ML20005G6831990-01-0505 January 1990 Part 21 Rept Re Installation Instructions for Grommet Use Range for Patel Conduit Seal P/N 841206.Conduit Seals in Environ Qualification Applications Inspected for Proper Wire Use Range & Grommets Replaced ML19325E0861989-10-16016 October 1989 Followup Part 21 Rept Re Class 1E Battery Chargers W/ Transformers Running at Temps Exceeding Those Used in Qualification Rept When Operating at or Near Full Load Rating of Equipment.Listed Corrective Actions Underway ML19351A2941989-10-0909 October 1989 Part 21 Rept Re Potential of Ambient Compensated Molded Case Circuit Breakers to Deviate from Published Info. Instantaneous Trip Check Will Be Instituted on All Class 1E Thermal/Magnetic Ambient Breakers Prior to Shipment ML19325C9521989-09-29029 September 1989 Part 21 Rept Re Potential Common Failure of SMB-000 & SMB-00 Cam Type Torque Switches Supplied Prior to 1981 & 1976. Vendor Recommends That Switch W/Fiber Spacer Be Replaced ML20248E0121989-09-13013 September 1989 Supplemental Part 21 Rept Re Potential Problem W/Six Specific Engine Control Devices in Air Start,Lube Oil, Jacket Water & Crankcase Sys.Initially Reported on 890429. California Controls Co Will Redesign Valve Seating ML20245K2411989-08-11011 August 1989 Part 21 Rept Re Error in Design of Nonsafety,Nonseismic Portion of Svc Water Pump House HVAC Sys.Situation Will Be Reviewed & Determined to Be Unique to Mod for Plant.Training Will Be Conducted Re Consideration of Flood Paths ML20246P7111989-07-17017 July 1989 Part 21 Rept Re Quench Cracks in Bar of A-SA-193 Grade B7 Component.Quench Cracks Found in One Bar of Matl.Listed Purchasers Informed of Potential Defect.Next Rept Will Be Submitted When Addl Info Becomes Available ML20247D3011989-07-12012 July 1989 Part 21 Rept 10CFR21-0047 Re Control Wiring Insulation of Inner Jacket Used on General Motors Diesel Generator Sets Identified as 999 or MP Series.Encl List of Owners of Units Notified ML20246C0881989-06-21021 June 1989 Potential Significant Deficiency Rept Re Possibility That Atmospheric Dump Valves May Fail to Open.Caused by High Bonnet Pressure Not Permitting Actuator to Open Valve.Plug Should Be Reworked to Enlarge Pilot Flow Area ML20245B6651989-06-15015 June 1989 Part 21 Rept 150 Re Potential Defect in Component of Dsr Standby Diesel Generator.Cause of Failure Determined to Be Combination of Insufficient Lubrication to Bushings.Listed Course of Action Recommended at Next Scheduled Engine Maint ML20246K7401989-04-26026 April 1989 Part 21 Rept Re Incorrectly Stamped Name Plates on Certain Asco Nuclear Qualified Valves.Vendor Will Contact Each Affected Facility & Furnish Correctly Stamped Plates & in Near Future Discontinue Sale of Rebuild Kits for Valves ML20244D8161989-04-13013 April 1989 Part 21 Rept Re Failure of Rosemount Transmitters.All Failed Transmitters Replaced,Inservice Test Procedure Prepared & Monthly Test of All 12 Transmitters in RCS Throughout Cycle 2 Operation Will Be Performed.Review Continuing 1999-09-24 Category:TEXT-SAFETY REPORT MONTHYEARML20217D6401999-10-31031 October 1999
[Table view]Rev 2 to WCAP-15102, VC Summer Unit 1 Heatup & Cooldown Limit Curves for Normal Operation RC-99-0202, Monthly Operating Rept for Sept 1999 for VC Summer Nuclear Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for VC Summer Nuclear Station.With ML20217H2841999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Seabrook Station. with ML20216J4191999-09-24024 September 1999 Part 21 Rept Re 990806 Abb K-Line Breaker Defect After Repair.Vendor Notified of Shunt Trip Wiring Problem & Agreed to Modify Procedure for Refurbishment of Breakers ML20212D1461999-09-17017 September 1999 SER Accepting Request to Use Proposed Alternative to Certain Weld Repair Requirements in ASME Boiling & Pressure Vessel Code RC-99-0180, Special Rept on 990807,electric Driven Fire Pump XPP0134A Was Declared Inoperable.Caused by Pump Discharge Relief Valve Failing to Open as Normally Expected.Two Temporary Fire Pumps Were Installed to Provide Backup Suppression1999-09-0808 September 1999 Special Rept on 990807,electric Driven Fire Pump XPP0134A Was Declared Inoperable.Caused by Pump Discharge Relief Valve Failing to Open as Normally Expected.Two Temporary Fire Pumps Were Installed to Provide Backup Suppression ML20216F5141999-08-31031 August 1999 Rept on Status of Public Petitions Under 10CFR2.206 ML20211K6161999-08-31031 August 1999 Rev 2 to VC Summer Nuclear Station,Colr for Cycle 12, Dtd Aug 1999 RC-99-0183, Monthly Operating Rept for Aug 1999 for Virgil C Summer Nuclear Station,Unit 1.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Virgil C Summer Nuclear Station,Unit 1.With ML20212B8671999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Seabrook Station. with RC-99-0168, Special Rept:On 990804,electric Driven Fire Pump XPP0134A & Diesel Driven Fire Pump XPP0134B,were Removed from Svc to Allow for Plant Mod.Fire Pumps Were Returned to Operable Condition on 990818,after Mod Was Completed1999-08-19019 August 1999 Special Rept:On 990804,electric Driven Fire Pump XPP0134A & Diesel Driven Fire Pump XPP0134B,were Removed from Svc to Allow for Plant Mod.Fire Pumps Were Returned to Operable Condition on 990818,after Mod Was Completed ML20210Q7581999-08-11011 August 1999 SER Approving Proposed Merger of CES & Bec,Which Will Create New Parent Company of Canal ML20210R9781999-08-0606 August 1999 ISI Exam Rept of Seabrook Station, for RFO 6,period 3 ML20210J8681999-08-0303 August 1999 SER Approving License Transfer from Montaup Electric Co to Little Bay Power Corp & Approval of Conforming Amend for Seabrook Station Unit 1 ML20210R6001999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Seabrook Station, Unit 1.With ML20211C2201999-07-31031 July 1999 Rev 1 to WCAP-15102, VC Summer Unit 1 Heatup & Cooldown Limit Curves for Normal Operation RC-99-0163, Monthly Operating Rept for July 1999 for VC Summer Nuclear Station,Unit 1.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for VC Summer Nuclear Station,Unit 1.With ML20210M7071999-07-31031 July 1999 Rev 1 to VC Summer Nuclear Station COLR for Cycle 12 ML20209H1371999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Seabrook Station, Unit 1.With ML20210H1151999-06-30030 June 1999 Naesc Semi-Annual Fitness-for-Duty Rept for 990101-0630 RC-99-0137, Monthly Operating Rept for June 1999 for VC Summer Nuclear Station,Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for VC Summer Nuclear Station,Unit 1.With RC-99-0122, Monthly Operating Rept for May 1999 for VC Summer Nuclear Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for VC Summer Nuclear Station.With ML20195G5391999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Seabrook Station, Unit 1.With ML20195C0491999-05-25025 May 1999 Offshore Intake Seal Deterrent Barrier Design ML20206H2971999-05-0505 May 1999 Part 21 Rept Re Common Mode Failure for magne-blast Breakers.Vc Summer Nuclear Station Utilizes These Breakers in Many Applications,Including 7.2-kV EDG Electrical Buses ML20206K2421999-04-30030 April 1999 Rev 0 to COLR for Cycle 12 for Summer Nuclear Station RC-99-0103, Monthly Operating Rept for Apr 1999 for VC Summer Nuclear Station.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for VC Summer Nuclear Station.With ML20206E4761999-04-30030 April 1999 LER 99-S01-00:on 990408,contractor Employee Was Granted Temporary Unescorted Access to Seabrook Station Protected Area.Caused by Failure of Contractor Employee to Provide Accurate Info.Individual Access Revoked.With ML20206N1751999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Seabrook Station, Unit 1.With ML20196L2081999-04-19019 April 1999 Rev 01-07-00 to RE-21, Cycle 7 Colr RC-99-0087, Part 21 Interim Rept (SSH 99-0001) Re 990218 Failure of Circuit Breaker Located in Cubicle 14 of XSW1DB to Close During Surveillance Testing.Caused by Positive Interlock Angle Was Incorrect.Breaker Was Returned to GE Factory1999-04-15015 April 1999 Part 21 Interim Rept (SSH 99-0001) Re 990218 Failure of Circuit Breaker Located in Cubicle 14 of XSW1DB to Close During Surveillance Testing.Caused by Positive Interlock Angle Was Incorrect.Breaker Was Returned to GE Factory ML20205K5441999-03-31031 March 1999 Decommissioning Update ML20205L8141999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Seabrook Station. with RC-99-0083, Monthly Operating Rept for Mar 1999 for VC Summer Nuclear Station,Unit 1.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for VC Summer Nuclear Station,Unit 1.With RC-99-0063, Special Rept:On 990302 & 16,meteorological Site Number One 10 Meter Temp Element Was Declared Inoperable.Caused by Erratic Operation.Cabling & 10 Meter Electrical Connectors Were Replaced1999-03-26026 March 1999 Special Rept:On 990302 & 16,meteorological Site Number One 10 Meter Temp Element Was Declared Inoperable.Caused by Erratic Operation.Cabling & 10 Meter Electrical Connectors Were Replaced ML20205C1981999-03-24024 March 1999 Safety Evaluation Concluding That Proposed Relief Request IR-8,Rev 1,provides Acceptable Alternative to ASME Code Requirements.Recommends Authorization of Proposed Alternative Pursuant to 10CFR50.55a(a)(3)(i) ML20196K5421999-03-22022 March 1999 Rev 2 to VC Summer Nuclear Station,Training Simulator Quadrennial Certification Rept,1996-99, Books 1 & 2. Page 2 of 2 Section 2.4.4 (Rev 2) of Incoming Submittal Were Not Included RC-99-0055, Special Rept:On 990302,Meteorological Site Number One 10 Meter Temp Element (RTD) Was Declared Inoperable Due to Erratic Operation.Cause of Original RTD Failure Is Unknown. Equipment Was Declared Operable on 9903121999-03-16016 March 1999 Special Rept:On 990302,Meteorological Site Number One 10 Meter Temp Element (RTD) Was Declared Inoperable Due to Erratic Operation.Cause of Original RTD Failure Is Unknown. Equipment Was Declared Operable on 990312 ML20207F4941999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Seabrook Station. with RC-99-0050, Monthly Operating Rept for Feb 1999 for VC Summer Nuclear Station,Units 1.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for VC Summer Nuclear Station,Units 1.With ML18106B0931999-02-25025 February 1999 Part 21 Rept Re Possible Defect in Swagelok Pipe Fitting Tee,Part Number SS-6-T.Caused by Crack Due to Improper Location of Heated Bar.Only One Part Out of 7396 Pieces in Forging Lot Was Found to Be Cracked.Affected Util,Notified ML20203F4511999-02-12012 February 1999 SER Finding Licensee Adequately Addressed GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves, for Virgil C Summer Nuclear Station ML18106B0551999-02-0101 February 1999 Part 21 Rept Re Possible Matl Defect in Swagelok Pipe Fitting Tee,Part Number SS-6-T.Defect Is Crack in Center of Forging.Analysis of Part Is Continuing & Further Details Will Be Provided IAW Ncr Timetables.Drawing of Part,Encl ML18106B0441999-01-29029 January 1999 Part 21 Rept Re Possible Defect in Swagelok Pipe Fitting Tee Part Number SS-6-T.Caused by Crack in Center of Forging. Continuing Analysis of Part & Will Provide Details in Acoordance with NRC Timetables ML20202E8241998-12-31031 December 1998 Naesc Semi-Annual Fitness-for-Duty Rept for 980701-981231 ML20206R5241998-12-31031 December 1998 Santee Cooper 1998 Annual Rept ML20206R5191998-12-31031 December 1998 Scana Corp 1998 Annual Rept RC-99-0004, Monthly Operating Rept for Dec 1998 for VC Summer Nuclear Station,Unit 1.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for VC Summer Nuclear Station,Unit 1.With RC-99-0052, Vsns 1998 Annual Operating Rept. with1998-12-31031 December 1998 Vsns 1998 Annual Operating Rept. with ML20198P1831998-12-31031 December 1998 LER 98-S01-00:on 981214,incomplete pre-employment Screening Records Was Noted.Caused by Failure of Contractor Employee to Provide Accurate Info.Subject Contractor Employees Employment Was Terminated.With 1999-09-08 |
Text
gg gggg7lgg Fairbank] Morse Engine Division 701 Lawton Avenue
@ Beloit Wisconsin 53511 608/364-4411 March 8,1984 Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Ill . 60137 Attention: Mr. James G. Keppler, Director, Region III
Subject:
. Colt Industries-Fairbanks Morse Engine Division Emergency Diesel Generators South Carolina Electric & Gas Co.-Summer Station January 14,1980 Part 21 Report-Failed Engine Thrust Bearing Supplement No. 5-Public Service of New Hampshire, Seabrook Unit 1
+
Gentlemen:
We have completed our inspection of the crankshaft thrust bearings on the two Diesel Generators for Public Service of New Hampshire, Seabrook Unit 1.
The plugs were properly installed in both units. The units are free of the reported potential defect.
A copy of this report is being forwarded to the utility involved via the A/E.
We will report our findings on the remaining suspect units as the inspections are made, prior to their initial operation.
Very truly yours,
/Moriarty2:
MANAGER UTILITY S JMM:jc cc: United Engineers & Constructors, Inc.
P. O. Box 8223 Philadelphia, PA 19101 Attention: Mr. D. H. Rhoads Project Engineering Manager (Seabrook)
U. S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D. C. 20555 8403190240 040300 a oon on o,in. coie inoo n., op.,.. co<,
gDRADOCKOSOOO95 MAR S1984 g6 6 40