N UNITED STATES NUCLEAR REGULATORY COM4ISSION
)
BOSTON EDISON COMPANY DOCKET NO. 50-293 PILGRIM NUCLEAR POWER STATION
]
ENVIR0ltlENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of an exemption from certain requirements of its regulations to Facility Operating License No. DPR-35, issued to Boston Edison Company (the
)
licensee), for operation of the Pilgrim Nuclear Power Station located in
)
Plymouth, Massachusetts.
ENVIR0letENTAL ASSESSMENT Identification of Prooosed Action:
I The proposed action is in accordance with the licensee's application i
dated June 21, 1995, for an exemption from certain requirements of 10 CFR 73.55, " Requirements for physical protection of licensed activities in nuclear power plant reactors against radiological sabotage." The requested exemption would allow the implementatwn of a hand geometry biometric system
. 1 i
of site access control in conjunction with photograph identification badges, and would allow the badges to be taken offsite.
The Need for the Pronosed Action:
Pursuant to 10 CFR 73.55(a), the licensee is required to establish and j
maintain an onsite physical. protection system and security organization.
The Code of Federal Regulations at 10 CFR 73.55(d), " Access Requirements," specifies in part that:
"The licensee shall control all points of personnel and vehicle access into a protected area." The Code of Federal 9508150080 950808 PDR ADOCK 05000293' P
-__-.~.-,._,
4 f Regulations at 10 CFR 73.55(d)(5), specifies in part that: "A numbered picture badge identification system shall be used for all individuals who are authorized access to protected areas without escort."
It further indicates that an individual not employed by the licensee (e.g.,-contractors) may be authorized access to protected areas without an escort provided the individual, " receives a picture badge upon entrance-into the protected area which must be returned upon exit from the protected area."
Currently, unescorted access for both employee and contractor personnel into the Pilgrim Nuclear Power Station is controlled through the use of picture badges.
Positive identification of personnel who are authorized and request access into the protected area is established by security personnel making a visual comparison of the individual requesting access and that individual's picture badge. The picture badges are issued, stored, and retrieved at the entrance / exit location to the protected area. These picture badges are not taken offsite. This current practice is in accordance with the applicable requirements of 10 CFR Part 73 discussed above.
The licensee proposes to implement an alternative unescorted access control system which would eliminate the need to issue and retrieve picture badges at the entrance / exit location to the protected area. The proposal would also allow all individuals, including centractors, who have unescorted access to keep their picture badges in their possession when departing the Pilgrim site. Thus, an exemption is required from 10 CFR 73.55(d)(5) to allow contractors who have unescorted access to keep their pictura badges in their possession when departing the Pilgrim site.
A.
Environmental Imnacts of the Proonsed Action:
The Commiission has completed its evaluation of the proposed action.
In addition to their picture badges, all individuals with authorized unescorted access will have the physical characteristics of their hand (hand geometry) registered with their picture badge number in a computerized access control system. Therefore, all authorized individuals must not only have their picture badges to gain access into the protected area, but must also have their hand geometry confirmed.
All other access processes, including search function capability and access revocation, will remain the same. A security officer responsible for access control will continue to be positioned within a bullet-resistant structure. The proposed system is only for individuals with authorized unescorted access and will not be used for individuals requiring escorts.
The underlying purpose for requiring that_ individuals not employed by the licensee must receive and return their picture badges at the entrance / exit is to provide reasonable assurance that the access badges could not be compromised or stolen with a resulting risk that an unauthorized individual could potentially enter the protected area. Although the proposed exemption will allow individuals to take their picture badges offsite, the proposed measures require not only that the picture badge be provided for access to the protected area, but also that verification of the hand geometry registered
~
with the badge be performed as discussed above. Thus, the proposed system provides an identity verification process that is equivalent to the existing process.
~
i i
' i Accordingly, the Commission concludes that the exemption to allow individuals not employed by the licensee to take their picture badges offsite will not result in an increase in the risk that an unauthorized individual could potentially enter the protected area. Accordingly, the Commission concludes that there are no significant radiological impacts associates with l
the proposed action.
)
The proposed exemption does not affect nonradiological plant effluents and has no other environmental impact. Accordingly, the Commission concludes that there are no significant nonradiological environmental impacts associated with the proposed action.
Alternatives to the Procosed Action:
Since the Commission has concluded there is no measurable environmental impact associated with the proposed action, any alternatives with equal or greater environmental impact need not be evaluated. The principal alternative to the proposed action would be to deny the requested action. Denial of the i
requested action would not significantly enhance the environment in that the proposed action will result in a process that is equivalent to the existing identification verification process.
Alternate Use of Resources:
This action does not involve the use of any resources not previously considered in the April 1973 Final Environmental Statement for the Pilgrim Nuclear Power Station.
9 Aaencies and Persons Consulted:
In accordance with its stated policy, on July 17, 1995, the staff consulted with the Massachusetts State official, James Muckerheide of the Massachusetts Emergency Management Agency regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT Based upon the environmental assessment, the Comeission concludes that the proposed action will not have a significant effect on the quality of the aan environment. Accordingly, the Commission has determined not to prepare 4n environmental impact statement for the proposed exemption.
For further details with respect to this action, see the licensee's letter dated June 21, 1995, which is available for public inspection at the Commission's Public Document Room, The Gelman Building, 2120 L Street, NW.,
Washington, DC 20555, and at the local public document room located at the Plymouth Public Library, 11 North Street, Plymouth, MA 02360.
Dated at Rockville, Maryland, this 8th day of August 1995.
FOR THE NUCLEAR REGULATORY COMISSION Ledyard B. Marsh, Director Project Directorate I-l Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation v
E. Boulette l This notice is being forwarded to the Office of the Federal Register for publication.
Sincerely, Original signed by:
Ronald B. Eaton, Senior Project Manager Project Directorate I-1 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosure:
Environmental Assessment cc w/ enc 1: See next page DISTRIBUTION:
Docket File PUBLIC PDI-I Reading SVarga JZwolinski LMarsh Slittle KCotton REaton LCunningham OGC EJordan ACRS (4)
CCowgill, RGN-I DOCUMENT NAME: G:\\ PILGRIM \\PI92776.ENV To meelve e copy of this document, indiente in the box: "C" p Copy without enclosurss/%!M Copy with ecolosures *N' = No copy 0FFICE LA:PDI-InO l PM:@lryl t.. I NRR:764 W /('
PM9F$ld l OGC,,s,j
[
NAME Slittle W KCont"En:sW LCunntingbin '
RE ntin UVW DATE 07/l' /95 07/ 0 95 V 07f)G95 07P2,J/95 07/7l/95 0FFICE D:PDI-I A
t<
t NAME LMarsh 1h DATE (ff y /95 0FFICIAkRECORD;COM