ML20087B340

From kanterella
Jump to navigation Jump to search
Submits Details of Vendor Manual Review Program in Response to 830506 Order Modifying Licenses.Commitment to Incorporate All Vendor Manuals for safety-related Equipment Into Document Control Sys Completed
ML20087B340
Person / Time
Site: Salem  
Issue date: 02/22/1984
From: Liden E
Public Service Enterprise Group
To: Kister H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8403090049
Download: ML20087B340 (3)


Text

'

JO PSEG Public Senace Electric and Gas Company - P.O. Box 236 Hancocks Bridge, New Jersey 08038 Nuclear Department February 22, 1984

0. ' S.

Nuclear Regulatory Commission - Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406 Attention:

Mr.

H.

B.

Kister, Chief Reactcr Projects' Branch 2 Division of Project and Resident Programs Gentlemen:

VENDOR MANUAL REVIEW PROGRAM SALEM GENERATING STATION-UNITS-NO. 1 AND 2-

-DOCKET NO. 50-272 AND 50-311.

The May 6, 1983 Order Modifying the Licenses for Salem Generating-Station, Units l'and 2, included a commitment to

~

incorporate all vendor manuals for safety-related equipment into ya' document control system.

This program is complete and Public LService Electric & Gas (PSE&G) has commenced a program to review the vendor manuals against maintenance'and operating sprocedures.-

As discussed-with the Salem Resident Inspector, we have undergone a learning process in implementing this review program and, at his suggestion we are submitting this letter to provi'de you with an understanding of what this_ program entails.

We believe Salem's existing operating, surveillance and maintenance-procedures reflect the best available engineering

.and' vendor-information.

The existing procedures were originally derived from startup procedures and existing vendor manuals.

They have been ' subsequently revised to -reflect design changes, engineering recommendations, vendor bulletins, and operating and maintenance experience.

All plant procedures were developed and revised using administrative controls that have.been in-place since initial' operation; thus, PSE&G places a high level of

-confidence-in the existing. procedures.

~

i B403090049 840222 PDR ADOCK 05000272-

^

P PDR The Energy Peorie p

, o

.r-,

n w.

u

L

'E Li[

U.K S. Nuclear Regulatory' Commission. 2/22/84

^

h t.

L PSE&G hasJcompleted an, extensive program to update vendor manuals for' safety related equipment to ensure that we have the most: current' revision of-each-pertinent manual in-house.

It was i t-our : intent toEthen-' implement a_ program to ensure that F

information in.these vendor manuals was properly reflected in all station maintenance and operating procedures.

It was recognized,.however, that there can still be inconsistencies between a manual and the installed equipment.

These differences are legitimate in:that they represent equipment modifications

~

.done by persons other than the vendor, incorporate engineering recommendations identified in PSE&G' Field Directives or Safety

Evaluations, incorporate. vendor. field representative

_ recommendations and/or reflect operating experience.

We believe into the station 5that all of these differences must be factored procedure verification' program.

Although the initially envisioned program consisted of a straight-forward approach where the vendor manuals would be

. reviewed against plant procedures as " stand-alone" documents

' the above concerns dictated a more comprehensive approach.

-Accordingly, PSE&G has implemented an intensive procedure verification program.- This program is multi-phased and

includes:'

a.

Review of the current safety related vendor manuals against pertinent operating, maintenance and surveillance procedures.

This task will be completed by.. July 1, 1984.

b.-

Review of safety related vendor manuals, completed

-. design changes, field. directives and safety evaluations

.to. identify significant differences.

Completed design changes, field. directives or safety evaluations which

affect specific.-informativa addressed in the vendor

' manuals will be documented by issuing manual revisions orzaddenda by January 1, 1985.

4 c.

Differences identified in.-(a) will be evaluated.

This

-evaluation will resolve each difference by either certifying its acceptability,' revising station procedures and/or initiating c long' term investigation, as appropriate.

This task will be complete by January

. 1, '1 9 8 5.-

.d.

Review of revised Vendor Manuals (identified during task (b)), Safety Evaluations and Field Directives against. station procedures will'be completed by July 1, 1985.-

F


n.-


1.-

k w

o, 4

)

- e W*

.+

,%3^-

-U..S.. Nuclear Regulatory Co 2/22/84

-e.

Review of vendor manua.a-aga.ast procedures.will also be incorporated into an. ongoicg process as part of the normal review and validation program conducted

~

biennially for each procedure..

PSE&G=b'elieves that the program as detailed'abcVe.will ensure vendor: manuals and. plant procedures reflect current plant

,.' u; configuration and engineering requirements.

If1_you have.any questions, please contact us.

b

~

Sincerely, 4

E.

A.

Liden Manager - Nuclear Licensing and Regulation