t 'N Commonwealth Edison

.) one First Natdrtti Plaza. Chic"go, thnois

$ C "' Xddr:ss Riply to. Post Offica Box 767

\\ j/ Chicago, Illinois 60690 February 24, 1984 Mr. James G. Keppler Regional Administrator U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Byron Generating Station Units 1 and 2 Byron QC Inspector Reinspection Program I&E Inspection Report Nos. 50-454/82-05 and 50-454/82-04 References (a):

W. L. Stiede letter to J. G. Keppler dated October 20, 1983 (b):

L. O. DelGeorge letter to J. G. Keppler dated January 12, 1984

Dear Mr. Keppler:

Attached is the Commonwealth Edison Report on the Byron QC Inspector Reinspection Program.

That report constitutes the final report on the Reinspection Program, and supercedes previous reports on this subject submitted in references (a) and (b).

If you have any questions on this report or the Reinspection Program conducted at Byron, please contact this office.

One signed original and twenty copies of this letter and the attachments are submitted for your use.

Very truly yours, o

~

L. O. De1Georg Assistant Vice President Attachmeni.s Mr. H. R. Denton (NRR) - w/20 copies of attachments cc:

Mr. R. C. DeYoung (IE Headqusrters) - w/20 copies of attachments 8201N 8403010003 840224

[ g DR ADOCK 05000

l O

Commonwealth Edison 9

Report on the Byron QC Inspector Reinspection Program Docket Nos. 50-454 and 50-455 s-February,1984

..