Amend 44 to License NPF-57,changing Channel Functional Test Surveillance Intervals for RPS Electrical Protective Assemblies (EPA) & Power Range Neutron Monitoring Sys EPAs to Each Time Plant in Cold Shutdown for More than 24 H
ML20086B906
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 11/05/1991
From: Chris Miller
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20086B908 List:
References
NUDOCS 9111210128
Download: ML20086B906 (7)


Text

._

  1. p naq%'

UNITED STATES l'

' 'n NUCLE AR REGULATORY COMMISSION 3,,,

U w AsmNO T ON, D. C. 705%

o i

'I s

/

PUBLIC SERVICE E,LE,CTR.lC. &, GAS, C0f,PAKY 0.TLpMJ,C.,C,1,T,Y, EL,ECTRIC COMPANY DOCKET NO. 50 354 HOPE CREEK GENERATitlG STAT 10l4 Af!ENDf4EtiT TO FACIL1,TY,0PE,PATitlG,}lCENSE, Amendment flo. 44 License tio. NPF-57 1.

The !!uclear Regulatory Commission (the Conunission or the NRC) has found that:

A.

The application for amendn.ent filed by the Public Service Electric &

Gas Company (PSE&G) dated September 6,1991, complies with the stendards and requirements of the Atomic Energy Act of 1954, as an. ended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter 1; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D.

The issuance of this arrendtrent will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendrrent is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by changes to the Technical Specifica-tions as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of facility Operating License No. !!PF-57 is hereby amended to read as follows:

(2) Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment i;o.44, and the Envirnnmental Protection Plan contained in Appendix B, are hereby incorporated in the license.

PSE&G shall operate the facility in accordance with the Technical Specifications and the l

Environmental Protection Plan.

l I

91112101PO 91110D PDR ADOCK 050003S4 l

p PDR

2 3.

This license amendment is effective as of its date of issuance and shall be implemented within 60 days of the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION ddYMM Charles L. Miller, Director Project Directorate 1-2 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issu6nte: November 5, 1991 l

I

I ATTACHMENT TO LICENSE AMENDf'ENT NO. 6 FACILITY OPERATING LICENSE NO. NPF-57 DOCKET NO. 50-364 Replace the folicwing pages of the Appendix "A" Technical Specifications with

the attached pages.- The revised pages are identified by Amendment number and contain vertical lines indicating the area of change. Overleaf pages provided to maintain document completeness.*

Remove Insert 3/4 8-39

-3/4 8-39*

3/4 8-40 3/4 8-40 3/4 8-43 3/4 8-43*

3/4-B-44 3/4 8-44 I

2a

TABLE 3.8.4.3-1 MOTOR OPERATED VALVES - THERMAL OVERLOAD PROTECTION (NOT BYPASSED)

VALVE NUMBER SYSTEM (S) AFFECTED IBC-HV-F003A Residual Heat Removal 1BC-HV-F003B Residual Heat Removal 1GS-HV-5741A Containment Atmosphere Control r

IGS-HV-5741B Containment Atmosphere Control 1KC-HV-3408V.

Fire Protection f

HOPE CREEK 3/4 8-39

}

. _ - - - = -

ELECTRICAL POWER SYSTEMS REACTOR PROTECTION SYSTEM ELECTRICAL POWER MONITORING LIMITING CONDITION,FOR OPERATION 3.8.4.4 Two RPS electric power monitoring channels for each inservice RPS MG set or alternate power supply shall be OPERABLE.

APPLICABILITY:

At all times.

ACTION:

\\

a.

With one RPS electric power monitoring channel for an inservice RPS MG set or alternate power supply inoperable, restore the inoperable power j

monitoring channel to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or remove the associated RPS MG set or alternate power supply from service.

b.

With both RPS electric power monitoring channels for an inservice RPS MG set or alternate power supply inoperable, restore at least one electric power monitoring channel to OPERABLE status within 30 minutes or remove the associated RPS MG set or alternate power supply from service.

SURVEILLANCE REQUIREMENTS 4.8.4.4 The above specified RPS electric power monitoring channels shall be determined OPERABLE:

a.

By performance of a CHANNEL FUNCTIONAL TEST each time the plant is in COLD SHUTDOWN for a period of more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, unless performed in the previous 6 months.

I b.

At least once per 18 months by demonstrating the OPERABILITY of over-voltage, under-voltage, and under-frequency protective instrumentation by performance of a CHANNEL CAllBRATION including simulated automatic actuation of the protective relays, tripping logic and output circuit breakers and verifying the following setpoints.

1.

Over-voltage 5 132 VAC, (Bus A), 132 VAC (Bus B) 2.

Under-voltage 1108 VAC, (Bus A),108 VAC (Bus B) 3.

Under-frequency 3 57 Hz.

(Bus A and Bus B)

HOPE CREEK 3/4 8-40 Amendment No. 44

TABLE 3.8.4.5-1 (Continued) 480 VAC POWER CIRCUIT BREAKERS 1.

Type AKR-5A-30 (Continued)

Class 1E Circuit Class IE Breaker No.

Bus Non-Class 1E Load Description 52-45034 10B450 Reactor Building Exhaust Fan ICV 301 52-46011 108460 Reactor Area MCC 10B262 52-46014 108460 Radwaste Area Exhaust Fan OBV305 52-47011 10B470 Reactor Area MCC 108272 52-47014 10B470 Radwaste Area Exhaust Fan OCV305 52-47024 10B470 Radwaste Area Supply Fan OAV316 52-47031 108470 Technical Support Center MCC 008474 52-48011 108480 Reactor Area MCC 10B282 52-49024 10B480 Reactor Building Exhaust Fan 1AV301 400 VAC MOLDED CASE CIRCUIT BREAKERS 1.

Type HFB150 Class IE Circuit Class 1E Breaker No.

Bus Non-Class IE Load Description 52-441043 108441 N555 Computer Inverter 100485 52-451023 10B451 Public Address System Inverter 100496 52-471023 10B471 Security System Inverter 0A0495 HOPE CREEK 3/4 8-43

ELECTRICAL POWER SYSTEM POWER RANGE NEUTRON MONITORING SYSTEM ELECTRICAL POWER MONITORING l

LIMITING CONDITION FOR OPERATION l'

3.8.4.6 The power range neutron monitoring system (NMS) electric power monitoring channels for each inservice power range NMS power supply shall be OPERABLE.

APPLICABILITY:

At all times.

ACTION:

a.

With one power range NMS electric power monitoring channel for an l

inservice power range NMS power supply inoperable, restore the in-operable power monitoring channel to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or deenergize the associated power range NMS power supply feeder circuit.

i b.

With both 90wer range NMS electric power monitoring channels for an inservice power range NHS power supply inoperable, restore at least l

one electric power monitoring channel to OPERABLE status within 30 minutis or deenergize the associated power range NHS power supply feeder circuit.

SURVEILLANCE REQUIREMENTS l

4.8.4.6 The above specified power range NMS electric power monitoring channels-shall be determined OPERABLE:

a.

By performance of a CHANNEL FUNCTIONAL TEST each time the plant is in l

COLD SHUTOOWN for a period of more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, unless performed in the previous 6 months.

b, At least once per 18 months by demonstrating the OPERABILITY of over-voltage, under-voltage, and under-f requency protective instrumentation by performance of a CHANNEL CALIBRATION including simulated automatic actuation of the protective relays, tripping L

logic and output circuit breakers and verifying the following setpoints.

1.

Over-voltage 5, 132 VAC (BUS A), 132 VAC (BUS B) 2.

Under voltage 1 109 VAC (BUS A), 108 VAC (BUS B) 3.

Under-frequency 3 57 Hz.

-0,

+2%

HOPE CREEK 3/4 3-44 Amendment No. 44