Forwards Commitments Re Electrical Separation.Standby Liquid Control Sys Terminations as Technical Blocks in Main Control Room & Local Panels Will Be Reviewed & Where Electrical Feeds Are Different,Terminations Will Be Separated
ML20086A671
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 11/15/1983
From: Schroeder C
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8311160064
Download: ML20086A671 (2)


Text

_-

7#~'N 7 Commonwealth Edison

) one First NTtiotti Pitza. Chicago, Ilknois

,, O 7 Address Reply to: Post Offics Box 767

'(f Chicago. Illinois 60690 -

November 15, 1983 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

LaSalle County Station Units 1 and 2 Comitments Regarding Electrical Separation NRC Docket Nos. 50-373 and 50-374

Reference:

(a) Meeting on November 14, 1983 at Maryland National Bank Building Regarding Electrical Separation (b) Trip Report Concerning Cable Separation Concerns at LaSalle, Unit 2 (TIA 83-76)

Dear Mr. Denton:

On November 14, 1983, Dr. A. Bournia, et al, of your office met with C. W. Schroeder, et al, of Comonwealth Edison Company regarding electrical separation.

With respect to separation regarding the terminations of (and not routing of) cables at termination blocks for standby liquid control system, our commit-ment is attached.

With respect to other separation concerns, the applicant has received a copy of Reference (b). Commonwealth Edison's comitment regarding these concerns is also attached.

To the best of my knowledge and belief, the statements contained herein and in the attachments are true and correct. In some respects, these statements are not based upon my personal knowledge but upon information furnished by other Comonwealth Edison employees and consultants. Such information has been reviewed in accordance with Company practice and I believe it to be reliable.

If there are any further questions in this matter, please contact this office.

Very truly yours, f31116006483J115 R ADOCK 05000373 C. W. Schroeder P

PDR Nuclear Licensing Administrator cc: NRC Resident Inspector - LSCS l 2P*{

I I

Commitment For the SBLC system, terminations on terminal blocks in the main control room and local panels shall be reviewed. In those cases for those terminal

-blocks where electrical feeds are from different divisions, those terminations shall be separated (either on the same or-different terminal blocks) by at least six inches and uniquely identified by division per FSAR commitments.

This shall be accomplished before initial critical on Unit 2, and prior to startup following the first refueling outage on Unit 1.

Commitment Commonwealth Edison shall review the " Trip Report Concerning Cable Separation Concerns at LaSalle, Unit 2 (TIA 83-76)." Commonwealth Edison shall address sections 4.1,4.2, 4.3, and 4.5 of that report to assure that independence of RPS channelization is not compromised by external bridging curcuits.

This shall be accomplished and corrective actions shall be implemented prior to the startup following the respective first refueling outage for Units 1 and 2.

It is understood that for Item 4.5, addition of zipper tubing to divisional cabling not c' urrently protected for the seven ADS and .two Low Low Set valves with service from two different divisions will be acceptable, even if the tubing is "touching." It is further understood that in those cases whre all three cable feeds to the remaining SRV valves are the same division, pgt protection is required.

?