Forwards Rev 3 to Implementation Schedule in 830415 Response to Generic Ltr 82-33,Suppl 1 to NUREG-0737, Requirements for Emergency Response Capability
ML20085L187
Person / Time
Site: Cooper Entergy icon.png
Issue date: 10/18/1983
From: Judith Weaver
NEBRASKA PUBLIC POWER DISTRICT
To: Siegel B
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 GL-82-33, NUDOCS 8310210302
Download: ML20085L187 (3)


Text

~

GENERAL OFFICE g

Nebraska Public Power District

" ~" " V e Afo"a W ?ei4 ***

  • October 18, 1983 Mr. Byron Siegel M/S 308 Project Managey - Cooper Nuclear Station Operating Reactors Branch No. 2 Division of Licensing U.S. Nuclear Regulatory Commission Eshington, D.C. 20555

Dear Byron:

Subject:

Revised Response to NUREG-0737, Supplement 1,

" Emergency Response Capability" - Revision 3

Reference:

(1)

NPPD Letter from J. M. Pilant to D. G. Eisenhut dated April 15,

1983, LQA8300120, " Response to NUREG-0737, Supplement 1" Reference (1) is the District's response to Generic Letter 82-33, Supplement 1 to NUREG-0737, " Requirements for Emergency Response Capability", for Cooper Nuclear Station.

Enclosed is Revision 3 to Attachment 2 to Reference (1) which includes changes in two dates.

The changes are indicated by revision bars on the right-hand side of the page.

These changes have been discussed with our NRC Project Manager and are necessary for the following reasons:

1.

Regulatory Guide 1.97 Assessment Report Submittal Date Efforts to date in coordinating all Supplement 1 projects have shown that the instruments and parameters associated with the Regulatory Guide 1.97 Assessment Report are also impacted by the SPDS, CRDR, and EOP upgrade projects.

It would be premature for the District to justify deviations or propose alternatives on November 30, 1983, when the other projects will not be completely assessed until March 1, 1984.

2.

CRDR Summary Report Submittal Date Efforts of the District's contractor have resulted in a better estimate of this submittal date.

A 003 8310210302 831018 PDR ADOCK 05000298 II F

PDR I

~

Mr. Byron Siegel Page 2 October 18, 1983 As discussed in Attachment 8 of Reference (1), the District will continue to keep you informed of the status of these projects.

Sincerely, A

J. D. Weaver Licensing Manager JDWremzl8/2 Enclosure 1

m

Ravision 3 October 17, 1983 ATTACHMENT 2 Implementation Schedule INITIATIVE MILESTONE DATE STATUS

  • SPDS/PMIS Award of SPDS/PMIS Contract Sep. 30, 1983 C

Submittal of Safety Analysis Mar. 1, 1984 C

and submit firm completion dates for remaining sched-ule milestones SPDS Computer Deliver July 31, 1984 E

and Install System Integration Complete Dec. 31, 1985 E

SPDS Operable Feb. 28, 1986 E

Operators trained Feb. 28, 1986 E

Pre-Implementation Review by NRC (Verification & Valida-tion Review)

  • Start Mar. 1, 1984 E
  • Completion May 31, 1984 E
  • Audit of installed Feb. 28, 1986 E

system by NRC CRDR Select Contractor Aug. 1, 1983 C

Submittal of Program Plan Mar. 1, 1984 C

and submit firm completion dates for remaining sched-ule milestones l

Submittal of Summary Report June 30, 1984 E

Regulatory Submit firm completion dates Mar. 1, 1984 C

Cuide 1.97 for remaining schedule milestones and submit Assessment Report Implement Requirements June 30, 1985 E

E0P Upgrade Submittal of Generic Dec. 22, 1982 C

Technical Guidelines Select Contractor Aug. 1, 1983 C

Submit firm completion dates Dec. 30, 1983 C

for remaining schedule milestones Submittr' of Procedures June 30, 1984 E

Generation Package Implementation of E0P's Dec. 31, 1984 E

ERF/PMIS Emergency Plan Exercise April 6, 1983 C

verifies facilities complete at this time Submit firm completion dates Mar. 1, 1984 C

for remaining schedule milestones ERF's operational per Feb. 28, 1986 E

Supplement 1 Exercise to verify April, 1986 E

facilities complete per Supplement 1

  • E = estimate (subject to change)

C = commitment