i LOUISIANA POWER & LIGHT /Waterford 3 SES/P. O.
Box E/Killona, LA 70066 NSNhYSE October 7, 1983 W3K83-1512 Q-3-A35.07.70 Mr. John T. Collins Regional Administrator, Region IV I
U. S. Nuclear Regulatory Commission i
OCT I 4 M3 1
611 Ryan Plaza Drive, Suite 1000 g
. y Arlington, Texas 76012 g
-l
REFERENCE:
LP&L letter W3183-0305 dated September 9, 1983
Dear Mr. Collins:
SUBJECT:
Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 70 "GE 480-V Trip Coils Do Not Drop Out After Tripping" Fifth Interim Report l
The above referenced letter indicated that a Final Report would be submitted l
to the USNRC by October 11, 1983.
At the present time, only 2 of 86 breakers remain to have the design change installed, and verification of supporting documentation is in progress. The corrective action is expected to be completed in November 1983.
l A Final Report will therefore be submitted to the USNRC on December 21, 1983.
Very truly yours, D
T. F. oerrets Quality Assurance Manager TFG:CNH:VBR cc: Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D.C.
20555 8310210293 831007 PDR ADOCK 05000382 1 b-1 S
PDR eO
t-
.o 3.,
Mr. John T. Collins October 7, 1983 W3K83-1512 Page 2 cc: Director Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D.C.