Text
,
~
Citation Support Deprrtm:nt
']
n c..
_w l
G v' ' PECO ENER Y "eco e"-av e a ">
c Nuclear Group Headquaders s
965 Chesterbrook Boulevard Wayne, PA 19087 5091-June _16,1995 '
f i
Docket Nos. 50-353' i
i License Nos. NPF-85 i
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk r
Washington, D. C. 20555
- j
,e
Subject:
Limerick Generating Station, Unit 2 Generic Letter 89-10, " Safety Related Motor-Operated Valve Testing and Surveillance - 10CFR 50.54_ (f)"
- i NRC Notification of Completion of items Contained in First i
Paragraph of item 1.
References:
1)
Letter from D. R. Helwig (PECO Energy Company) to NRC l
dated December 28,1989 j
i 2)
Letter from D. R. Helwig to NRC dated March 16,1992 i
3)
Letter from G. A. Hunger, Jr. (PECO Energy Company) to i
NRC dated April 14,1994 l
4)
Letter from G. A. Hunger, Jr. to NRC dated December 21,
{
1994
)
Dear Sir:
NRC Generic Letter (GL) 89-10 " Safety Related Motor-Operated Valve Testing i
and Surveillance - 10CFR 50.54 (f)," item m, requires recensees to notify the j
NRC in writing within 30 days after the actions described in the first paragraph of item i of the GL have been completed. The purpose of this letter is to provide the NRC with notification that these actions were completed on May 20, j
1995, for Umerick Generating Station (LGS) Unit 2 valves in accordance with j
PECO Energy Company's commitments as documented in the referenced letters. A GL 89-10 program completion report, as well as supporting technical i
information, is.being prepared and will be available for review.
i 26003,;
1 95o628o243 95o616 PDR ADOCK 05ooo353 t
'P PDR
June 16,1995 Page 2 irt response to GL 89-10, PECO Energy developed and implemented a program to verify the design basis capability of motor operated valves (MOVs) that were within the scope of the GL. In accordance with our GL 89-10 program, the LGS Unit 2 MOVs have been tested and setup with the best available data.
PECO Energy has made a significant commitment of resources toward implementing the GL 89-10 program at LGS. Completion of the program
)
involved more tN A a five year effort. Future program changes deemed necessary in response to emerging issues and newly available data will be handled under the provisions of 10 CFR 50.59.
If you have any questions or require additional information, please contact us.
Sincerely,
.h.
f<
G. A. Hunger, Jr.
Director - Licensing cc:
T. T. Martin, Administrator, USNRC, Region i N. S. Perry, Senior Resident inspector, USNRC, LGS i