ML20085G036
| ML20085G036 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 05/31/1995 |
| From: | Hutchinson C, Lin S ENTERGY OPERATIONS, INC. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| GNRO-95-00068, GNRO-95-68, NUDOCS 9506200039 | |
| Download: ML20085G036 (5) | |
Text
_
.- ( *.
- Ent:rgy Oper; tion:,Inc.'
-=5~ ENTERGY eo eox 758 Purt Gbson.MS 39150 Tel 601437 2800
'l C. It Hutchinson vce F%soent Opewos June 13, 1995 cru ca nicu sam U.S. Nuclear Regulatory Commission Mail Station P1-137 Wu'agton, D.C. 20555
/4.antion:
Document Control Desk
SUBJECT:
Grand Gulf Nuclear Station Unit 1 Docket No. 50-416 License No. NPF-29 Monthly Operating Report GNRO-95/00068 I Gentlemen:
in accordance with the requirement of Technical Specification 3.6.4 Entergy Operations is providing the Monthiv Operating Report for Grand Gulf Nuclear Station Unit i for May 1995.
If you have any questions or require additional information,'please contact this office.
Yours truly, b
CRH/TMC attachments:
1.
Operating Status 2.
Average Daily Power Level 3.
Unit Shutdown and Power Reductions cc:
(See Next Page) 1 9506200039 950531 PDR ADOCK 05000416 j
R PDR L i
/
l
- June'13, 1995 GNRO-95/00068
' Page 2 of 3 cc:
Mr. D. C. Hintz (w/a)
Mr. R. B. McGehee (w/a).
Mr. N. S. Reynolds (w/a)
Mr. J. E. Tedrow (w/a)
Mr. H. L Thomas (w/o)
Mr. Stewart D. Ebneter (wla)
Regional Administrator U.S. Nuclear Regulatory Commission Region 11 101 Marietta St., N.W., Suite 2900 Atlanta, Georgia 30323 J
Mr. P. W. O'Connor, Project Manager Omce of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission -
Mail Stop 13H3 Washington, D.C. 20555 4
t 1
1
- e m
if9-p, m,
p b
y
{
+&
F-(--
Mg y+
Attachm:nt 1 to GNRO-95/00068 DOCKET NO 50-416 DATE 06/02/95 COMPLETED BY S. D. Lin TELEPHONE (601) 437-8793 OPERATING STATUS 1.
Unit Name: GGNS UNIT 1 2.
Reporting Period: Mav 1995 3.
Licensed Thermal Power (MWt): 3833 MWT 4.
Nameplate Rating (Gross MWe): 1372.5 MWE 5.
Design Electrical Rating (Net MWe): 1250 MWE 6.
Maximum Dependable Capacity (Gross MWe): 1190 MWE 7.
Maximum Dependable Capacity (Net MWe): 1143 MWE 8.
If changes occur in Capacity Ratings (items 3 through 7) Since Last Report. Give Reason:
N/A 9.
Power Level To Which Restricted, if Any (Net MWe):
N/A
- 10. Reasons For Restrictions, if Any:
N/A This Month Yr to Date Cumulative
- 11. Hours in Reporting Period 744 3.823 93.039
- 12. Number of Hours Reactor was Critical 0.0 2.470.5 75.621.8
- 13. Reactor Reserve Shutdown Hours 0
0 0
- 14. Hours Generator On-Line 0.0 2.457.7
_ 72.804.1
- 15. Unit Reserve Shutdown Hours 0
0 0
- 16. Gross Thermal Energy Generated (MWH) 0 9.189.458 258.032.951_
- 17. Gross Electrical Energy Generated (MWH) 0 2.991.883 82.313.38L
- 18. Net Electrical Energy Generated (MWH) 0 2.871.343 78.857.48o
- 19. Unit Service Factor 0.0 87.8 80.2
- 20. Unit Availability Factor 0.0 67.8 80.2
- 21. Unit Capacity Factor (Using MDC Net) 0.0 69.3 78.0
- 22. Unit Capacity Factor (Using DER Net)
QA_
63.4 70.9
- 23. Unit Forced Outage Rate 0.0 1.5 8.3
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
- 25. If Shut Down At End of Report Period. Estirw.tod Date of Startup:J6/09/95
- 26. Units in Test Status (Prior to Commercial Operetion).
Forecest Achieved INITIA! CRITICALITY 08/18/82 INITIA_ ELECTRICITY 10/20/84 COMMERCIAL OPERATION 07/01/85
a 4
Attachmsnt 2 to GNRO-95/OOO68 DOCKET NO 50-418 DATE 08/02/95 COMPLETED BY S. D. Lin TELEPHONE (801) 437-8793
(
i.
MONTH May1995 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWesNet)
(MWe-Net) 1 0
17 0
2 0
18 0'
3 0
19 0
4 0
20 0
5 0
21 0'
6 0
22 0
l 3
7 0
23 0
8 0
24 0
9 0
25 0
10 0
26 0
11 0
27 0
4 12 0
28 0
13 0
29 0
t-14 0
30 0
d 15 0
31 0
]
16 0
UNIT SilUTDOWNS AND POWER REDUCrlONS DOCKET NO.
50-416 UNIT NAME GGNS Unit 1 DATE 06/02/95 COMPLETED BY S. D. Lin TELEPIIONE (601M37-6793 REPORT MONTII May 1995 No.
Date Type (1)
Duration Reasori Method Of Licensee System Code Component Cause & Corrective Action To llours (2)
Shutting Down Event Report #
(4)
Code Prevent Recurrence (C&CA) -
Reactor (5)
(3)95-003 04/15SS S
744.0 C
4 N/A N/A N/A Scheduled Refueling Outage #7 extended for approximately 18 days because of generator stator leak repairs.
I 2
3 4
5 F: Forced Reason:
Method:
Exhibit G - InstnidSns for Preparation of Exhibit 1 - Same Source S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry Sheets foi Licensee Event B-Maintenance or Test 2-Manual Scram Report (LER) File (NOREG-0161)
C-Refueling 3-Automatic Scram D-Regulatory Restrictim 4-Continued E-Operator Training &
5-ReducedIcad Licensing Examination 6-Other F-Admini<eative G-Operstanal Enw (Explain)
H-Other (Explain) l l
.