ML20084L159
| ML20084L159 | |
| Person / Time | |
|---|---|
| Site: | Midland |
| Issue date: | 04/27/1984 |
| From: | Jackie Cook CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.) |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| 83-02-#5, 83-2-#5, OL, OM, NUDOCS 8405140362 | |
| Download: ML20084L159 (4) | |
Text
, - -
o 4
Colsumers Power James W Cook O
llf Vice President - Projects, Engineering i
and Construction General offices: 1945 West Parnali Road, Jackson, MI 49201 * (517) 788-0453 April 27, 1984 83-02 #5 Mr J G Keppler, Regional Administrator US Nuc1 car Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 MIDLAND ENERGY CENTER PROJECT DOCKET NOS 50-329 AND 50-330 NSSS AND B0P INSTRUMENT CABINETS FILE:
0.4.9.74 SERIAL:
30021
References:
J W Cook letters to J G Keppler, same subject
- 1) Serial 20697, dated February 11, 1983
- 2) Serial 22189, dated May 16, 1983 l
- 3) Serial 23768, dated August 19, 1983
- 4) Serial 23829, dated October 31, 1983 This letter, as were the referenced letters, is an interim 10CFR50.55(c) report concerning deficiencies in the installation design of certain C1 css IE cabinets and pancis.
In the previous submittal (reference 4), Consumers Power Company reported that equipment location changes and modifications were being translated into revised documents and in one particular case, Could Motor Control Centers, the need for a design change relative to proximity concerns remained to be determined subject to seismic qualification testing by the vendor. Hence, this 10CFR50.55(e) report would remain open until such final design changes were confirmed.
Based upon the existing schedule, the final documentation and design modification recommendations (if required) from Could will not be received until the fourth quarter of 1984. Therefore, a final report will not be submitted until completion of this activity.
A point of clarification is also required on the attached MCAR 67, Final Report to reference 4.
On page 2, a statement referring to BC-TOP-4A j
(Topical Report, Seismic Analysis of Structures and Equipment for Nuclear Power Plants, Rev 3, November 1974), states: The minimum clearance between any two structures, components or equipment is maintained at twice the absolute sum of the predicted displacements of the two items under consideration.
8405140362 B40427 i
nq PDR ADOCK 05000329 0 g4
[
gp PDR MM j
S OC0484-0022A-MP01
2 Serial 30021 83-02 #5 This refers to a screening limit and not an acceptance criteria that Bechtel utilized to first identify equipment that was subject to further evaluation which formed the basis of the attached Table to the MCAR 67 report.
Equipment which did not pass the acreening limit was dispositioned as described in item 1 of the Corrective Action portion of MCAR 67.
Equipment is considered acceptable if detailed analysis supported a clearance less that the screening limit described above.
Consumers Power Company will submit another report, either interim or final, by December 21, 1984.
JWC/JJZ/cd CC Document Control Desk. NRC DSHood, NRC Office of NRR Washington, DC RJCook, NRC Resident Inspector 1NPO Records Center Midland Nuclear Plant OC0484-0022A-MP01 w
3 i
e i
Sorial 30021 83-02 f5 OM/0L SERVICE LIST Mr Frank J Kelley Atomic Safety & Licensing Attorney General of the Appeal Board State of Michigan U S Nucicar Regulatory Commission Ma Carole Steinberg Washington, DC 20$55 Assistant Attorney General Environmental Protection Division Mr C R Stephens (3) 720-Law Building Chief. Docketing & Services Lansing, MI 48913 U S Nucicar Regulatory Commission Office of the Secretary Washington, DC 20555 Mr Myron M Cherry, Esq Suite 3700 Ms Mary Sinclair Three First National Plaza 5711 Summerset Streat Chicago, IL 60602 Midland, MI 48640 Mr Wendall 11 Marshall Mr William D Paron. Esq RFD 10 counsel for the NRC Staff Midland, MI 48640 U S Nuclear Regulatory Commission Washington, DC 20555 Mr Charles Bechhoofor. Esq Atomic Safety & Licensing Atomic Safety & Licensing Board Panel Board Panel U S Nuclear Regulatory Commission U S Nuclear Regulatory Commission East-West Towers Room E-413 Washington, DC 20555 Bethesda, MD 20014 Hs Barbara Stamaris Dr Frederick P Cowan 5795 North River Road 6152 N Verde Trail Rt 3 Apt B-125 Freeland, MI 48623 Boca Raton, FL 33433 Dr Jerry liarbour Mr Fred C Williams Atomic Safety & Licensing Isham, Lincoln & Beale Board Panel 1120 Connecticut Ave, NW, Suite 840 U S Nucicar Regulatory Commission Washington, DC 20036 East-West Towers, Room E-454 Bothesda, MD 20014 Mr James E Brunner, Esq Consumers Power Company Mr M I Miller Esq 212 West Michigan Avenuo Isham, Lincoln & Bealo Jackson, MI 49201 Three First National Plaza i
i OC0484-0022A-MP01
r 4
serial 30021 83-02 f5 Mr D F Judd Mr John Demeester, Ieq Babcock & Wticox Dow Chemical Building PO Box 1260 Michigan Division Lynchburg, VA 24505 Midland, M1 48640 Mr Steve Gadler, Esq 2120 Carter Avenue St Paul, MN 55108 Me Lynne Bernahei Covernment Accountability Project Mr F Bobert Brown 1901 Q Street, NW Clark, Klein & Beaumont Washinaton DC 20009 1600 First Federal Bids Woodward Ave Detroit, MI 48226 3/14/84 OC0444-0022A-MF01 l