Monthly Operating Rept for Mar 1984
ML20084E467
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 03/31/1984
From: Cowan K, Martin J
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
NUDOCS 8405020293
Download: ML20084E467 (4)


Text

'

1 OPERATING DATA REPORT DOCKET NO. 50-397 UNIT WNP-2 DATE 04/11/84 COMPLETED BY K.D. COwan TELEPHONE (509) 377-2501 X4736 OPER ATING STATUS

1. REPORTING PERIOD: March 1984 GROSS Hours IN REPORTING PERIOD: 0 ,
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): I66 MAX. DEPEND. CAPACITY (MWe Net): 1100 OESIGN ELECTRICAL RATING (hNet): 1100
3. POWER LEVEL TO WHICH RESTRICTED (IP ANY) (MWe Netti 5% Gross MW
4. REASONS FOR RESTRICTION (IP ANYl: Initial plant Startup and Power ascension test phase THIS MONTH YM TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR WAS CRITICAL ...............

0 13.93 13.93

6. REACTOR RESERVE SHUTOOWN HOURS . . . . . . . . . . . . . . . . . . .

0 0 0

7. HOUR S G E N E R ATOR ON U N E . . . . . . . . . . . . . . . . . . . . . . . . . .

0 0

8. UNIT RESERVE SHUTDOWN HOURS .....,,.......... ,,,,

0 0 0

9. GROSS THERMAL ENERGY GENERATED (MWHI ..............

0 0 0

10. GROSS ELECTRICAL ENERGY GENERATED (MWH) . . . . . . . . . . . . .

0 0 0

11. NET ELECTRICAL ENERGY GENERATED (MWM) .............,

0 0 0

12. R EACTOR SE RVICE F ACTOR . . . . . . . . . . . . . . . . . . . . . . . . . . . A
13. R EACTOR AVAILAglLITY F ACTOR . . . . . . . . . . . . . . . . . . . . . . .  !
14. U NI T SE R VICE P ACTOR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . N/A N/A N/A
15. UNIT AV AILA51 LITY F ACTOR , . . . . . . . . . . . . . . . . . . . . . . . . . /A N/A N/A
16. UNIT CAPACITY FACTOR (Using MOCl . . . . . . . . . . . . . . . . . . . . . /A
17. UNIT CAPACITY FACTOR (Using Design MWel . . . . . . . . . . . . . . . . . N/A N/A N/A
18. UNIT FO RCED OUTAGE M ATE , . . . . . . . . . . . . . . . . . . . . . . . . . N/A N/A N/A i 19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE. DATE. AND OURATION OF EACHl: 05/22/84, 06/18/84, and 07/04/84 all for maintenance during power ascension phase.
20. IF SHUT DOWN AT END OF REPORT PERIOD. ESTIMATED OATE OF STARTUP: 04/10/84
  • 21. UNITS IN TEST STATUS IPRIOR TO COMMERCIAL OPERATIONI: FORECAST ACHIEVED INITIAL CRmCAUTY 01/16/84 01/16/84 INITIAL ELECTRICITY 05/15/85 l COMMERCIAL OPERATION 08/15/84 l

l 8405020293 B40331

  • WNP-2 PDR ADOCK 05000397 R PDR

$h k

IXX'KET NO. 50-397 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME W -2 .

IJATE 04/11/84 COMPLETED BY K.D. Cowan REPORTMON'ni March 1984 TELEPilONE (509) 377-2501 X4/36_

00ETHOD OF

. TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO. DATE S: SCHEDULED (HOURS) REASON (1) REDUCING POWER (2F CORRECTIVE ACTIONS / COMMENTS 840123 S 1144.0 B 1 Continuation of shutdown i

sumaanRY: Plant remained in cold shutdown for perforniance of various tests associated with plant preoperational test program and maintenance.

(l) REASON E: OPERATOR TRAINING AND (2) METIIOD A: EQUIPMENT FAILURE (EXPLAIN) LICENSE EXAMINATION I: MANUAL 3: MAltfr.ORTIST F: ADMINISTRATIVE 2: M ANIf AL SCRAM.

C: REFUELING G: OPI RATIONAL FRROR (EXPLAIN) 3: AUIOMATICSCRAM D: REGULATORY RESTRICnON II: OTIIER (EXPLAIN) 4: 01Ill:R (EXPLAIN)

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-397 UNIT WNP-2 DATE 04/11/84 COMPLETED BY K.D. Cowan TELEPHONE (509) 377-2501 IU36 MONTH March 1984 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe Net) 1 0 17 0 2 0 ja 0 3 0 i, 0 4 0 3 0 5 0 21 0 6 0 a 0 7 0 n 0 8 0 24 0 9 0 g o 10 0 2g 0 11 0 27 0 12 0 2s 0 13 0 29 0 14 0 3a o 15 0 31 0 16 0 INSTRUCTIONS On this form, list the awrap dady unit power lewl in MWeNet for each dayin the reporting month. Compute to the nearest whole mopwatt.

Thew figures wdl be used to plot a paph for each reporting month. Note that wiwn maximum dependable capacity used for the net electrical rating of the unit, there may t,e occasions when the daily awray power lew! excuds the 100% line (or the restricted power lew! line). In such cases, the awrap daily unit power output sheet should be footnoted to explain the apparent anomaly.

T O

Washington Public Power Supply System P.O. Box 968 3000 GeorgeWashingtonWay Richland. Washington 99352 (509)372-5000 Docket No. 50-397 April 11, 1984 l

Director Office of Resource Management U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Sir:

Subject:

NUCLEAR PROJECT NO. 2 .

MONTHLY OPERATING REPORT Transmitted herewith is the Monthly Operating Report as required 'uy our Technical Specifications.

Very truly yours, Cy -

D. Mart'in (927M)

NP-2 Plant Manager JDM:1p Enclosure cc: Mr. John B. Martin - NRC, Region V Mr. A. D. Toth - NRC, WNP-2 Site Y*