Application for Amends to Licenses DPR-77 & DPR-79.Amends Would Conditionally Exempt Eol Mtc Measurement Required in TS SR 4.1.1.3
ML20083Q788
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 05/19/1995
From: Shell R
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20083Q790 List:
References
TVA-SQN-TS-95, TVA-SQN-TS-95-0, NUDOCS 9505260208
Download: ML20083Q788 (3)


Text

--- . - - - - . --- -

t i,

IUA Tennessee Va le t if Post Othce Box 2000. Soddy Daisy Tennessee 37379 l May 19,1995 i

TVA-SON-TS-95-07 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

In the Matter of ) Docket Nos. 50-327 l Tennessee Valley Authority ) 50-328 SEQUOYAH NUCLEAR PLANT (SON) - TECHNICAL SPECIFICATION (TS)

CHANGE 95-07, " CONDITIONAL EXEMPTION TO END-OF-LIFE (EOL)

MODERATOR TEMPERATURE COEFFICIENT (MTC) SURVEILLANCE MEASUREMENT" In accordance with 10 CFR 50.90, we are enclosing an amendment to Licenses DPR-77 and DPR-79 to change tht. TSs of SON Units 1 and 2. The proposed TS change will conditionally exempt the EOL MTC measurement required in TS Surveillance Requirement 4.1.1.3. Cemplementary changes to the administrative section of the TS are also provided. This change is similar to that  ;

proposed by D.C. Cook Nuclear Plant o;; July 26,1994.

The proposed TS change is identified in Enclosure 1. The justification for the proposed TS change is provided in Enclosure 2. A proposed determination of no significant safety hazards consideration performed pursuant to 10 CFR 50.92 is provided in Enclosure 3. Enclosure 4 provides a draft with the necessary changes to the Core Operating Limits Report for Units 1 and 2. The Westinghouse Electric Corporation Safety Evaluation Check List 93-117, R1 is supplied in Enclosure 5 for additional supporting documentation.

t 9505260208 950519 PDR ADOCK 05000327 p PDR h

r i .

U.S. Nuclear Regulatory Commission Page 2 May 19,1995 SON Unit 2 is expected to attain a boron concentration of 300 parts per million in November 1995. Therefore, TVA is requesting NRC approval prior to this time so the benefits afforded by this TS change can be utilized for this operating cycle.

TVA requests a 45-day implementation period for this TS change following issuance.

Please direct questions concerning this issue to W. C. Ludwig at (615) 843-7460.

Sincerely, ho Y.

R. H. Shell Manager SO.N Site Licensing Sworn t,p and subsc i ed before me t 's /97 day of d> A 1995

~

DY11 h > d JM Notf ry'P'ublic My Commission Expires 2//

Enclosures cc: Seu page 3

c __

U.S. Nuclear Regulatory Commission Page 3 May 19,1995 (Enclosures):

Mr. D. E. LaBargo, Project Manager Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland '20852-2739 Mr. Michael H. Mobley, Director (w/o Enclosures)

Division of Radiological Health 3rd Floor L & C Annex 401 Church Street Nashville, Tennessee 37243-1532 NRC Resident inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road Soddy-Daisy, Tennessee 37379-3624 Regional Administrator U.S. Nuclear Regulatory Commission Region ll 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323-2711 i

i