Monthly Operating Rept for Mar 1984
ML20083P885
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 03/31/1984
From: Mineck D, Putnam K
IES UTILITIES INC., (FORMERLY IOWA ELECTRIC LIGHT
To:
NRC OFFICE OF ADMINISTRATION (ADM), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
DAEC-84-209, NUDOCS 8404200233
Download: ML20083P885 (8)


Text

..

e OPERATING DATA REPORT 050-0331 DOCKET NO.

DATE 04-15-84 COMPLETED BY Ken Putnam TELEPHONE 319-851-7456 OPERATING STATUS Notes

1. Unit Name:

Duane Arnold Enerav Center

2. Reporting Period:

March, 1984 1658

3. Licensed Thermal Power (MWt):

565

4. Nameplate Rating (Gross MWe):
5. Design Electrical Rating (Net MWe):

538 545

6. Maximum Dependable Capacity (Gross MWe):

515

7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
9. Power Level To Which Restricted. If Any (Net MWe):

~

10. Reasons For Restrictions. If Any:

This Month Yr to-Date Cumulative 744.0 2184.0 80328.0

11. Hours In Reporting Period
12. Number Of Hours Reactor Was Critical 744.0 2018.6 57953.6
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 1992.9 56435.6
15. Unit Reserve Shutdawn Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1169208 3044616 70793178
17. Gross Electrical Energy Generated (MWH) 399833 1036674 23730731
18. Net Electrical Energy Generated (MWH) 377569 978578 22217169
19. Unit Service Factor 100.0%

91.3%

70.3%

20. Unit Availability Factor 100.0%

91.3%

70.3%

21. Unit Capacity Factor (Using MDC Net) 98.5%

87.0%

53.7%

i

22. Unit Capacity Factor (Using DER Net) 94.3%

83.3%

51.4%

23. Unit Forced Outage Rate 0.0%

8.8%

17.0%

24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Each):

Surveillance outage April 13, 1984 lasting approximately 10 days to two weeks.

Refueling or mini-outage September, 1984 of a. duration to be determinea.

25. If Shut Down At End Of Report Period. Estimated Date of Startup:

4 8404200233 840331 p @q PDR ADDCK 05000331 R

PDR-I m,,,

AVERA E DAILY UNIT POWER LEVEL DOCKET NO. 050-0331 LNIT Duane Arnold Energy Center DATE 04-15-84 COMFLETED BY Kenneth S. Putnar, TELEPHONE 319-851-7306 MONTH March 1984 i

DAY AVERAE DAILY POWER LEVEL DAY AVERAE DAILY POWER LEVEL (MWe-Net)

(MWe-Net) 1 511 17 514 2

516 18 500 3

513 19 515 4

4 478 20 513 5

512 21 512 6

515 22 509 7

514 23 512 8

515 24 500 9

515 25 440 to 515 26 508 i

11 491 27 507

- 12 512 28 510 13 515 29 512 14 513 30 512 15 512 31 507 16 514-lNSTRUCT10NS On this formet, list the everego delly unit power level in NWe-Net for each day In the report ing month. Compute to - l the neerest whole mogowatt..

UNIT SHUTDOONS AND PODER REDUCTIONS Docket No.

050-0331 Unit Name Duane Arnold Eneroy Confer.

Date 4-15-84 REPORT MONTH March, 1984 Completed by Kenneth S.

Putnam Telephone 319-851-7456 Licensee Cause & Correct ive

.No.

Dato' Event Action to Report #

Provent Recurrence NONE.

t if 2

3 4

'F: Forced:

Reason:

Method:

Exhibit G-Instruct ions S:. Scheduled A-Equipment Failure (Explain) 1-Manual f or Preparat ion of Data B-Maintenance or Test 2-Manual Scram.

Entry Sheets for Licensee C-RefueIIng.

3-Automatic Scram.

Event Report (LER) File (NURE@

D-Regulatory Restriction 4-Other(Explain) 0161)

E-Operator-Training &-License Examination F-Administrative 5

G-Operational Error (Explain)-

Exhibit 1-Same Source

"(9/77)

'H-Other(Explain)

Docket No.

050-0331 Unit Duane Arnold Energy Center Date March 15, 1984 MAJOR SAFETY RELATED MAINTENANCE Completed by Kenneth S.

Putnam Telephone 319-851-7456 DATE SYSTEM COMPONENT-DESCRIPTION 03-01-84 l ADS Roset Switch HS-4462 Replaced Switch (LER 84-012) 03-06-84

-HPCI HV2201 Turbine Stop Valve Replaced hydraulle oil seals in valve operator (LER 84-012) 03-27-84 Fire Protection System IP-49 Fire Pump Rebuilt Turbocharger, replaced head gasket 03-28-84' Fire Protection System IP-48 Electric Fire Pump Replaced Packing

~

Docket No. 050-0331 Unit Duane Arnold Energy Ctr Date April 15, 1984 Completed by Ken S.

Putnam Telephone 319-851-7456 REFUELING INFORMATION 1

Name of facility.

A.

Duane Arnold Energy Center 2

Scheduled date for next refueling shutdown.

J A.

October 1,

1984 (May be deferred until January, 1985.)

3 Scheduled date for restart following refueling.

A.

December, 1984 4

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

Yes.

A.

Reload license submittal Including power uprate.

B.

Additional MAPLHGR curves for new fuel bundles being Introduced for Cycle 8 5

Scheduled date(s) for submitting proposed llconsing act ion and supporting Information.

July 1984 6

Important licensing considerations associated with refueling, e.g.,

new or different fuel design or supplier, un rev i ewed design or performance analysis methods, significant changes In fuel design, new operating procedures.

None 7

The number of fuel assemblies (a) in the core and (b) In the spent fuel storage pool.

A.

a) 368 b) 576 8

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity _that has be e n requested or is planned, in number of fuel assemblies.

A.

2050 9.

The projected date of.the.last refuollng that can be d i s ch a rg ed to the spent fuel pool assuming the pr es e nt licensed capacity.

A.

1998

a*

~

Docket No. 055-0331 L

Unit Duane Arnold Energy Ctr Date March, 1984 Completed by Ken Putnum Telephone 319-851-7456 NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE 03-01-84 Normal plant operation at 550 MWe (gross).

03-01-84 Surveillance testing found the "B" side ADS timer would not initiate. At 1740 hours0.0201 days <br />0.483 hours <br />0.00288 weeks <br />6.6207e-4 months <br /> ADS was declared inoperable commencing a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> LC0 as HPCI was concurrently inoperable.. An unusual event was declared and a controlled power reduction initiated.

At 2230 hours0.0258 days <br />0.619 hours <br />0.00369 weeks <br />8.48515e-4 months <br /> repair and testing of "B" side ADS were completed cancelling the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> LC0 and unusual event. 7 day LC0 on HPCI inoperability (begun 2-29-84) continued.

(LER 84-012) 03-03-84 At 2326 hours0.0269 days <br />0.646 hours <br />0.00385 weeks <br />8.85043e-4 months <br />, reduction of reactor power with recirculation flow was-commenced for test performance and repair work on CV-1237, extraction steam dump valve on 6A/6B feedwater heaters.

03-04-84 Increased reactor power after completion of repairs and tests at' 0302 hours0.0035 days <br />0.0839 hours <br />4.993386e-4 weeks <br />1.14911e-4 months <br />.

03-05-84 Cummulative exposure of certain fuel bundle nodes exceeded the exposure of current MAPLHGR curves in T.S. Section 3.12. A Technical Specification change (RTS-163) is pending.

03-06-84 Repairs and testing of HPCI completed. HPCI declared operable cancelling 7 day LCO at 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br />.

I 03-20 At 0120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br />, during surveillance testing, the RHR discharge:

piping had a momentary decrease in pressure,-causing an RHR low pressure alarm.

03-21-84 At 1820 hours0.0211 days <br />0.506 hours <br />0.00301 weeks <br />6.9251e-4 months <br />, alarms were received-from ARM's on the refuel:

floor. The alarms were. caused by a loss of a common power-supply.

At 2007 hours0.0232 days <br />0.558 hours <br />0.00332 weeks <br />7.636635e-4 months <br />, power supply operability was restored.

03-24 Commenced dropping power at 2154-hours for' heater bay inspection and inspection of turbine building operations deck.

03-25-84

-Inspections completed, canmenced increasing powerjat 0345 hours0.00399 days <br />0.0958 hours <br />5.704365e-4 weeks <br />1.312725e-4 months <br />.

i 03-31-84

. Normal plant operation at 544 MWe'(gross).

t w

T c

-4

+

b/710 n

8' \\ /

C 5g DUANE ARNOLD ENERGY CENTER PALO, IOWA iowa Cktnc boht and power company PRINCIPAL STAFF RA

[}iO

_ b$

5/RA Aw to Ebl^

To:

Routing ago

'ws l

MP From:

B. Miller r

Subject:

Concurrence with outgoing correspondence

Reference:

Monthly Operating Report for March,1984, DAEC-84-21 Concurrence with and release of refer need cument is requested.

f J

5,, E d u e -

originator

/

,_,1.,,

(e,,vor <I,,.m ->off.,.-/ i. G / ue Technical Support Supervisor en, -) 1) v v

C. /& A Department Supervisor ShtJ/- (e.- 4.),

Department Supervisor n 3./,9),rf A.P.S.-Technical Support c/IMM

(, p,,,,,o A.P.S.-Operations

- 3,.

Ops. Comm. Chairman WM/kp i

g1b l

l

Iowa Electric Light and Ibwer Company April 15, 1984 DAEC-84-209 Director, Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission i

Washington, D. C.

20555 Attn: Document Control Desk

Subject:

Duane Arnold Energy Center Docket No. 50-331 Op. License DPR-49 March,1984 Monthly Operating Report

Dear Sirs:

Please find enclosed 12 copies of the Duane Arnold Energy Center Monthly Operating Report for March,1984.

The report has been prepared in accordance with the guidelines of Regulatory Guide 1.16 and distribution has been made in accordance with DAEC Technical Specifications, Appendix A, Section 6.11.1.c and Regulatory Guide 10.1.

Very truly yours, Daniel L. Mineck Plant Superintendent - Nuclear Duane Arnold Energy Center DLM/KSP/kp*

Enclosures File A-118d, TE-5 cc: Director, Office of Inspection Mr. Phillip Ross and Enforcement U. S. Nuclear Regulatory Commission U. S. Nuclear Regulatory Comission Maryland National Bank Bldg.

Region III Washington, D. C.

20555 799 Roosevelt Road Glen Ellyn, IL 60137 (1)

NRC Resident Inspector Director, Office of Management and Mr. Dennis Murdock Program Analysis Central Iowa Power Cooperative U. S. Nuclear Regulatory Comission Marion, IA 52302 Washington, D. C. 20555 (1)

Mr. George Toyne, Gen. Mgr.

O. S. Nuclear Regulatory Commission Corn Belt Power Cooperative ATTN: Mr. M. Thadani Box 508 Phillips Bldg.

Humboldt, IA 50548 Washington, D. C. 20555

@Q INP0 Records Center 1100 Circle 75 Parkway q/

Suite 1500 g

Atlanta, GA 30339 q'