Advises That Corrective Actions Resulting from Violation Noted in IE Insp Rept 50-352/83-19 Will Be Completed by 840630
ML20083N600
Person / Time
Site: Limerick 
Issue date: 03/26/1984
From: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8404190235
Download: ML20083N600 (1)


Text

.

i p

l PHILADELPHIA ELECTRIC COMPANY 23O1 M ARKET STREET P.O. BOX 8699 1881 -1981 PHILADELPHIA PA.19101 JOHN S KEMPER V IC E-PR ESID E N T RM4stNEE W8MCe AND Ritt A RCH March 26, 1984 Mr. Thomas E. Murley, Director United States Nuclear Regulatory Commission Office of Inspection and Enforcement, Region 1 631 Park Avenue King of Prussia, Pa.

19406

Subject:

US NRC IE Region 1 Letter dated January 10, 1984 Re: Site Inspection of October 17-November 30, 1983 Inspection Report No. 50-352/83-19 and 50-353/83-07

Reference:

J. S. Kemper Letter to T. E. Murley, dated 2/17/84 File:

QUAL 1-2-2 (352/83-19)

Dear Mr. Murley:

In our response to Violation 2 of Inspection Report No. 50-352/83-19 we committed to a follow-up response by 3/31/84. However, the corrective action stated in our previous response has not yet been completed. We now expect to complete the corrective actions by 6/30/84 and will inform you of our progress at that time.

Should you have any questions concerning this item, we would be pleased to discuss them with you.

Sincerely,

[

C J. S. Kemper FJC:am cc: