Informs That Milestone Dates for Submittal of Final Draft PRA to Nrr,Receipt of NRC Comments & Submittal of Camera Ready Copy Reset for 830204,11 & 18,respectively.Delay Due to Need to Divert Resources to Other Projects
ML20083L888
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 12/22/1982
From: Papazoglou I
BROOKHAVEN NATIONAL LABORATORY
To: Chelliah E
Office of Nuclear Reactor Regulation
Shared Package
ML20083L892 List:
References
NUDOCS 8212290219
Download: ML20083L888 (1)


Text

_ _ _ _ - _ _ _ -

BROOKHAVEN NATIONAL LABORATORY

(). l ASSOCIATED UNIVERSITIES, INC.

Upton. Long Island. New York 11973 (516) 282s Department of Nuclear Energy ' FTS 666' 2435 December 22, 1982 Erulappa S. Chelliah Reliability and Risk Assessment Branch Division of Safety Technology Mail Stop 216 U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Erul:

Owing to the NRC need for BNL personnel to divert resources to work on other projects in support of the Indian Point hearing, the milestones for the BNL final report on the " Review of the Limerick PRA" must change. As per discussions between R. A. Bari (BNL) and F. Coffman (RRAB) this diversion of resources will result in a forward shift of the milestone dates. As per our discussions the new milestone dates are as follows:

Submission of final draft to NRR February 4,1983 Receipt of NRC comments on final draft February 11, 1983 Submission of camera ready copy February 18, 1983 If you have any comments please let me know as soon as possible.

Best'regards, pi w Ioannis A. apazosklou, Gro w

Leader Risk Evaluation Group IAP/dm cc: W. Kato ,

R. Bari R. Hall W. T. Pratt A. Thadani A. Schwencer F. Coffman ' lT' k.