-_ - _ . _ _ _ _ _ _ - - _ _ _ - _ _ - - - - _ - - . _ _ _ _ _ - - - _ _ - _ _

Harry Tauber Group Vice President j 2000 Second Avenue Ed*

i son awer December 12, 1983 EF2 - 66,714 4

Director of Nuclear Reactor Regulation Attention: Mr. B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Youngblood:

Reference:

Enrico Fermi Atomic Power Plant, Unit 2 NRC Docket No. 50-341

Subject:

Revised Fuel Load Date for Fermi 2 This letter is to confirm that Detroit Edison has revised its estimate for the fuel load date of Fermi 2 to June 30, 1984. Despite this change in schedule date, Detroit Edison is making every possible effort to take the steps necessary to better this schedule.

Accordingly, we request your continued assistance and cooperation in completing the remaining NRC staff reviews and resolution of open items in a timely manner to support our effort.

Sincerely, cc: Mr. P. M. Byron Mr. M. D. Lynch f