MONTHYEARML20217G1521999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Wolf Creek Generating Station.With ML20212A0251999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Wolf Creek Generating Station.With ML20210R5741999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Wolf Creek Generating Station ML20210R5921999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Wolf Creek Generating Station ML20209H0821999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Wolf Creek Generating Station ML20210R5871999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Wolf Creek Generating Station ML20195K1021999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Wolf Creek Generating Station ML20195K1071999-04-30030 April 1999 Revised MOR for Apr 1999 for Wolf Creek Generating Station ML20206P8261999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Wcgs.With ML20210R5841999-04-30030 April 1999 Revised Monthly Operating Rept for Apr 1999 for Wolf Creek Generating Station ML20205Q0761999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Wolf Creek Generating Station.With ML20207K5991999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Wolf Creek Generating Station.With ML20199E6531998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Wolf Creek Generating Station.With ML20198D7321998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Wolf Creek Generating Station.With ML20195D1791998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Wolf Creek Generating Station.With ML20154L4591998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Wolf Creek Generating Station.With ML20151W1491998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Wcgs.With ML20237B0841998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Wolf Creek Generating Station ML20236P3441998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Wolf Creek Generating Station ML20236P3481998-05-31031 May 1998 Corrected Page of MOR for May 1998 for Wolf Creek Generating Station ML20249A0171998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Wolf Creek Generating Station ML20247H0901998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Wolf Creek Generating Station ML20216F6101998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Wolf Creek Generating Station ML20216G1971998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Wolf Creek Nuclear Operating Corp ML20202H0721998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Wolf Creek Generating Station ML20198P1931997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Wolf Creek Generating Station ML20197J0321997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Wolf Creek Generating Station ML20199C7081997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Wolf Creek Generating Station ML20211N7161997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Wolf Creek Generating Station ML20216H9561997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Wolf Creek Generating Station ML20210M4401997-07-31031 July 1997 Monthly Operating Rept for July 1997 for WCGS ML20148L8781997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Wolf Creek Generating Station ML20141H7541997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Wolf Creek Generating Station ML20137W5021997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Wolf Creek Generating Station ML20147E5931997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Wolf Creek Generating Station ML20134M9821997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Wolf Creek Generating Station ML20133M3991996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Wolf Creek Generating Station ML20132C0871996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Wolf Creek Generating Station ML20134L7281996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Wolf Creek Generating Station ML20128N0301996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Wolf Creek Generating Station ML20134C1291996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Wolf Creek Generating Station ML20134C1371996-07-31031 July 1996 Revised Monthly Operating Rept for Jul 1996 for Wolf Creek Generating Station ML20116M5431996-07-31031 July 1996 Monthly Operating Rept for July 1996 for Wolf Creek Generating Station ML20116M5471996-07-0808 July 1996 Revised Monthly Operating Rept for June 1996 for Wolf Creek) Generating Station ML20134C1321996-06-30030 June 1996 Revised Monthly Operating Rept for June 1996 for Wolf Creek ML20115F1211996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Wolf Creek Generating Station ML20112J1781996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Wolf Creek Generating Station.W/Undated Ltr ML20115F1251996-04-30030 April 1996 Monthly Operating Rept Revisions for April 1996 for Wolf Creek Generating Station ML20117D7701996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for Wolf Creek Generating Station ML20107D8971996-03-31031 March 1996 Monthly Operating Rept for March 1996 for WCGS 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217G1521999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Wolf Creek Generating Station.With ML20211N0161999-09-0202 September 1999 Safety Evaluation Supporting GL 95-07 to License NPF-42 ML20212A0251999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Wolf Creek Generating Station.With ML20217P6451999-08-30030 August 1999 Requests Commission Approval to Publish Encl Pr,Rg & SRP & to Issue Encl Ltr to Parties of Wolf Creek Transfer Proceeding Re Disposition of Existing Antitrust License Conditions in Event OL Transfer Approved ML20210R5741999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Wolf Creek Generating Station ML20210J1561999-07-29029 July 1999 Rev 0 to Wolf Creek Generating Station,Unit 1 Pressure & Temp Limts Rept ML20210R5921999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Wolf Creek Generating Station ML20209H0821999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Wolf Creek Generating Station ML20195D5261999-06-0202 June 1999 Safety Evaluation Approving Proposed ISI Program Alternative for Limited Reactor Vessel Shell Weld Exams & Relief Request from Requirements of ASME Code,Section XI ML20210R5871999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Wolf Creek Generating Station ML20195K1021999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Wolf Creek Generating Station ML20195K1071999-04-30030 April 1999 Revised MOR for Apr 1999 for Wolf Creek Generating Station ML20206P8261999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Wcgs.With ML20196L3401999-04-30030 April 1999 Rev 1 to WCGS Cycle 11 Colr ML20210R5841999-04-30030 April 1999 Revised Monthly Operating Rept for Apr 1999 for Wolf Creek Generating Station ML20205Q0761999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Wolf Creek Generating Station.With ML20207K5991999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Wolf Creek Generating Station.With ML20207K9761998-12-31031 December 1998 Annual SER 14,for Period 980101-1231, for WCGS ML20199E6531998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Wolf Creek Generating Station.With ML20195C0011998-12-31031 December 1998 Ks City Power & Light Co 1998 Annual Rept & Financial Statements as of 981231 & 1997 for Ks Electric Power Cooperative,Inc ML20195B9901998-12-31031 December 1998 Western Resources Annual Rept for 1998 ML20198D7321998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Wolf Creek Generating Station.With ML20195H9801998-11-17017 November 1998 Safety Evaluation Supporting Proposed Changes to WCGS Radiological Emergency Response Plan ML20195E7591998-11-10010 November 1998 WCNOC Proposed PASS Function Reduction ML20195D1791998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Wolf Creek Generating Station.With ML20154L4591998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Wolf Creek Generating Station.With ML20153G2771998-09-30030 September 1998 Rev 1 to WCAP-15079, Wolf Creek Heatup & Cooldown Limit Curves for Normal Operation ML20153G2851998-09-30030 September 1998 Rev 1 to WCAP-15080, Evaluation of Pressurized Thermal Shock for Wolf Creek ML20153G2691998-09-30030 September 1998 Rev 1 to WCAP-15078, Analysis of Capsule V from Wolf Creek Nuclear Operating Corp Wolf Creek Reactor Vessel Radiation Surveillance Program ML20153G7301998-09-23023 September 1998 Special Rept 98-003:on 980814,station Entered TS 3.3.3.6, Action Statment a Due to Inoperability of RVLIS B Train. Cause Has Not Yet Been Identified.Work Order 98-202813-000 Has Been Generated ML20151W1491998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Wcgs.With ML20237B7381998-08-14014 August 1998 Special Rept 98-001:on 980615,oxygen Analyzer on Wgs Was Declared Inoperable.Wgs Oxygen Analyzer OARC-1119A Was Indicating 0 Ppm on 980814 & Fluctuated Between 200 & 900 Ppm on 980615.Completed Work Order & Declared Wgs Operable ML20237B0841998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Wolf Creek Generating Station ML20236P3441998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Wolf Creek Generating Station ML20236P3481998-05-31031 May 1998 Corrected Page of MOR for May 1998 for Wolf Creek Generating Station ML20249A0171998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Wolf Creek Generating Station ML20249B2451998-05-18018 May 1998 Nonproprietary Version of Revised Chapters 4 & 5 to Rev 4 of HI-971769, Licensing Rept for Reracking of Callaway & Wolf Creek Nuclear Plants for Ue & Wcnoc. Chapters 4 & 5 Reflect Editorial Revs ML20248C3681998-05-18018 May 1998 Non-proprietary Version of Rev 4 to HI-971769, Licensing Rept for Reracking of Callaway & Wolf Creek Nuclear Plants ML20247H0901998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Wolf Creek Generating Station ML20216J7791998-04-15015 April 1998 SER Approving Requests for Relief I1R-46 Through I1R-49 & I2R-21 Submitted by Licensee on 970523.Relief for Exam Category B-A,Item B1.12,RPV Shell Welds Deferred Until Licensee Satisfies Regulations for Augmented Rv Exam ML20216C2641998-04-0606 April 1998 SER Accepting Addl Info Re GL 92-08, Thermo- Lag 330-1 Fire Barriers, for Plant ML20216F6101998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Wolf Creek Generating Station ML20217H3491998-03-31031 March 1998 SER Accepting Operational Quality Assurance Program Description Change for Wolf Creek Generating Station ML20217H7241998-03-30030 March 1998 SER Accepting Proposed Change to Operational Quality Assurance Program for Plant ML20216G1971998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Wolf Creek Nuclear Operating Corp ML20202H0721998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Wolf Creek Generating Station ML20217G4311997-12-31031 December 1997 Western Resources 1997 Annual Rept & Financial Statements for Years Ended 971231 & 1996 for Ks Electric Power Cooperative,Inc ML20203H0151997-12-31031 December 1997 Annual Operating Rept 13 for Jan-Dec 1997 ML20217G3711997-12-31031 December 1997 Kansas City Power & Light Co 1997 Annual Rept ML20216D7771997-12-31031 December 1997 Annual SER 12 for Jan-Dec 1997, for Wolf Creek Generating Station 1999-09-30
[Table view] |
Text
.,,
o_*-
i LF CREEK W@ NUCLEAR -
OPE 7 TING John A. Baitn .
Vice Presidoni operations September 12, 1991 NO 91-0241 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-137 Washington, D. C. 20555
Subject:
Docket No. 50-482: August, 1991, Monthly Operating Report I
' Gentlemen:
Attached is the August, 1991 Monthly Operating Report for Wolf Creek Generating _ Station. This submittal is being made in accordance with the requirements of Technical Specification 6.9.1.8.
Very truly yours, uC .
John A. Bailey Vice President Operations _,!
JAB /aem Attachment cc: L. L. Gundrum (NRC),'w/a A. T. Howell (NRC), w/a R. D. Martin-(NRC), w/a W. D. Rockley (NRC), w/a a109160340 91 og:3g PDF ADOCy 05000 app h 9 PD:E~
mm ee _ ,, ~ , _ s _ m ,3ie,3
_ - - - , \
Attachment to.N0 91-0241 t
NOIE CREEK NUCLEAR OPERATUG CORPORATION NOLF CREEK GDERATUG STATICN
)Df1HLY OPERATDG REPORT 10m1: August YEAR: 1991 Docket Ib. : 50-482 Facility Operating License No.: IFF-42 Report No. 78 Prepared by:
Merlin G. Williams i
1 Attachment to NO 91-0241 SmMARY
'Ihe following report highlights the operating experience of Walf Crook Generating Station for the manth of August,1991. '1his report is being provided pursuant to 'Ibchnical Specification 6.9.1.8.
I.
SUMMARY
OF OPERATI!G EXPERIDCE
= '1he unit operated at or near 100t p:xer throughout the period of August 1-17, 1991. Power began ranping 60wn as the coastdown to Refuel V ms cxxmenced August 18,1991 at 'J700. At nanth's end power had been reduced to 89% and the unit had operate.1 continuously for 467 days.
-II. MMOR SAFETIT RSATED MAINTDalCE ACTIVITIES No najor safety related naintenance ws perfornal during the nonth of August, 1991.
Wolf Creek Generating Station Monthly Operating Report August 1991 Page 1 of 5
Attachment to 140 91-0241 OPDIATIIG DATA RE1HtT DOCKER 10, 50-482 WJLF CREEK GE24DIATIIG STATION HOLF CREEK NUCLFAR OPHIATIIG 03UGIAT10N DATE 09-01-91 CCMPIEfED BY_& Willir;e TELET'110NE 316-364-8831 OPDIATIlO STAltlS
- 1. Reporting Period: Auentst , 1991 G3 0ss Iburs in Reporting Period: 744
- 2. Currently Authorized Power Level (!Nt):_3411 Max. Depend. Capacity (MWe-Net): 1135 Design Electrical Rat.ing (MWe-lbt): 1170
- 3. Pwer Invol to Milch Restricted (If Any)(MWo-lbt): N/A
- 4. Reasons for restriction (If Any): N/A This Month Yr. to Date Cunnlative
- 5. Numtrar of Hours Reactor was Critical 744,0 5,831.0 43,226.5
- 6. Rmetor Reserve Shutdown Iburs 0.0 0.0 339.8
- 7. Iburs Generator on Line 744.0 5,831.0 42,654.8
- 8. thrit Reserve Shutdown Iburs 6.0 0.0 0 . 0__
- 9. Gross Themm1 Energy Generated (MI) 2,466,381, 16,807.469 138,872,494
- 10. Gross Electrical Energy Generated (!Nii) _ 839,625 5,768,597 48.2J83,366
- 11. Net Electrical Energv Generated (MWil) 801,668 5.490,28J 46,087,143
- 12. Reactor Service Factor 100.0 100.0 02.3
- 13. Reactor Availability Factor 100.0 100.0 _
82.9
- 14. Unit Service Factor 100.0 100.0_ 81.2
- 15. Unit Availability Factor 100.0 100.0 81.2
- 16. Unit Capacity Factor (Using MDC) 94.9 83.0 77.6
- 17. Unit Capacity Factor (Using Design MWe) 92.1 80.5 75.0
- 18. Unit Forced Outage Rate 0.0 0.0 3.5
- 19. Shutdowns Schoduled Over Next 6 Months (2ype, Date, and Duration of each): Refueling Outage on Septanber 19, 1991 for 75 days.
- 20. If Shut Dawn at End of Report Pericd, Estinnted Ihte of Startup: N/A Wolf Creek Generating Station Monthly Operating Report August 1991 Page 2 of 5
Attachment to NO 91-0241 AVERIGE DAIuY UNIT POWER LEVEL DOCKET 10. 50-482 NOLF CREEK GENERATDG STATIM NOLF CREEK NLCLEtJ1 OPERATI!G 00RPORATICN DATE 09-01-91._
OCNPLL'IED BY M. Williams
_1-TELEPIDF 316-364-8831
}CNIH August, 1991 DAY AVERIGE DAILY POWD1 LEVEL DAY AVER 1GE DAILY POWER IREL (MWe-Not) (MWe-Net) 1 1111 17 1105
-2 1109 18 1100 ,
3 1108 19 1092 4 1109 20 1092 5 1104 21 1086
- 6. 1099 22 1066 .
7 -_ 1097 23 1057 8 1104 24 1048 9 _. 1106 25 1037 10 1110 26 1024 11: 1109 27 1017 I
12 1111 28 1007 13 1111 29 997 14 1108 30 988 15 1105 31 978
- 16 1108 Wolf Cmek Generating Station Monthly Operating Report August 1991 Pago 3 of 5
. .c s
?
UNIT SHUTDOWN AND POWER REDUCTIONS DOCKE' NO.- 50-482 I
, Q WOLF CREEK GENERATING STATION 5 WOLF CREEK NUCLEAR OPERATING CORPORATION * @
DATE 09-01-91 c+
COMPLETED BY M. Williams c.
REP 0".T MONTH August, 1991 TELEPHONE 316-364-8831 0 5-TYPE METHODS SHUTTING $*
F: FORCED DURATION REASON DOWN THE REACTOR CORRECTIVE ACTIONS / COMMENTS Wo Date S: SCHEDULED (HOURS) (1) OR REDUCING POWER (2) O 3
SUMMARY
- The unit operated thrc :ghout the month of August with no power reductions that resulted in a greater than 20%
reduction in average daily pcwer level as compared to the previous 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
- 3) REASON: A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION (2) METHOD: 1. MANUAL B: MAINTENANCE OR TEST F: ADMINISTRATIVE 2. MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3. AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: OTHER (EXPLAIN) 4. CONTINUED
- 5. REDUCED LOAD
- 9. OTHER Volf Creek Generating Station Monthly Operating Report August 1991 Page 4 of 5
^
Attachment to NO 91-0241 4
WOLF CREEK NUCLEAR OPERATIlG 00RPORATIOt1 -
WJ12 CREEK GPdERATIlU STATIOt1
- UN1" 10. 1 FOmi Aucmst, 1991 SINMARY OF OPERATIIG EXPERIDCE Tdsted below in chronological sequence is a sununry of operating experiences for tMs tranth Meh required load reduction or resulted in significant non-load related incidents.
ggg TIME EVINP August 1, 1991 0000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> Unit at 100% power.
August 18, 1991 0700 hours0.0081 days <br />0.194 hours <br />0.00116 weeks <br />2.6635e-4 months <br /> Ccncenced unit coastdown to Refuel V.
August 31, 1991 2400 hours0.0278 days <br />0.667 hours <br />0.00397 weeks <br />9.132e-4 months <br /> Unit at 89% Lwer.
Wolf Creek Generating Station Monthly Operating Report August 1991 Page 5 of 5
,