Application for Amend to License DPR-50,revising Tech Specs to Comply More Fully W/Manufacturer Recommendations for Operation of Carbon Dioxide Fire Suppression Sys
ML20082P886
Person / Time
Site: Crane Constellation icon.png
Issue date: 12/01/1983
From: Hukill H
GENERAL PUBLIC UTILITIES CORP.
To:
Shared Package
ML20082P872 List:
References
NUDOCS 8312090223
Download: ML20082P886 (4)


Text

.

FETROPOLITAN EDISON COMPANY JERSEY CENTRAL POWER & LIGHT COMPANY AND PENNSYLVANIA ELECTRIC COPANY TFREE MILE ISLAND N'JCLEAR STATION, UNIT 1 Operating License No. DPR-50 Docket No. 50-289 Technical Specification Change Request No. 97 Rev. 1 This Technical Specification Change Request is submitted in support of Licensee's request to change Appendix A to Operating License No. DPR-50 for Three Mile ~ Island Nuclear Station, Unit 1.

As a part of this request,

~

proposed replacement pages for Appendix A are also included.

GPU NUCLEAR CORPORATION By h

Director, TMI-l Sworn and subscribed to before me this 1st day of December, 1983.

s

. ~

Notary PuOlic

- JuuA s. paar, % %

M'** IhneNn Comney, A l

"Y ^

toku se v. a, was 8312090223 831201 PDR ADOCK 05000289 P

PDR

UNITED STATES OF A ERICA NUCLEAR REGULATORY COMMISSION IN TE MATTER OF DOCKET NO. 50-289 LICENSE NO. OPR-50 GPU NUCLEAR CORPORATION This is to certify that a copy of Technical Specification Change Request No. 97 Rev. 1 to Appendix A of the Operating License for Three Mile Island Nuclear Station Unit 1, has, on the date given below, been filed with the U.S. Nuclear Regulatory Commission and been served on the chief executives of Londonderry Township, Dauphin County, Pennsylvania; Dauphin County, Pennsylvania; and the Pennsylvania Department of Environmental Resources, Bureau of Radiation Protection, by deposit in the United States mail, addressed as follows:

Mr. Jay H. Kopp, Chairman Mr. John E. Minnich, Chairman Board of Supervisors of Board of County Commissioners Londonderry Tnwnship of Dauphin County R. D. #1, Geyers Church Road Dauphin County Courthouse Middletown, PA 17057 Harrisburg, PA 17120 Mr. Thomas Gerusky, Director Penna. Dept. of Environmental Resources Bureau of Radiation Protection P.O. Box 2063 Harrisburg, PA 17120 GPU NUCLEAR CORPORATION BY k

> 1)irector,' iMI-l DATED: Decmber 1, 1983

Three Mile Island Nuclear Station, Unit 1 Operating License No. DPR-50 Docket No. 50-289 7

I.

Technical Specification Change Recuest No. 97 Revision 1 The licensee requests that the attached revised pages replace pages 3-86, 3-87. 3-87a, 3-89, 3-90, 3-91, 3-92, _ 3-93, 3-94, 4-72, 4-75, and 4-76a of the existing Technical Specifications.

II.

Rearons for Change Recuest This change was requested by the NRC in their letter of September 19, 1980, and supersedes TCCR Nos. 83 and 96.

Operational experience (see LER 83-013/03L-0) has prompted a request to revise Technical Specification 4.18.1 to have it more fully comply with the manufacturers recommendations for operation of the CO2 fire suppression system.

As a result of an additional fire hazards analysis, prompted by the issuance of Appendix R to 10 CFR 50, there have been modifications made to the fire detection system in the screen house.

In addition, a determination was made that a manual deluge spray system is preferable to the automatic system described in the original TSCR No. 97 for the auxiliary building containment penetration area, elevation 281'0".

The above changes have been appropriately incorporated in Revision 1 to TSCR No. 9_7.

(See also GPUN letter 5211-83-095 dated 4/8/83).

III. Safety Evaluation Justifying Change These modifications do not compromise any of the fire protection specifications and they comply with the model Technical Specifications supplied in the above referenced NRC letter.

These modifications do not comprornise safety since this change adds administrative controls on fire detection and suppression systems, thus further ensuring the operability of the fire equipment currently installed.

IV.

Sionificant Hazards Considerations Evaluation The Technical Specification changes mandated by the license amencnent 44 modifications (original TSCR No. 97) the changer in Revision 1 to TSCR No. 97 which incorporate some Appendix R modifications and operating experience do not; a) involve an increase in the Drobability of occurrence or the consequences of an accident previously evaluated since this change adds administrative controls on fire cetection and suppression systems, thus further ensuring the operability of the fire equipment currently installed; or

b) create the pcssibility for an accident or ralf uncticn of a new or different kind of accident from any accicent previcusly evaluated since the previously installed automatic suppression system for the auxiliary building containrent penetration area at elevation 281'-0" has been made a manual deluge spray system, thereby minimizing the potential for inadvertent water spray in tne area; or c) involve a reouction in the margin of safety since as stated above, additional controls are proposed to further ensure the operability of the fire detection and suppression systems at TMI-1.

V.

Amendment Class (10 TR 17]3 This change is an NRC requested change and as ruch does not require the payment of a fee. This revision does not substantially broaden the scope of TSCR No. 97 and should not require any additional fee, particularly since TSCR No. 97 has not been acted upon by the NRC staff since its submittal on January 26, 1981.

e VI.

Implementation Period In order to finalize the necessary procedures and to train operators and support personnel, an implementation period of 60 days from the date of receipt of the applicable amendment is requested.