ML20082P667

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept,Item M-96 Re Indeterminate Qualification of Cooperheat Per ASME Section Iii.Hj Kaiser Co QA Dept in Process of Performing Evaluation of Purchase Orders Re Acceptability.Final Rept by 840601
ML20082P667
Person / Time
Site: Zimmer
Issue date: 11/29/1983
From: Williams J
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, LOZ-83-0230, LOZ-83-230, M-96, NUDOCS 8312090129
Download: ML20082P667 (2)


Text

-. -. - . . . .

m, 4 .,

%siv8L .

THE CINCINNATI GAS & ELECTRIC COMPANY CINCINNATI,OHto 4 520t November 29, 1983 ,

LOZ-83-0230  ;

J. WILU AMS. JM "

esmion voce passeormt

nucLaam omanations Docket No. 50-358 .

U.S. Nuclear Regulatoafy Commission

.i Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 i

Attention: 'Mr. J.G. Keppler Regional' Administrator Gentlemen:

RE: WM. H..ZIMMER NUCLEAR ~ POWER STATION - UNIT 1 10CFR50.55 (e) , ITEM M-96, INDETERMINATE QUALIFICATION OF SUPPLIER PER ASME SECTION III W.O. 57300, JOB E-5590, FILE NO. 956C, M-96 This letter constitutes an interim report concerning the subject condition reported to the Commission on September 2, 1983, as a potentially reportable deficiency under 10CFR50.55 (e) . "

Our last report, LOZ-83-0167, was submitted on September 30,

1983.

i The audit of Cooperheat by H.J. Kaiser Company has been

completed. The results of this audit have determined that Cooperheat implemented a quality assurance program in September 1982. All purchase orders issued to Cooperheat were dated prior to September, 1982.

H.J. Kaiser's Qu'ality-Assurance Department is in the process of performing an evaluation of the purchase orders to determine the_ acceptability of items procured from Cooperheat. A report detailing the results of this evaluation and any identified

!' corrective action will.be submitted by June 1, 1984.

l' k

i 83120901P.9 831129 PDR ADOCK 05000358 S PDR ,9, ip 9 Wl

. _. - .- --- . e. .

.. 2.-

Mr. J.G. Keppler Regional Administrator

-November 29, 1983 LOZ-83-0230

< Page 2 We trust the above will be found acceptable as an interim report under 10CFR50.55 (e) .

Very truly yours, THE CINCINNhTI GAS & ELECTRIC COMPANY

By .

AMS, R.

SENIOR VICE RESIDENT DJS/sfr cc: NRC Office of Inspection & Enforcement Washington, D.C. 20555 NRC Resident Site Supervisor ATTN: W.M. Hill NRC Zimmdr Project Inspector, Region III ATTN: E. R. Schweibinz i