Interim Deficiency Rept,Item M-101 Re Itt Hydromotor Actuator Oil Seal Leakage.Initially Reported on 831102. Corrective Actions Will Proceed Under 831005 Program.Item Not Reportable Under 10CFR50.55(e)
ML20082P555
Person / Time
Site: Zimmer
Issue date: 11/30/1983
From: Williams J
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, LOZ-83-0229, LOZ-83-229, M-101, NUDOCS 8312090063
Download: ML20082P555 (2)


Text

n

  • N n

L sg

~

THE CINCINNATI GAS & ELECTRIC COMPANY sE CINCINNATI. OHIO 4 52OI November 30, 1983 LOZ-83-0229 J. WILLIAMS, Jpq SENIOR VICE PRESIDENT NWCLEAR OPERATIONS Docket No. 50-358 U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention:

Mr. J.G. Keppler Regional Administrator Gentlemen:

RE:

WM. H. ZIMMER NUCLEAR POWER STATION - UNIT 1 10CFR50.55(e), ITEM M-101; ITT HYDROMOTOR ACTUATOR OIL SEAL LEAKAGE W.O. 57300, JOB E-5590, FILE NO. 956C, M-101 This letter is in regard to the subject condition initially reported to the Commission on November 2, 1983 as a potentially reportable deficiency under 10CFR50.55 (e).

This item is the result of a review of an unresolved CG&E nonconformance report, 81-65-E of 5/6/81, documenting this condition, along with a

. review of correspondence in the 50.55(e) M-14 file concerning HVAC damper actuator deficiencies which was originally identified to CGEE in April 1980, by NRC IE Bulletin 80-09.

CG&E has determined that this condition does not represent a reportable condition under 10CTR50.55(e) since the plant's preventative maintenance program should preclude oil leakage to

'the' point of-failure.

Nevertheless, the following corrective

' actions will be taken to correct the damper actuator deficiencies reported under Item M-14 and including the oil leakage problem:

.l.- Remove the top-and yoke assembly covers and inspect all 110 damper actuators for oil leakage.

2.

On a scheduled basis, remove from service and disassemble those actuators indicating oil leakage and determine probable cause.

3.

Correct any actuator shaft and/or damper linkage misalignment.

4.

Resolve all other damper actuator deficiencies.

yhk 8312090063 831130 PDR ADOCK 05000358

'5 g

S PDR

...-3 Mr. J.G. Keppler Regional Administrator November 30, 1983 LOZ-83-0229' Page 2 L

Corrective work will proceed under the program described in 1

the Course of Action submitted to the NRC on October 5, 1983.

The resolution of the subject condition, as outlined above, will be included in the final report for 50.55(e) M-14 (HVAC Damper Actuator. Deficiencies).

We trust the above will be found to be an acceptable f

resolution of this matter.

[

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY r

By jA

w1LLlams, ENIOR VICE P ESIDENT BLT/sfr cc:

NRC Office of Inspection & Enforcement Washington, D.C.

20555 NRC Resident Site Supervisor ATTN:

W.M. Hill NRC Zimmer Project Inspector, Region III ATTN:

E. R. Schweibinz i