Advises That Restart Can Occur Approx 2 Wks Following NRC Approval or 840115,whichever Is Later.Preparations Complete, W/Listed Exceptions
ML20082N048
Person / Time
Site: Crane Constellation icon.png
Issue date: 12/01/1983
From: Hukill H
GENERAL PUBLIC UTILITIES CORP.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
5211-83-354, NUDOCS 8312060364
Download: ML20082N048 (2)


Text

1 4

GPU Nuclear Corporation NggIgf Post Office Box 480 Route 441 South Middletown, Pennsylvania 17057-0191 717 944 7621 TELEX 84 2386 Writer's Direct Dial Number:

Decembe-1, 1983 5211-83-354 Office of Nuclear Reactor Regulation Attn:

D. G. Eisenhut Division of Licensing U. S. Nuclear Regulatcry Commission Washington, D.C.

20555

Dear Sir:

Three Mile Island Nuclear Station, Unit 1 (TMI-1)

Operating License No. DPR-50 Docket No. 50-289 TMI-l Restart Schedule On June 10, 1983, we provided a Restart !!ilestone Schedule.

In our letter (5211-83-182) we noted that we would keep the NRC appraised of any signifi-cant changes in our schedule via discussions with the TMI-1 NRC Project Manager.

Preparations for restart are now essentially complete.

The only remaining milestones for restart are the final heatup and testing (7 days), followed by criticality and Zero Power Physics Testing (10 dayi and the Power Escalations Test Program (65 days). These milestones, of course, cannot begin until permission for restart has been obtained, any remaining restart items are completed end the necessary final surveillances/

system lineups are made.

A Management Review Meeting for the final heatup is scheduled for December 16, 1983. We currently expect that by that time the remaining plant modifi-cations and administrative items will be completed or can be handled by subsequent signoff and verification by specified management. We anticipate that our review on December 16 will shcw that any items not then complete can be completed before the end of December.

Assuming that approval for restart were to be given by December 23, 1983, final preparations for heatup (i.e. complete surveillance, complete valve /

system lineup, etc.) will require about 2 weeks to complete. We believe this could be done in parallel with resolving the final few restart items that extend beyond December 16, 1983. The plant could then be ready for final heatup and testing prior to criticality by the first week in January.

Our schedule for this te. sting would then lead to being ready to go critical about January 15th.

8312060364 G31201 PDR ADOCK 05000289

/\\/

P PDR l

O GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation

e Mr. D. G. Eisenhut 5211-83-354 i

In summary, restart can occur about 2 weeks following NRC approval, or January 15, 1984 whichever is later.

.To further reduce the calendar time to criticality (or alternately to minimize the impact of a potential further deferral of restart approval) we are currently comtemplating a request for permission to perform non-nuclear hot testing in advance of final approval for plant startup. We believe NRC could grant such a request on the same basis that permission to do non-nuclear hot testing of the steam generators was granted on August 25, 1983.

We will keep you informed of our plans in this regard via discussions with the TMI-1 NRC Project Manager.

i Sincerely,

/

Director, DfI-l HDH:CWS:vj f cc: