Submits Monthly Status Completion Rept.Fuel Load Date for Unit 1 Is Jan 1986.Const on Unit 2 Abandoned in Dec 1981.At End of Sept 1983,const Progress Approx 76.28% Complete
ML20081M207
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/28/1983
From: Landrieu P H
Public Service Enterprise Group
To: Mccabe E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
M-P82-81-20, NUDOCS 8311170140
Download: ML20081M207 (1)


Text

lI Public Serdce O')# Electric and Gas Company 80 Park Plaza, Newark, NJ 07101/ 201430-7000 MAILING ADDRESS / P.O. Box 570, Newark, NJ 07101 October 28, 1983 Mr. Ebe C. McCabe Chief-Reactor Projects-Section 1D U.S. Nuclear Regulatory Commission Division of Project and Resident Programs Region I 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. McCabe:

HOPE CREEK GENERATING STATION DOCKET NO. 50-354 LICENSE NO. CPPR-120 MONTHLY STATUS COMPLETION REPORT The fuel load date for Unit No. 1 is January 1986. Unit 2 construction was abandoned in December 1981.

At the end of September 1983 construction progress of the unit was approximately 76.23 percent complete.

Very truly yours,

. W P. R. H. Landrieu Project Manager - Hope Creek Engineering and Construction JSW:gs M P82 81/20 8311170140 831028 PDR ADOCK 05000354 R PDR The Energy People f,d f0 ""*