Responds to 810529 Request for Const Schedule Quarterly Update.Target Date for Fuel Load Remains 860103,w/commercial Operation Scheduled for 861101.Unit 2 Canceled on 831014 Based on Unit 1 Electrical Sales Projections
ML20081D528
Person / Time
Site: Clinton Constellation icon.png
Issue date: 10/27/1983
From: Hall D
ILLINOIS POWER CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
0982-L, 982-L, NUDOCS 8311010228
Download: ML20081D528 (1)


Text

.l 090 ~L lLLINO/S POWER OOMPANY IP CLINTON POER STATION. P.O. BOX 678. CLINTON. ILLINOIS 61727 October 27, 1983

'\\

Docket 50-461 Mr. Harold R. Denton., Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Subject:

Clinton Unit I Construction Schedule Update

Reference:

USNRC letter dated 5/29/81, H. R. Denton to W. J. Kelley, Illinois Power Company

~

Dear Mr. Denton:

The referenced letter requested Illinois' Power Company (IP) to provide a quarterly update concerning the Clinton Unit I construction schedule.

As of September 30, 1983, the target date for Unit I fuel load remains at January 3, 1986, with commercial operation scheduled for November 1, 1986.

On October 14, 1983 IP officially, announced the cancella-tion of Clinton Unit 2.

The decision was based on electrical sales projections indicating that after^Clinton Unit I is com-pleted no additional generating units will be needed until the 1990s.

m We will continue to submit quarterly updates of the Unit I construction schedule.

re

yours, t

D.

Hals Vice President ~

RPR/j t

\\