Requests That Completion Date of Emergency Operations Facility Be Extended from 850201 to 850628,per 830415 & 0824 Ltrs & NUREG-0737,Suppl 1.Completion Date Does Not Cover Safety Parameter Display Sys Installation
ML20080U471
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 02/29/1984
From: Bayne J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Vassallo D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 JPN-84-15, NUDOCS 8403020327
Download: ML20080U471 (2)


Text

l '3 M4n Street Wtee f%ns. New w;rk 10601 m

914 081 C200 j

  1. > NewYorkPower t=::=_

4# Authority

-o-February 29, 1984 UPN-84-15 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Mr. Domenic B.

Vassallo, Chief Operating Reactors Branch No. 2 Division of Licensing

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Supplement No. 1 to NUREG-0737 Schedule for Completion of the Emergency Operations Facility (EOF)

References:

1.

PASNY letter, J.

P. Bayne to D.

B. Vassallo, dated April 15, 1983 (JPN-83-33).

2.

NYPA letter, J.

P.

Bayne to D.

B. Vassallo, dated August 24, 1983 (JPN-83-77).

Dear Sir:

The Power Authority submitted, via Reference 1, a description of a new proposed Emergency Operations Facility (EOF) for the FitzPatrick plant.

In Reference 2, the Authority confirmed our intention to build the new EOF and stated that the scheduled completion date was February 1, 1985.

To date, the Authority has completed the purchase of land from Oswego County.

The conceptual design of the EOF has been finalized, and the design specification for construction of the building is nearly complete.

Based on the time required for bidding, contract award and mobilization, the Authority expects to break ground in June of 1984 and begin to erect the building in August of 1984.

This would allow only six months to complete construction, finish the interior, install the necessary equipment and put the EOF into service.

h DR F

1

v

/

. The Authority-will continue to attempt to complete the EOF by February _.1, 1985.

However, even if construction delays, which can reasonably be expected, do not occur, this schedule for completion of the EOF is unrealistic.

Therefore, the Authority requests-that the date for completion of the EOF be extended from February 1, 1985 to June 28, 1985.

The Authority has a functional interim EOF.

This facility was previously described in Reference 1.

We plan to continue using this interim facility until the new EOF is complete and opera-tional.

The June 28, 1985 date is applicable to'the EOF only and does not include the installation (in the EOF) of the

' Plant Safety Parameter Display Systen (SPDS) and Regulatory Guide-1.97 instrumentation.

These items have been addressed separately, and~ individual completion dates given, in LReferences 1 and.2.-

If you have any questions or require additional information

- regarding our schedules, please contact Mr. J. A. Gray, Jr.

of my staff.

Very truly yours, e*h^

a xecutive Vice President

~ Nuclear Generation State.of New York

. County of Westchester Subscribed and Sworn to before me this J7 day of -Jduum/ 1984.

M/RN LA LUHA NOTA'tY PU?uC, STATE OF NEW YORK

\\

40. 60 45143C5

\\

QUAUFIED IN WESTCHESTER COUNTY TERM EXPIRES MARCH 30tli 19.87....

. Notary Public cc:

ffice of the Resident Inspector U. S. Nuclear Regulatory Commission.

P. O. Box 136 Lycoming, New-York 13093 in