Proposes Schedule for Balance of Safety Review Questions to Support 840221 Draft SER Date.Responses Could Be Transmitted to NRC by 840110 If Questions Finalized by 831111.Two Major FSAR Chapters Still Under NRC Review
ML20080T304
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/13/1983
From: Mittl R
Public Service Enterprise Group
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 8310200239
Download: ML20080T304 (2)


Text

t

~

s.

  • s s Pubhc Smice I .'

O PS G Compar*y Electric and Gas 80 Park Plaza, Newark, NJ 07101/ 201430-8117 n',

MAILING ADDRESS / P.CT. Box 570, Newark, NJ 07101

~

Robert L. Mitti General Manager ,

Nuclear Assurance and Recu!ation s

's Aw October 13, 19831 h%

?

Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, MD 20014 Attention: Mr. Albert Schwencer, Chief Licensing Branch 2 Division of Licensing Gentlemen:

> HOPE CREEK GENERATING STATION

/ DOCKET NO. 50-354 s

TECHNICAL QUESTION SCHEDULE 1

Your letters dated August 4, 1983 and August 10, 1983 (A. Schwencer, URO to R. L. Mittl, PSE&G) indicated that PSE&G would roceive all 5 plests for additional information generated by your safety review by the end of August 1983D Although the bulk of the safety review questions have been received in accordance with the August date, two major FSAR Chapters are still under your review. As of this date we have not received technical safety review questions on Chapter 7, " Instrumentation end Controls", and Chapter 8, " Electric Power". -

In order to support the February 21, 1984 draft SER date, we would like to propose the following schedule for the balance of the safety' review questions, particularly the Chapter 7 and 8 requests. If PSE&G were to receive the initial safety review questions on Chapters 7 and 8 by ,

late October,1983; we could meet with the NRC staff reviewers to discuss the questions within two weeks of receipt of the review requests. If ,

these [ safety review questions are then finalized by November 11, 1983, PSE&G could have the responses transmitted to the NRC by January 10, 1984 (60 days). ,

+

1 B310200239 031013 ,'

PDR ADOCK 05000354 E PDR

. I O The Energy People - s 3 3

\ & } k t

-- ____________________________________s i  !'

-*^ . co

. s

--U.S. Nuclear Regulatory Commission 10/13/83 (The actual amendment reflecting the responses would follow within 3 weeks.) This schedule would aid in maintaining the February 21, 1984 draft SER date.

.Should you have any questions on our proposal, do not hesitate to contact us.

Very truly yours, kJ //l BAP: sal

'CC Mr. D. H. Wagner U.S. NRC Licensing Project Manager