Forwards Response to 830916 Request for Most Realistic Schedule for Inservice Insp & Testing Items Requiring NRC Approval for Fifth Refueling Outage.Approval of Proposed Changes & SER Rev by 840101 Requested
ML20080S223
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 10/11/1983
From: Clayton F
ALABAMA POWER CO.
To: Varga S
Office of Nuclear Reactor Regulation
References
TAC-49547, TAC-52015, NUDOCS 8310180308
Download: ML20080S223 (3)


Text

i Memng Address e

Alabama Power Company 600 North 18th Street Post Offica Box 2641 Birmingham, Alabama 35291 Telephone 205 783-6081 F. L. C:eyton, Jr.

Senior Wce President Maballia NWer Flintndge Building Docket NO. 50-348 me sournem e*ctre system October 11, 1983 Director, Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention:

Mr. S. A. Varga Joseph M. Farley Nuclear Plant - Unit 1 ISI and IST Requirements for the hfth Refueling Outage Centlemen:

Your letter of September 16, 1983 requested t!st Alabama Power Company provide the most realistic schedule for the Inservice Inspection (ISI) and Testing (IST) items requiring NRC approval for the Farley Nuclear Plant Unit 1 fifth refueling outage. In response to this request, the attached describes each item, lises milestone dates and discusses impact upon the outage if NRC approval is not received. Details, including bases for the proposed changes, are described in Alabama Power Company submittals dated January 28, July 5, and September 27, 1983. These items, with one exception, have been previously approved or are not applicable to Unit 2.

Alabama Power Company respectfully requests that the NRC approve the proposed changes and revise the Unit 1 SER by January 1, 1984. The fifth refueling outage is scheduled to begin in the January / February, 1984 timeframe. This schedule would allow less than four weeks for procedural changes, outage planning and scheduling revisions.

Should any additional information be needed in support of your review, please advise.

Yours truly, f

a/

L. C2ayton, STB:kc/D-302 Attachment cc:

Mr. R. A. Thomas Mr. G. F. Trowbridge Mr. J. P. O'Reilly E

j Mr. E. A. Reeves

j Mr. W. H. Bradford 8310180308 831011 DR ADOCK 05000348 PDR

ATTACIDGENT Pcg2 1 cf 2 UNIT 1 ISI/IST ITEMS REQUIRING MC APPROVAL FOR THE FIFTH REFUELING OUTAGE SUBMITTED CURRENT UNIT 2 DATE WHEN ISI/IST OPEN ITEMS BY REQUESTED APPROVAL PLANT IMPACT cop 9 TENTS APCO NRC APPROVAL STATUS OCCURS DATE INSERVICE TESTING (IST) 1.

Encapsulated Valve 7/5/83 1/1/84 Approved 1/1/84 If relief for Unit I is not granted, Position Indication (Att. 1, (9/1/83 Previ 9/16/83 encapsulation covers will have to Verification Item 2) ous Requested lbe removed for valve position Date)

Iverification during the 5th refuel-

,ing outage.

2.

RWST Check Valve Stroke 7/5/83 1/1/84 Approved 1/1/84 NRC's latter of May 2, 1983 has Test - Submittal of (Att. 1, (9/1/83 Previ-9/16/83 granted limited relief but requested Additional Information Item 3) ous Requested additional fnformation by the start Date) of the fifth refueling outage. APCO will be evaluating alternatives during the fifth refueling outage.

By letter of 7/5/83, APCO requested that information be sumbitted prior to the end of the sixth refueling outage.

3.

Accumulator Discharge 7/5/83 1/1/84 Approved 1/1/84 NRC's letter of May 2, 1983 has Check Valve Stroke (Att. 1, (9/1/83 Previ-9/16/83 granted limited relief but requested Test - Submittal of Item 4) ous Requested additional information by the start Additional Information Date) of the fifth refueling outage. APCO will be evaluating alternatives during the fifth refueling outage.

By letter of 7/5/83, APCO requested that information be sumbitted prior to the end of the sixth refueling outage.

UNIT 1 ISI/IST ITEMS REQUIRING IEC APPROVAL Pcg2 2 ef 2 FOR THE FIFTH REFUELING OUTAGE Str3MITTED CURREBrf UNIT 2 DATE WHEN ISI/IST OPEN ITEMS BY REQUESTED APPROVAL PLANT IMPACT COIGEENTS APCO NRC APPROVAL STATUS OCCURS DATE 4.

Accumulator Discharge 7/5/83 1/1/84 N/A 1/1/84 Limited relief for deferral of test-Check Valve Test (Att. 1, (9/1/83 Previ-ing has already been granted ar dis-Deferral Item 5) ous Requested cussed in Item 3 above. These valves Date) were included, due to editorial error, in the NRC SER summary list.

5.

Pressure Isolation 7/5/83 1/1/84 Review 1/1/84 If the NRC's SER is not revised to Valves (Att. 1, Requested require testing of the 16 pressure Item 6) 9/27/83 isolation valves identified by 9/27/83 APCO's 7/5/83 and 9/27/83 letters, 19 additional valvcs must be tested during the fifth refueling outage.

6.

Instrument Air Check 7/5/83 1/1/84 N/A 1/1/84 This requirement to verify valve Valve Position (Att. 1, (9/1/83 Previ-Due to position cannot be complied with, Verification Item 7) ous Requested Difference since there is no method to Date) in Design physically verify valve position during normal operation.

7.

Diesel Generator 7/5/83 1/1/84 Relief 1/1/84 Failure to revise the NRC's SER to Check Valve Tests (Att. 1, (9/1/83 Previ-Granted allow this test to be conducted in Item 8) ous Requested 4/8/83 accordance with commitments made in Date)

APCO's letter of 6/10/83 will require APCO to conduct burdensome inspections in excess of the commit-ments made related to IE Bulletin 83-03.

It is the laterpretation of APCO that Section 1.3 of the 4/8/83 NRC SER grants requested relief for for Unit 2.

INSERVICE INSPECTIONS (ISI) 1.

Hydro Test Relief 1/28/83 1/1/84 Relief 1/1/84 Certain Code requirements are Requests (9/1/83 Previ-Granted impractical and cannct be complied ous Requested 9/22/83 with unless relief is granted.

Date)