i THE CINCINNATI GAS & ELECTRIC COMPANY 6cTd WE'to', W Eh I
LOZ-83-0173 J. WILLIAMS JR semon wer PAtmock?
Mbt;&EAN OPENATIONS Docket No. 50-358 u
U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 i
Attention:
Mr. J.G. Keppler Regional Administrator Gentlemen RE:
WM. H. ZIMMER NUCLEAR POWER STATION - UNIT 1 10CFR50. 55 (e), ITEM M-45, INDETERMINATE WELDER QUALIFICATIONS W.O.
57300, JOB E-5590, FILE NO. 956C, M-45 This letter constitutes an interim report concerning the subject condition initially reported to the Commission on April 30, 1982.
Our last report, LOZ-83-0066, was submitted June 30, j
1983.
Since our last report, Task II of the Quality Confirmation Program (QCP) has continued to review the Henry J. Kaiser Company (HJK) welder qualifications performed prior to March 15, 1982.
Of the approximately 2500 welders identified by HJK, 2368 welders were eventually certified to weld.
To date, QCP Task II has reviewed approximately 1492 of the 2368 welders' qualification
. records.
Our last report also indicated that a program was being developed to generate a computer data base to assist in the identification and resolution of welder qualification deficiencies.
This program, the Computerized Welding Information
. System (CNIS), is scheduled to be completed by February 15, 1984.
Upon completion of the CWIS, any deficiency identified will be evaluated to determine if it is a reportable deficiency.
A follow-up report will be submitted by March 21, 1984.
8310170485 831010 PDR ADOCK 05000358 S
PDR h
t octi T63%d
Mr. J.G. Keppler Regional Administrator October 10, 1983 LOZ-83-0173 Page 2 We trust the above will be found acceptable as an interim report under 10CFR50.55(e).
Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By
_jz __
LINMS,'J ENIOR VICE PRESIDENT DJS/DLC/sfr cc:
NRC Office of Inspection & Enforcement Washington, D.C.
20555 NRC Resident Site Supervisor ATTN:
W.M. Hill NRC Zimmer Project Inspector, Region III ATTN:
E. R. Schweibinz
-. -. -...