ML20080P872

From kanterella
Jump to navigation Jump to search
Provides Addl Info Requested by NRC Re Plant Unit 1 mid-cycle Outage Plan
ML20080P872
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 02/27/1995
From: Saccomando D
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9503080161
Download: ML20080P872 (2)


Text

7 s

r

'e

/

) 1400 Opus Placa

-JV-(

C 7 Downers Grove, minois 60515 -

EJ

(_/

Febryary'27,J1995

~

U.S.-Nuclear Regulatory Commission Document Control Desk

. ashington, D.C. 20555 j

W

' Attn:

Document Control Desk-

Subject:

Additional Information Regarding Braidwood. Unit 1 Mid-Cycle Outage Plan NRC Docket Number'50-456 o

References:

1)

Teleconference between~ Commonwealth Edison.

, Company and the Nuclear Regulatory Commission dated February 16, 1995, regarding the'Mid-Cycle Inspection Plan for Braidwood Unit 1 Steam Generators l

2)

D.

Saccomando letter to. Nuclear Regulatory Commission dated November 23, 1994, transmitting Braidwood Unit 1 Mid-Cycle Inspection Plan i

3)

R. Assa letter to D.

Farrar dated August 18, t

1994 transmitting the Safety Evaluation for l

Amendment 54 Reference 3 transmitted the Nuclear Regulatory Commission (NRC)'s Safety Evaluation Report (SER) for the Use of Interim Plugging Criteria for Commonwealth Edison Company (Comed)'s Braidwood Unit 1.

In the SER, the Staff required Braidwood Station to perform a i

mid-cycle steam generator tube inspection on Unit 1.

Reference 3 also requested that Braidwood Station submit plans.for assessing the mid-cycle inspection data at least 60 days prior to the planned shutdown.

Reference 2 transmitted Braidwood's plan. The i

referenced teleconference was held to clarify information that was submitted in the November 23rd letter.

The following provides Comed's understanding of that teleconference.

Referring to the November 23, 1994, letter: fg3 441 Insoection Scoce: Braidwood Station intends on donducting 100%

full length inspection of all four steam generators using the bobbin coil.

Probe Wear Standard (Refer to Attachment A, page 2, Draft Generic Letter Section 3.c.4)."...since the last acceptable probe wear l

measurement that were within 5%, required reinspection." Comed intends on changing the 5% to X%.

i Kinla\\bwd\\mideyc1\\1 nMnnnq 9503000161 950227

'~

PDR ADOCK 05000456 0

P PDR

I 9

e NRC Dscd$~ent Control Desk February 27, 1995 Methodoloav for Braidwood Leakaae calculation For End of Cycle distribution, Comed clarified that we would use bobbin coil voltages, apply NDE uncertainty and then do the Monte Carlo for the purpose of leakage calculation.

Methodoloav for Braidwood conditional Probability of Burst Calculation: Comed clarified that Braidwood will use the methodology described in WCAP 14277, "SLB Leak Rate and Tube Burst Probability Analysis Methods for ODSCC at TSP Intersections," January 1995.

Also the Staff and Comed agreed that, " Calculation of leakage and of conditional burst probability to be performed prior to returning the S/Gs to service (mode 4) uses the as found end of midcycle voltage distribution (as opposed to a projected distribution.)"

Proiected Versus Actual Insnections Results:

Braidwood Station will develop projected voltage distributions for all four steam generators for the mid-cycle inspection.

These projections will be compared to the actual inspection results obtained during the mid-cycle inspection. Results of this comparison will bo submitted with Braidwood Station's 90 Day Inspection Report for alm 05.

If you have any questions concerning this information please contact this office.

Sincerely, sv-.O

~%%

v Denise M. Se comando Nuclear Licensing Administrator cc:

D.

Lynch, Senior Project Manager-NRR gx R. Assa, Braidwood Project Manager-NRR(f S. Dupont, Senior Resident Inspector-Braidwood J. Martin, Regional Administrator-RIII Office of Nuclear Safety-IDNS K:nla\\ lwd \\midcycl\\2