February 9,1984 Shippinoport PA 15077-0004 firector of Nuclear Reactor Regulation United States Nuclecr Regulatory Commission Attn: Mr. Steven A. Varga, Chief Operating Reactors Branch No. 1 Division of Licensing Washington, DC 20555
Reference:
Beaver Valley Power Station, Unit No.1 Docket No. 50-334, License No. DPR-66 Inservice Inspection Interval Extension Gentlemen:
This letter is to inform the Nuclear Regulatory Commission of our intention to extend the first Ten-Year Inservice Inspection Interval from September 30, 1986 to July of 1988 in accordance with Section XI, subarticle IWA-2400(a) cf the ASME Boiler and Pressure Vessel Code 1974 Edition through Summer 1975 Addenda.
Subarticle IWA-2400(a) states:
The examinations and pressure tests required by I'.JB, IWC and IWD shall be completed during each ten-year interval of service, hereinafter designated the inspection interval. These inspection ir.tervals represent calendar years after the reactor facility has been placed into commercial service.
The interval may be extended by as much as one year to permit inspections to be concurrent with plant outages.
For plants that are out of service continuously for one year or more, an inspection interval may be extended for an equivalent period.
The extension of this first inspection interval is based on the following:
a.
An extension of the first 40-month interval for approximately ten months to permit inspections to be concurrent with our first refueling and plant modification outage. This added ten months to the ten-year inspection interval extending the program to July of 1987.
b.
An extension of the ten-year inspection interval for a period equal to the first refueling and plant mod 1 fica-tion outage which lasted from November 30, 1979 to November 20, 1980. During this period, Beaver Valley Power Station, Unit No. I was continuously out of service to refuel and perform a piping and support verification required by IE Bulletin 79-14. This added approximately 12 months to the ten-year inspection interval extending the program to July of 1988.
8402220466 840209 0
DR ADOCM 05000334 PDR
'~
B:aysr Valley Power Station, Unit No.1 Docket No. 50-334, License No. DPR-66 Inservice Inspection Interval Extension Page 2 The extension of the first inspection interval to July of 1988 will provide Duquesne Light Company the means to better control personnel radiation exposure and capital costs during forthcoming plant outages.
If you have any questions concerning this subject, please contact my office.
Very trul
- yours, 1
J. J.
arey Vice President, Nuclear cc: Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatory Commission Beaver Valley Power Station Shippingport, PA 15077 U. S. Nuclear Regulatory Commission c/o Document Management Branch Washington, DC 20555 Director, Safety Evaluation & Control Virginia Electric & Power Company P.O. Box 26666 One James River Plaza Richmond, VA 23261 y