ML20080M615

From kanterella
Jump to navigation Jump to search
Submits Monthly Status Rept for Dec 1983.Fuel Load Date for Unit 1 Is Jan 1986.Unit 2 Const Abandoned in Dec 1981.Const Progress Approx 81.14% Complete
ML20080M615
Person / Time
Site: Hope Creek, 05000355  PSEG icon.png
Issue date: 01/03/1984
From: Landrieu P
Public Service Enterprise Group
To: Mccabe E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8402210202
Download: ML20080M615 (1)


Text

_. . _ _ _ _ __________

O PSIEG Public Service Electric and Gas Company 80 Park Plaza Newar k, N.J. 07101 Phone 201/430-7000 January 3, 1984 l

Mr. Ebe C. McCabe Chief-Reactor Projects-Section 1D U.S. Nuclear Regulatory Commission Division of Project and Resident Programs Region I 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. McCabe:

HOPE CREEK GENERATING STATION DOCKET NO. 50-354 LICENSE NO. CPPR-120 MONTHLY STATUS COMPLETION REPORT The fuel load date for Unit No. 1 is January 1986. Unit 2 construction was abandoned in December 1981.

At the end of December 1983 construction progress of the unit was approximately 81.14 percent complete.

Very truly yours, P. R. H. Landrieu Project Manager - Hope Creek Engineering and Conctruction JSW:gs l