Forwards Effluent & Waste Disposal Semiannual Rept for Jul-Dec 1994.Unit 1 Svc Water Monitor Inoperable from 940701-0805.Compensatory Samples Analyzed to Allow Svc Water to Be Released Via Subj Pathway
ML20080M305
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 02/22/1995
From: Pearce L
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20080M307 List:
References
LWP-95-013, LWP-95-13, NUDOCS 9503030179
Download: ML20080M305 (1)


Text

e

~ ~4's Commonwealth Edison

) ; Quad Cities Nuclear Power Station

/

c i

.)

y 22710 206 Avenue North

'\\

~'

Cordova, Ilhnois 61242 9740 N,s._y'/

' Telephone 309/654-2241 LWP-95-013 February 22, 1995 U.S. Nuclear Regulatory Commission t

Document Control Desk Washington, D.C.

20555

SUBJECT:

Quad Cities Station Operating Report NRC Dockets (50-254 and 50-265)

Enclosed is the Radioactive Effluent Report for July through December 1994, for Quad Cities Nuclear Power Station.

The Unit One service water monitor was inoperable from July 1,1994 until August 5. 1994.

Troubleshooting activities were performed throughout this.

period to return it_to service. During this time,. compensatory samples were analyzed to allow service water to be released via this pathway.

A copy of this report will be furnished to the NRC Resident Inspector, e

Sincerely,

[

COMMONWEALTH EDIS0N QUAD CITIES NUCLEAR POWER STATION i

UW j

(. W. Pet e St ion Manager LNP/JGW/pim Enclosure t

I g.w i

-%i, s,

g)

I b

p 9503030179 950222 l

l smORW1395.LWP PDR ADOCK 05000254 R

PDR

.-