Advises That Facility Will Be Physically Ready to Load Fuel in Mar 1984.Litigation Over Diesel Generators Will Probably Be Completed Before Summer 1984
ML20080J655
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 02/08/1984
From: Reveley W
HUNTON & WILLIAMS, LONG ISLAND LIGHTING CO.
To: Brenner L, Ferguson G, Morris P
Atomic Safety and Licensing Board Panel
References
NUDOCS 8402150159
Download: ML20080J655 (1)


Text

8:An tn II U NT O N & WI L LIN5I S 707 EAs? MAIN STREET P. o. Box 1535 wAS HINGTON. D. C.

RICIIMOND. VI HOI.

lui A11:18 24566.000003

,.u o.

Mcw YoR n. NEW Yo R K Los ANocLcs.CAttroRNI A Tet t pwoh r 004-788-8200

'^' " "* ' * * - 8 3 5 9 RAL esGH. NORTH CAROLINA bfblbt, T M L it kr NoR roLK.VIRGINf A TWX - 710 95600t#6(lhG & SEPv;r.~

Knox vt LLt. TE N N ES S E C BRANCH February 8, 1984 Lawrence Brenner, Esq.

Dr. George A.

Ferguson Administrative Judge Administrative Judge Atomic Safety and Licensing School of Engineering I

Board Panel IIcward University U.S.

Nuclear Regulatory 23.00 5th Street, N.W.

Commission Washington, D.C.

20555 Washington, D.C.

20555 Dr. Peter A. Morris Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, D.C.

20555 In the Matter of LONG ISLAND LIGilTING COMPANY

~

(Shoreham Nuclear Power Station, Unit 1)

Docke t. No. 50-322 Gentlemen:

[

LILCO believes that Shoreham will be physically ready to load fuel in March 1984.

It does not now appear, however, that litigation over the diesel generators can be completed before s umme r 19 84, i f then, though LILCO will do all that it can to expedi te the process.

I

~

1 Very truly yours,

7

'w, p //s.un W.

T r Revelef, I

2 l

cc:

All Parties EP ASLB 8402150159 840200 PDR ADOCK 05000322 o