Forwards Response to IE Bulletin 83-05, ASME Nuclear Code Pumps & Spare Parts Mfg by Hayward Tyler Pump Co. Util Plans to Develop Inservice Test Requirements for Each of Affected Pumps,Per ASME Section VI
ML20080J392
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 08/12/1983
From: Oprea G
HOUSTON LIGHTING & POWER CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
REF-SSINS-6820 IEB-83-05, IEB-83-5, ST-HL-AE-985, NUDOCS 8309260344
Download: ML20080J392 (5)


Text

.

The Light  !

cotttPuy ii"""" i.isi i"x & r"-<< it o. is"s ivoo iie s'"". rex"s 77ooi <7ia> 228-92i >

l August 12, 1983 ST-HL-AE-985 File Number: M1.2/G3.3/G2.2/

G12.108

$ k h Mr. John T. Collins AUG l 61983 I Regional Administrator, Region IV Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 a -

j l

Arlington, Texas 76011 _-

Dear Mr. Collins:

South Texas Project Units 1 & 2 Docket Nos. STN 50-498, STN 50-499 Response to IE Bulletin 83-05 Bulletin 83-05, "ASME Nuclear Code Pumps and Spare Parts Manufactured by the Hayward Tyler Pump Company," has been reviewed by Houston Lighting &

Power Company (HL&P). The requirements of the Bulletin have been addressed, and the appropriate actions are being implemented. Those actions being implemented in response to the Bulletin are described in the enclosed attachment.

Our staff time expended to date in preparing a response to the subject Bulletin is ten man-days.

If you should have an Mr. Michael E. Powell at (y questions 713) 877-3281.concerning this matter, please contact Very truly yours,

. .- re .

Executive Vice President MEP/bjc Attachment 8309260344 830012 PDR ADOCK 05000499 l

([ l a

G PDR 5

l

t., .

Ilouston Lighting & Power Company cc: G. W. Oprea, Jr. ST-HL-AE-985 J. H. Goldberg File Number: M1.2/G3.3/G2.2/

J. G. Dewease G12.108 J. D. Parsons Page 2 D. G. Barker M. R. Wisenburg R. A. Frazar J. W. Williams R. J. Maroni J. E. Geiger H. A. Walker S. M. Dew J. T. Collins (NRC)

A. Vietti (NRC)

W. M. Hill, Jr. NRC)

M. D. Schwarz Baker &Botts)

R. Gurdon Gooch Baker & Botts)

J. R. Newman Lowenstein, Newman, Reis, & Axelrad)

STP RMS Director, Office of Inspection & Enforcement Nuclear Regulatory Commission Washington, D. C. 20555 G. W. Muench/R. L. Range Charles Bechhoefer, Esquire Central Power & Light Company Chairman, Atomic Safety & Licensing Board P. O. Box 2121 U. S. Nuclear Regulatory Consnission Corpus Christi, Texas 78403 Washington, C. C. 20555 H. L. Peterson/G. Pokorny Dr. James C. Lamb, III City of Austin 313 Woodhaven Road P. O. Box 1088 Chapel Hill, North Carolina 27514 Austin, Texas 78767 J. B. Poston/A. vonRosenberg Mr. Ernest E. Hill City Public Service Board Lawrence Livermore Laboratory P. O. Box 1771 University of California San Antonio, Texas 78296 P. O. Box 808, L-46 Livermore, California 94550 Brian E. Berwick, Esquire William S. Jordan, III Assistant Attorney Ceneral Harmon & Weiss for the State of Texas 1725 I Street, N. W.

P. O. Box 12548 Suite 506 Capitol Station Washington, D. C. 20006 Austin, Texas 78711 Lanny Sinkin Citizens for Equitable Utilities, Inc.

Citizens Concerned About Nuclear Power c/o Ms. Peggy Buchorn 5106 Casa Oro Route 1, Box 1684 San Antonio, Texas 78233 Brazoria, Texas 77422 Robert G. Perlis, Esquire Hearing Attorney Office of the Executive Legal. Director U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Revision Date 07-05-83

r- '

O

. b- Attachment ST-HL-AE-985 Page 1 of 2 South Texas Project Units 1 & 2 Response to IE Bulletin 83-05 Item 1 a) Houston Lighting & Power Company (HL&P) has reviewed all ASME Code pumps manufactured by the Hayward Tyler Pump Company (HTPC). A list of the affected pumps and their service application follows:

Quantity Service Application 2/ unit Reactor Makeup Water pumps 3/ unit Electrical Auxiliary Building chilled water pumps

  • 3/ unit Essential Cooling Water screen wash booster pumps 3/ unit Component Cooling Water pumps 3/ unit Essential Cooling Water pumps
  • The EAB chilled water system has been redesigned. Therefore, new pumps will be ordered, and the six pumps (3/ unit) above will not be used on the South Texas Project (STP).

b) HL&P plans to develop inservice test requirements for each of the affected HTPC pumps installed at the STP in accordance with ASME Section XI. The pump inservice tests shall be performed as required based upon the IWP Pump Inservice Test Requirements.

c) A performance test shall be performed on each HTPC pump in accordance with the HTPC " Expanded Commission Tests and Inspections" procedure as submitted with the subject Bulletin.

Included shall be a 48-hour endurance test on all pumps in question at desian pump capacity. The following dates are approximate for preoperational performance testing of the pumps:

Essential Cooling Water: 38 weeks prior to fuel load (including screen wash booster pumps)

Component Cooling Water: 21 weeks prior to fuel load Reactor Make-up Water: 38 weeks prior to fuel load d) An ASME code system Hydrostatic Pressure Test shall be performed in accordance with our Quality Control and Construction Site Pro-cedures. Should Hydrostatic pressure testing of a component not be practical, visual inspection shall be performed at maximum operating pressure. All test results will be made available to the NRC at the STP site. The following dates are approximate for hydrostatic testing of the systems:

Essential Cooling Water: 54 weeks prior to fuel load (including screen wash booster pumps)

Component Cooling Water: 46 weeks prior to fuel load Reactor Make-up Water: 54 weeks prior to fuel load

(.

ST-HL-AE-965 Page 2 of 2 Item 2 To date, HL&P has not ordered any spare parts for the Hayward Tyler ASME code pumps nor have we ordered spare parts from HTPC for other ASME Code pumps.

6

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter 6 9

Houston Lighting & Power 5 Docket Nos. 50-498 Company, et al., 5 50-499 s

South Texas Project i g

Units 1 and 2 AFFIDAVIT G. W. Oprea, Jr. being duly sworn, hereby deposes and says that he is an Executive Vice President of Houston Lighting & Power Company; that he is duly authorized to sign and file with the Nuclear Regulatory Commission the attached Response to NRC IE Bulletin 83-05; that he is familiar with the content thereof; and that the matters set forth therein are true and correct to the best of his knowledge and belief.

,1 /

. W.g%fp'rea,Qr/

Executive Vice President STATE OF TEXAS. 5 6

COUNTY OF HARRIS Q Subscribed and sworn to before me, a Notary Public in and for Harris County, Texas th ,,,, pA day of , 1983.

n Q

[bd. ...f ,#+,,,di w a&

Be1 i ,! c, j Notary Public in and fopthe State of Texas y%,,,w.....',\/

A

, v My commissio gig

(, s 1A'ZG

,