Commonwealth Edison Quad Cities Nuclear Power Station 22710 206 Avenue North
. '
- Cordova, Illinois 61242 y.
Telephone 309/654-2241 ESK-94-099 November 23,1994 U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attn:
Document Control Desk
Subject:
Quad Cities Power Station Units 1 and 2; NRC Docket Number 50-254 and 50-265; NRC Generic Letter 94-02"Long-Term Solutions And Upgrade Of Interim Operating Recommendations For Thermal-liydraulic Instabilities In Boiling Water Reactors" Interim Corrective Actions Response Reference.
Comed Letter dated Septembe. 9,1994; from J.C. Brons, Vice President Nuclear Services to Wm. T. Russell, Directos, Office of Nuclear Reactor Regulation, transmitting the Dresden, La Salle and Quad Cities Stations response to GL 94-02.
Commonwealth Edison's revision to the response to the Generic Letter (GL) transmitted with the referenced letter is as fellows:
In the response for the Generic Letter, the following commitment was made:
- 1) The Training Department "will provide the training for the licensed operators in Session 94-7, to begin i I/7/94 and end on 12/16/94."
'lhe station is wrising the above commitment to end I/15/95 to allow for the completion of the necessary tmining by the Smtion Tndning Department.
If there are any questions or comments concerning this letter, please refer them to Mervin Miller, Regulatory Assurance at (319) 654-2241, extension 3107.
Respectfully, Od. Se E. S. Kraft [)r.
Site Vice President Attachment cc:
J. Martin, Regional Administrator, Rlll R Pulsifer, Project Manager, NRR C. Miller, Senior Resident inspector, Quad Cities 60 9412060320 941123 i
PDR ADOCK 05000254
(