Interim Deficiency Rept on Item E-30 Re Lack of Installation Insp of non-Class IE Cables in Panels.Initially Reported on 821027.Status of Corrective Actions Discussed.Next Rept Will Be Submitted by 830930
ML20080B277
Person / Time
Site: Zimmer
Issue date: 07/28/1983
From: Williams J
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, LOZ-83-0090, LOZ-83-90, NUDOCS 8308050394
Download: ML20080B277 (2)


Text

,

s b

Jeg 4_ -

THE CINCINNATI G AS & ELECTRIC COM PANY dI CINCINN ATI. OHIO 45201 July 28, 1983 LOZ-83-0090 I

J. WILLI AM S, J R SENIOR WCE PRESsOENT NUCLEAR OPERATIONS Docket No. 50-358 U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention:

Mr. J.G. Keppler Regional Administrator Gentlemen:

RE:

WM. H.

ZIMMER NUCLEAR POWER STATION - UNIT 1 10CFR50.55(e), ITEM E-30, LACK OF INSTALLATION INSPECTION OF NON-CLASS lE CABLES IN PANELS W.O.

57300, JOB E-5590, FILE NO. 956C, E-30 This letter constitutes an interim report concerning the subject condition initially reported to the Commission on October 27, 1982 under the requirements of 10CFR50.55(e).

Our previous report, QA-2232, dated January 25, 1983, identified the corrective actions that are being implemented to resolve this item.

The status of each corrective action is discussed below, i

1.)

The Stop Work (82-05) issued on October 12, 1982, suspending the installation and termination of non-l essential and associated cables in Category I l

structures is still in effect.

This order will not be rescinded until items 2 and 3 below are complete.

I l

2.)

Construction and inspection procedures for Cable Pulling, Raceway Installation and Cable Termination have been revised to include inspection criteria for electrical separation.

The procedure for cable termination is also being revised to identify the panels requiring inspection.

We anticipate that this procedure will be approved by July 29, 1983.

3.)

The contractor's construction personnel and QC inspectors will receive training on the construction and inspection procedures and the applicable design documents in accordance with the contractor's QA program.

CG&E's QA personnel will ensure compliance.

I AUG 011983 8308050394 830728 PDR ADOCK 05000350

}Q}

PDR 9

Il0

d L

Mr. J.G.

Keppler Regional Administrator July 2S, 1983 LOZ-83-0090 Page 2 4.)

Procedure NEP-8.5, Rev. O for the review of electrical separation of cables in essential panels was prepared and approved.

The review was initiated on March 3, 1983.

However, the review was halted on May 27, 1983~ to allow procedure revisions and retraining of personnel involved in the walkdown to the revised procedures.

The walkdown was re-initiated on July 6, 1983.

We anticipate completion of this program by August 31, 1983.

A follow-up report will be submitted by September 30, 1983.

We trust the above will be found acceptable as an interim report under 10CFR50.55 (e).

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By M

f

. WILLIAMS, JJ SENIOR VICE PRSSIDENT DJS/sfr cc:

NRC Office of Inspection & Enforcement Washington, D.C.

20555 NRC Senior Resident Inspector ATTN:

W.F.

Christianson NRC Zimmer Project Inspector, Region III ATTN:

E.

R. Schweibinz