- ff Northem States Power Company 414 Nicollet Ma's Menneapots. Minnesota 55401 Teephone i612) 330-5500 January 31, 1984 Director Office of Nuclear Reactor Regulation U S Nuclear Regulatory Commission Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLA!TI Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Generic Implications of Salem ATWS Events (Generic Letter 83-28)
Action 4.1 Reactor Trip System Reliability (Vendor Related Modifications)
Action 4.5 Reactor Trip System Reliability (System Functional Testing)
This letter furnishes the information committed in our November 4, 1983 submittal.
Inspections have now been completed to ensure that all vendor recommended modifications have been effected. The inspection revealed one improper Undervoltage Trip Attachment which was replaced.
Modified procedures have been developed and issued for testing the reactor trip switch gear (test of each manual trio function). The procedures were verified during the recent refueling outage for Unit 1.
D Mw.
David Musolf Manager - Nuclear Suppo Services DMM/ECW/bd c: Regional Administrator-III, NRc NRR Project Manager, NRC Resident Inspector, NRC G Charnoff d 'b R402070011 840131 9