o. ;.
GF ear Corporation U
68r Post Office Box 480 Route 441 South Middletown, Pennsylvania 17057 0191 717 944 7621 TELEX 84 2386 Writer's Direct Dial Number:
February 1, 1984 5211-83-381 Office of Nuclear Reactor Regulations Attn:
D. G. Eisenhut, Director Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Sir:
Three Mile Island Nuclear Station, Unit 1 (TMI-1)
Operating License No. DPR-50 Docket No. 50-289 Required Actions Based on Generic Implications of Salem /ATWS Events (GL 83-28)
The purpose of this letter is to correct several typographicnl errors in our November 8, 1983 letter (5211-83-330).
In our letter we stated the B&W Owners Group Program was submitted to the NRC on 11/5/83 by Arkansas Power and Light (AP&L). The date of the AP&L letter was 11/4/83.
Also, the enclosure -
" Estimated Schedule for GPUN (TMI-1) Activities" contained three incorrect dates. We have identified the corrections with an asterik on the attached revised table.
Sincerely,
- 1. D. h kill Director, TMI-l HDil: PGD:vj f Attachment cc:
R. Conte J. Van Vliet 8402060388 840201 h5 PDR ADOCK 05000289 P
PDR l
t GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation
,g Generic Letter 83-28 Estimated Schedule for GPUN (TMI-1) Activities Estimated Item Description Completion Date 1.1 Implement Ti1I-l Reactor Trip Program 6/30/84 Recommendation into Procedures Implement Training 6/30/84 1.0 Incorporate Data Checklists 6/30/84 into Till-1 Procedures 2.1 Equipment Classification (RTS)
Complete Vendor Interface B&WOG Activity 2.2 Equipment Classification (all Safety -
Complete Related Equipment)
Recommendations Issued on a Component 3/31/84 Quality Classification List Technical Review of all Vendor flanuals 1/3i/87 Review of Itaintenance and Surveillance 1/31/90 Procedures 3.1 Review of GPUN Procedures (RTS)
Complete Revise Procedures (RTS) 2/1/84 Additional Guidelines B&WOG Activity 3.2 Reveiw Program of 11aintenance & Surveillance See 2.2 Procedures Technical Review of all Vendor llanuals Se,e 2.2 Revise Procedures for Review of Operating Experience 4/30/84 4.1 Vendor Recommendations (RTB's)
Ccaplete 4.2 Revise Procedure due to Vendor Recommendation 2/1/84 Reactor Trip Breaker Reliability Program B&WOG Activity 4.3 Install Automatic Actuation of Shur.t Trip 9/30/84 4.4 Revise Procedure for SCR Testing Complete Submit Tech. Spec. Change Request for SCR Testing 1/31/84 4.5 Revise Surveillance Procedure based on B&W Guidelines Complete Revise Surveillance Procedures for the Three Diverse Trip Functions 9/30/84 Program to Justify Online Test Intervals B&WOG Activity