f,~

1-

. O, DUQUESNE LIGIT C:NPANY Beaver Valley Power Station Beaver Valley Imer Station Friewcy Preparedness Plan (Operations Manual Chapter 57)

Volumes I and II Distribution List I

Controlled Copies Number 1 Bnergency Response Facility - Technical Support Center Recipient - n= ant Control Supervisor Nunber 2 BVPS Unit 1 Control Rc m Recipient - Nuclear Operations S' W agor Nunber 3 BVPS Unit 1 Control Rocan

?

Recipient - Nuclear Operations Supervisor Number 4 Alternate EOF - South Heights T & D Building M

Recipient - Radi5 tion Centrol Supervisor Q

Nunber 5 NRC Region I (3 cx: pies)

].

Recipient - NRC Director, King of Prussia, PA Nuuber 6~

"BBC (?tational) ~ fl0 copies) -

w ie-Nnc nirector,:arthesda, e r

Number 7 Onsite Safety Cburittee Meeting Roc:n Recipient - osC Sec e Nunber 8 Dnergency Response Facility - Emergency Cperations Facility g

piph+ - n,,,marit Control Supervisor Number 9 DTrgercy Repsonse Facility - EA & DP Section of EOF y

Recipient - Document Control b W -

.7

..e

.c Number 10 Office of Manager, Nuclear Operations

-)

Recipient - Manager, Itclear Operations b

Number 11 Office of Manager, Nuclear Safety and Licensing q

Recipient - Manager, Naclear Safety and Licensing NCyrE: All controlled copies distributed are to be aWrded by the Records Transmittal for Controlled Copies of EPP Ebrm (Annex X of Volume II).

The person delivering the copy will sign and date the " Person Transmitting

]

Re,w.d5" line, the person receiving the copy will sign and date the " Recipient" line and the Emergency Planning Supervisor and/or designee will sign the

+

?j bottcun line.

S If the controlled copy and L.cusuittal form cannot be hand carried to the recipient, the signed transmittal form nust be mailed back to the BVPS file by sending it to:

.i BVPS Unit 1 i :O P. O. Box 4 f]j V Shippingport, PA 15077 c/o Donna J. Miller, Dnergercy Planning Supervisor i

sa01310115 840120 Pev.12/1/83 i

PDR ADOCK 05 3

F

-~

>--s---

p--

EPP/IP Annex X Annex X.

Page 1 of 1

Duquesne Light Company Beaver Valley Power Station Records Transmittal for Controlled' Copies of EPP Date 12/8/83 Transmittal No.

ER-1 Plea'se' make the appropriate changes per the following filing instructions:

Filina Instructions Remove Insert Manual Section's)

Manual Section(s)

EPP/IP Vol. II I-1, I-2, I-3, I-4, I-5 EPP/IP Vol. lI I-1, I-2, I-3, I-4 IP 1.1, IP 1.2, IP 1.2.1 I-5, IP 1.1 (Interim; IP 1.3, IP 1.4, IP 1.5 IP 1.1, IP 1.2, l

IP 1.6 IP 1.2.1, IP 1.3, IF 3.3 IP 1.4, 1? 1.5, IP 1.4.1 IP 1.6. IP 3.3 IP 1.4.1 I-

\\ (T

  • 2 i

Special Instructions:

Insert IP 1.1 (Interim) in conjunction with IP 1.1.

j Further instructions will follow.

I verify that the records transmitted are in agreement with this transmittal document and are in good condition.

}

(Person Transmitting Records)

(Date)

I verify that the records received are in agreement with this document, indicated new secticns have been inserted in the applicable manual and superceeded sections as indicated have been removed and destroyed.

I (Recipient)

(Date)

(Transmittal Verification)

(Date) i C O NOTE:

Return this form within 15 days to Donne. J. Miller, Emergency Planning Supervisor ISSUE 7 Rev. 2 e