p a-a FOSTER WHEELER ENERGY CORPORATION Energy Applications Dwision B PEACH THEE HILL HoAD. LtVINGSTON, NEW JERSEY 07030
- PHONE 201-635-2354 4
October 7, 1991 Mr. J.
Spraul Nuclear Regulatory Commission Washington D.C.
20555
Subject:
'Further Response to NRC Queries --
Rev. 6 of FWEC/EA QA Manual
Reference:
(1) Telecon J.
Spraul and D.
Lamvermeyer on October 3, 1991 -- Items 4, 8,
11, 16 and
-18 of FWEC/EA ltr. to J.
Spraul from D,
Lamvermeyer dated Feb. 10, 1991 - same subject.
(2) NRC Ltr. from F.W. Brach to D.J.
Lamver-meyer dated January 22, 1991 with enclosure
" Request for additional information".
Dear'Mr.'Spraul:
This. letter is written to document the FWEC/EA responses in reply to further comments made and discussed during the reference (1) telecon.: The-following clarifications will-be added to the FWEC/EA QA Manual-by the next revision'(Revision 7) to implement.
Affected responses'are numbered ~the same as the original NRC request for information -'Ref. (2).
-Item '4
- Para. 2.5.3'will be revised to clarify (1) that the-QA
~
Mgr.. oversees and approves the training plan and schedule for-other personnel not within Quality organization) who perform quality activitie(s and the Mgr. of the "other" personr.el performing quality activ(2)ies is responsible for having-the trai-it ning carried out.
Item 8
- Rereview of Ref. (1) Ltr. response indicates the qua -
'lification' requirements for a' supervisor in order to be eligible-as a Design reviewer require 1) that he has not made a contribution
-to the design approach'or-input and
- 2) that he be the individual
'in the organization competent: to perform-the verification (design-review).
Para. 3.4.2.3 will be clarified to be consistent with these requirements.
/
{
n f Ib l
CG00H p
l 911112O202' 911007 "...
~
AOLE ADDRESS. REWOP PERRYVILLENEWJERSEY F
q]9 C.
L-
~
g.
i r
s W
Item 11
- Provision will be added to Para. 4.5.1 to clarify that the corrective actions required by the conditions of approval for a vendor as stated in the purchase order will be natisfied to assure full approval prior to the start of actual work on tt der.
Item 16
- Provision will be added to clarify that the calibration records required by para. 17.4.3h will include accumulated cali-bration data that will allow assessment / adjustment of equipment /
instrument calibration intervals, as necessary.
Item 18
- Para. 18.6 will be revised to clarify that the profi-ciency of auditor skills will be maintained by continued perfor-mance of audit activities, i.e.,
internal audits, vendor surveys and audits, etc.
The above clarifications will be implemented by June, 1992.
Very truly yours, jf $ f fd.'.hs@A%4iAA DJ L/gd D.